Demolition Permit in Yuma, Arizona

Required for demolition of buildings within Yuma city limits, processed as a building permit under the 2024 IBC (commercial, § 150-015) or 2024 IEBC/IRC (residential, § 150-170/180) as locally amended. The City's own Building Permit Processing Time Frames document lists 'Commercial Demolition' and 'Residential Demolition' as distinct tracked permit activities, billed on the same governing Table 1-A valuation-based building permit fee schedule verified for new construction in this file. A full review of the Yuma City Code Chapter 150 table of contents (American Legal) confirms no separate demolition-specific subchapter, bond ordinance, or fee table exists distinct from § 150-016/171/181.

Verified 2026-07-03 · Source

When you need this permit

  • Demolition permit required before demolishing a building within Yuma city limits, reviewed under the applicable adopted building code (2024 IBC for commercial, 2024 IEBC/IRC for residential); no permit-type-specific demolition ordinance exists — demolition is valued and permitted under the general building-permit provisions
  • Governing fee is the valuation-based Table 1-A schedule (Yuma City Code § 150-016(I) / § 150-171(I) / § 150-181(K)), the same schedule verified for the Residential Building Permit (New Construction) permit type in this file, applied to the demolition's contract valuation
  • Review timeline is governed by the City's A.R.S. § 9-835 Building Permit Processing Time Frames document, which separately tracks 'Commercial Demolition' and 'Residential Demolition' at an 11-business-day overall review time
  • Confirmed via a full read of the Yuma City Code Chapter 150 table of contents (§§ 150-001 through 150-999) that no distinct demolition subchapter, site-bond requirement, or utility-disconnection provision exists separate from the general adopted-code 'work requiring a permit' and permit-fee sections
  • Apply through the Development Portal or in person

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee — valuation-based (governing Table 1-A schedule, same as new construction)Yuma City Code § 150-016(I) / § 150-171(I) / § 150-181(K), Table 1-A — the governing fee schedule; no distinct demolition bond or fee table exists in the amlegal-hosted Yuma City Code
$50.00 minimum ($1-$500 valuation), scaling per Table 1-A (e.g., $110.00 for first $2,000 plus $16 per additional $1,000 up to $25,000)
Other Inspections and FeesYuma City Code § 150-016(I), Table 1-A
$75.00/hour minimum (2-hr minimum after-hours), $150.00/hour weekends/holidays, or total hourly City cost if greater

Review timeline

Plan reviewYuma’s published plan-review target
6–11 business days

How long did your Demolition Permit permit actually take in Yuma?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Site cleared and restored per approved demolition permit prior to close-out

See the full Yuma inspection guide — scheduling & re-inspection fees →

Tips

  • Per the City's Building Permit Processing Time Frames document (A.R.S. § 9-835 compliance document), both 'Commercial Demolition' and 'Residential Demolition' carry an 11-business-day overall review time (1-day admin + 5-day first review) — the same governing timeline source verified for other permit types in this file.
  • No distinct demolition ordinance, site bond requirement, utility-disconnection provision, or dedicated demolition fee table (comparable to what some other cities publish) was located for Yuma; recovery exhausted via direct site fetch (blocked, Akamai 403), Wayback Machine snapshots, WebSearch, and a full read of the amlegal.com Yuma City Code Chapter 150 table of contents (all sections § 150-001 through § 150-999 reviewed — no separate demolition subchapter exists distinct from the general IBC/IEBC/IRC adoption and permit-fee sections). Demolition is billed and reviewed exactly as a building permit under the governing Table 1-A schedule and A.R.S. § 9-835 time-frames document.

Frequently asked questions

Yuma requires a demolition permit for: Demolition permit required before demolishing a building within Yuma city limits, reviewed under the applicable adopted building code (2024 IBC for commercial, 2024 IEBC/IRC for residential); no permit-type-specific demolition ordinance exists — demolition is valued and permitted under the general building-permit provisions; Governing fee is the valuation-based Table 1-A schedule (Yuma City Code § 150-016(I) / § 150-171(I) / § 150-181(K)), the same schedule verified for the Residential Building Permit (New Construction) permit type in this file, applied to the demolition's contract valuation; Review timeline is governed by the City's A.R.S. § 9-835 Building Permit Processing Time Frames document, which separately tracks 'Commercial Demolition' and 'Residential Demolition' at an 11-business-day overall review time; Confirmed via a full read of the Yuma City Code Chapter 150 table of contents (§§ 150-001 through 150-999) that no distinct demolition subchapter, site-bond requirement, or utility-disconnection provision exists separate from the general adopted-code 'work requiring a permit' and permit-fee sections; Apply through the Development Portal or in person. If your project isn't listed, confirm with City of Yuma Department of Community Development, Building Safety Division at (928) 373-5163 before starting work.

In Yuma, the published Building Permit Fee — valuation-based (governing Table 1-A schedule, same as new construction) is: $50.00 minimum ($1-$500 valuation), scaling per Table 1-A (e.g., $110.00 for first $2,000 plus $16 per additional $1,000 up to $25,000). Additional published fees: Other Inspections and Fees — $75.00/hour minimum (2-hr minimum after-hours), $150.00/hour weekends/holidays, or total hourly City cost if greater. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Yuma's published plan-review target for a demolition permit is 6–11 business days.

You'll need: Demolition Permit Application. See the required-documents checklist on this page for details on each.

Yuma requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Yuma Department of Community Development, Building Safety Division ((928) 373-5163).

Apply through City of Yuma Department of Community Development, Building Safety Division at Yuma City Hall, Second Floor, One City Plaza, Yuma, AZ 85364-1436. Phone: (928) 373-5163, email: Inspection@YumaAZ.gov. Office hours: Monday - Thursday 7:00 AM - 5:00 PM; every other Friday 7:00 AM - 5:00 PM; closed on designated City holidays. Inspections: (928) 373-5170 (non-emergency, request by 3 p.m. for next-business-day scheduling); after-hours/emergency inspections (928) 373-5163.. Official information: https://www.yumaaz.gov/government/building-safety.

Yuma, Arizona has adopted: Arizona has no mandatory statewide building code — code adoption is a per-city/county authority under A.R.S. §§ 9-801 et seq. (municipal adoption of technical codes) and City of Yuma Charter Art. VII, § 6(g)(6). The City of Yuma's Department of Community Development, Building Safety Division administers and enforces its own adopted codes within city limits; this is not a county-run or state-run program for the incorporated City of Yuma. Source: Yuma City Code Chapter 150, §§ 150-015, 150-060, 150-045, 150-076, 150-180 (adoption sections, each citing A.R.S. §§ 9-801 et seq. and Charter Art. VII, § 6(g)(6)), codelibrary.amlegal.com/codes/yuma; 2024 International Building Code (IBC), including Appendices C, I, J, K, and O — adopted by City of Yuma Ord. O2025-033, passed 10-1-25 (effective November 3, 2025); Yuma City Code § 150-015; 2024 International Residential Code for One- and Two-Family Dwellings (IRC), including Appendices BB, BF, BG, BH, BJ, BO, CD, and CF — adopted by City of Yuma Ord. O2025-034, passed 9-17-25 (effective November 3, 2025); Yuma City Code § 150-180; 2024 International Existing Building Code (IEBC), including Appendices A, B, and E — adopted by City of Yuma Ord. O2025-035, passed 9-17-25 (effective November 3, 2025); Yuma City Code § 150-170; 2024 International Property Maintenance Code (IPMC) — effective November 3, 2025; Yuma City Code § 150-090; 2024 International Fire Code (IFC), including Appendices B, C, D, E, F, G, H, and I — adopted by reference with local amendments by City of Yuma Ord. O2025-039, passed 10-1-25; Yuma City Code § 131-15 (amendments at § 131-16). Appendices A, J, K, L, M, N and O are expressly NOT adopted (§ 131-16(SS) through (GGG)). The City of Yuma Fire Code is enforced by the Community Risk Reduction Division within the Yuma Fire Department, under the supervision of the Fire Chief and with a Fire Marshal in charge of the division (§ 131-18; IFC § 103.1 as amended at § 131-16(D)) — fire permitting is NOT delegated to an independent fire district. Confirmed live on the City’s own Community Risk Reduction page: “The City of Yuma has adopted the 2024 International Fire Code (IFC) with local amendments.” Sources: codelibrary.amlegal.com/codes/yuma (2026 S-74, read 2026-08-16); yumaaz.gov/government/yuma-fire-department/community-risk-reduction/about-fire-codes-and-ordinances (read in a real browser 2026-08-16).; Per the City of Yuma Building Safety Division page: a transitional period ran through January 31, 2026 during which applicants could choose either the 2018 or 2024 codes; use of the 2024 codes became mandatory for all new permit applications beginning February 1, 2026. Source: yumaaz.gov/government/building-safety; 2018 International Plumbing Code (IPC), including Appendices C and E, made public record by Resolution R2022-018 — adopted by City of Yuma Ord. O2022-008, passed 5-4-22; Yuma City Code § 150-060 (Note: Arizona municipalities may adopt either the UPC or IPC; Yuma has adopted the International Plumbing Code, not the Uniform Plumbing Code); 2018 International Mechanical Code (IMC), made public record by Resolution R2022-019 — adopted by City of Yuma Ord. O2022-009, passed 5-4-22; Yuma City Code § 150-045; 2018 International Fuel Gas Code (IFGC) — adopted by City of Yuma; Yuma City Code § 150-065; NFPA 70 National Electrical Code (NEC), 2020 Edition, and 2006 International Code Council Electrical Code (ICCEC) Administrative Provisions, made public record by Resolution R2022-021 — adopted by City of Yuma Ord. O2022-011, passed 5-4-22; Yuma City Code § 150-076; 2009 International Energy Conservation Code (IECC), made public record by Resolution R2013-09 — adopted by City of Yuma Ord. O2013-15, passed 4-3-13; Yuma City Code § 150-020 (this is the most recent energy-code edition found adopted by ordinance; no more recent IECC adoption ordinance was located as of this review); 2018 International Swimming Pool and Spa Code (ISPSC) — Yuma City Code § 150-018; ICC A117.1 Accessibility — referenced via Yuma City Code § 150-016(T), in conjunction with Arizona Revised Statutes Title 41, Chapter 9, Article 8 (A.R.S. § 41-1492 et seq., The Arizonans with Disabilities Act) and ADAAG; Adobe Building Code (locally authored, not an ICC model code) — Yuma City Code §§ 150-030 through 150-035, covering burnt/unburned adobe masonry construction, electrical, and plumbing requirements specific to adobe structures. Local amendments apply — see the Yuma overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yuma building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.