Inspection sequence, scheduling, and re-inspection fees for building permits in Commerce City, Colorado.

Verified 2026-07-13 · Source

How to schedule

Inspections are requested through the building department below.

Address
South Platte Crossing Building, 7190 Colorado Blvd. Ste 600 (6th Floor), Commerce City, CO 80022
Phone
303-289-3790
Office hours
Monday - Friday, 8:00 a.m. - 5:00 p.m.

Inspection sequence

Applies to: Commercial Building Permit (New Construction / CNEW)

  1. 1

    Special Inspections (per SITA)

    Special inspections and testing per the approved Statement of Special Inspections / SITA; the Special Inspections Final Certification Report must be uploaded to the parent permit and approved before a CO is issued

  2. 2

    Building Safety Stage Inspections

    The permit holder/contractor must notify the city when stages of construction requiring inspection are reached; inspections are scheduled in eTRAKiT with a deadline of 4 p.m. the business day before the desired date. City-approved site plan, building plans and shop drawings must be on the jobsite; ladders/scaffolds must be provided for inspector access. The city does not publish a fixed numbered commercial inspection sequence — required stages are per the C3BC/2021 IBC

  3. 3

    Planning Inspection

    If a planning inspection is required it can take up to five days after the date scheduled (Planning Division: cdplanner@c3gov.com, 303-227-8777)

  4. 4

    Outside-Agency Inspections

    South Adams County Fire Department, Public Works, Adams County Health and South Adams County Water and Sanitation District conduct their own inspections; all applicable agency finals must be approved before a CO

  5. 5

    Final Inspection and Certificate of Occupancy

    After the Building Safety Division final inspection is approved, a new building cannot be occupied until a CO or TCO is issued via a separate Certificate of Occupancy/Completion (CO) permit in eTRAKiT linked to the parent permit; core-and-shell buildings receive a Certificate of Completion instead. Prerequisites include approved deferred submittals, finaled linked permits (fire sprinklers, alarms), UFER certification, Improvement Location Certificate, Energy Compliance Certificate, and elevator Certificate of Operation where applicable

Applies to: Residential Building Permit (New Construction / RNEW)

  1. 1

    Foundation/Footing

    Before concrete pour, per approved foundation plan and 36-inch minimum frost line depth

  2. 2

    Framing

    Structural framing per approved plans; truss shop drawings must be available to the inspector at this stage

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Insulation/Energy

    Insulation and 2021 IECC (Commerce City Residential Energy Conservation Code) compliance before drywall

  5. 5

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    If new construction, before concrete pour

  2. 2

    Framing

    Structural framing, egress windows, fire separation between primary dwelling and ADU where required

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in, including separate heating/ducting for the ADU

  4. 4

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Change of Use / Change of Occupancy

  1. 1

    Zoning Use-Conformance Review

    Community Development confirms, via the Zoning Verification review, that the newly proposed use is allowed within the property's zoning district

  2. 2

    Building Safety Final Inspection(s)

    Required only where CALT construction/alteration work accompanies the change of use

  3. 3

    Outside-Agency Final Inspections

    South Adams County Fire Department, Public Works, Adams County Health, and South Adams County Water and Sanitation District finals, where applicable, must be approved before a CO can be finalized -- per the existing Commercial Building Permit and Commercial Tenant Improvement Permit entries

  4. 4

    Certificate of Occupancy Issuance

    Filed as a CO/TCO/CC/TCC permit in eTRAKiT, linked to the parent permit, once all applicable prerequisites and agency finals are on record

Applies to: Residential Addition / Alteration Permit (RADD / RALT)

  1. 1

    Foundation (if new footings)

    Before concrete pour for new footings, deck posts, or garage foundations

  2. 2

    Framing

    Structural framing and connection to existing structure

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit (Commercial Alteration / CALT)

  1. 1

    Building Safety Stage Inspections

    Scheduled via eTRAKiT by 4 p.m. the business day before the desired date; city-approved plans must be on the jobsite and accessible to the inspector

  2. 2

    Outside-Agency Inspections

    South Adams County Fire Department (fire-protection systems), health department (food establishments) and other applicable agencies inspect separately; all applicable agency finals must be approved before a CO

  3. 3

    Final Inspection and Certificate of Occupancy

    A commercial tenant space cannot be occupied until a CO or TCO is issued after the Building Safety Division final inspection, via a separate CO permit in eTRAKiT linked to the parent CALT permit; linked permits (fire sprinklers, alarms) must be finaled first

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Rough and Hydrostatic Inspection (fire sprinkler)

    Combined rough and hydro inspection before concealment, per SACFD's fee schedule descriptions

  2. 1

    Rough Inspection (fire alarm)

    Wiring and device placement before concealment

  3. 2

    Final Inspection and Test

    SACFD final sign-off and system test; required before Commerce City will finalize a Certificate of Occupancy for the building

Applies to: Electric Vehicle Charging Station Permit

  1. 1

    Rough-In

    Wiring and conduit before walls closed (new circuit/outlet installations)

  2. 2

    Final

    Charger installed, circuit/outlet verified, system energized

Applies to: Electrical Permit (RELEC / CELEC)

  1. 1

    Rough-In

    Wiring and conduit before walls closed

  2. 2

    Final

    Devices installed, panel labeled, system energized; for solar, the Residential Solar Installation Certification must be available onsite

Applies to: Fence and Retaining Wall Permit

  1. 1

    Footing

    For engineered retaining walls, before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans and the Fence and Wall Standards table

Applies to: Mechanical/Gas (HVAC) Permit (RMECH / CMECH)

  1. 1

    Rough-In / Equipment

    Equipment installation and ductwork before concealment

  2. 2

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing/Gas Permit (RPLMB / CPLMB)

  1. 1

    Underground/Rough-In

    Before concealment — pipe slope, materials, cleanouts

  2. 2

    Final

    Fixtures connected, backflow protection verified, no leaks

Re-inspection fees

Commercial Building Permit (New Construction / CNEW)Re-inspection / Re-review Fees · Additional plan review for changes/revisions $75/hr; inspection outside normal business hours $75/hr; reinstating a lapsed commercial permit $640; work without a permit = double permit and plan fees
$75 first re-inspection; $112 second; then doubling. $320 first re-review; $640 second; then doubling
Fire Sprinkler and Fire Alarm System PermitRe-Inspection · South Adams County Fire Department Plan Review, Inspection, and Permit Fee Schedule effective January 1, 2024, Miscellaneous Construction Plan Review and Inspection Fee Schedule, p. 5
$120.00 per hour per inspector (2-hour minimum)

Sources & verification

Verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Commerce City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Commerce City building permits

Get alerts for Commerce City

We'll email you when Commerce City's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.