Solar PV Permit — Commerce City, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.c3gov.com/files/assets/city/v/1/bd-building-safety/documents/forms-amp-publications-library/solar-installation-certificate.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Commerce City, Colorado
Required for installation of rooftop solar photovoltaic systems in Commerce City. A Building Permit and an Electrical Permit are required, billed on the City's standard valuation-based Building Permit Fee Schedule (Table 1-A) — but capped by Colorado's statutory Fair Permit Act limit on solar fees. Commerce City's Building Safety Division also requires a Solar Installation Certificate (a self-certification form, Version 2021.0) to be completed by a state-licensed journeyman or master electrician employed by a Commerce City-licensed electrical contractor and uploaded to the City's eTRAKiT portal after installation.
Verified 2026-07-20 · Source
When you need this permit
- Obtain a Building Permit and an Electrical Permit for a rooftop solar PV installation via the City's eTRAKiT portal
- Solar Installation Certificate (Version 2021.0, City of Commerce City Building Safety Division) must be completed by a state-licensed journeyman or master electrician employed by a Commerce City-licensed electrical contractor, certifying code-compliant installation of the solar panels and associated rooftop equipment/wiring Contractor
- The Solar Installation Certificate applies to rooftop installations on one- and two-story homes up to three stories
- A completed copy of the Solar Installation Certificate must be uploaded to the eTRAKiT portal and must also be kept onsite and available to the City's electrical inspector at the time of inspection
- The Solar Installation Certificate must be submitted within six months of project completion
- Under Colorado's Fair Permit Act (C.R.S. 24-48.5-113, enacted by HB21-1284), the aggregate of all City permit and plan-review fees for the installation is capped at $500 for a residential system and $1,000 for a commercial/nonresidential system producing less than 2 megawatts DC
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of Commerce City Building Permit Fee Schedule (Table 1-A), c3gov.com/files/assets/city/v/1/fd-finance-department/documents/city-fees/section-2-building-permit.pdf, combined with the statewide… Show full citationHide
City of Commerce City Building Permit Fee Schedule (Table 1-A), c3gov.com/files/assets/city/v/1/fd-finance-department/documents/city-fees/section-2-building-permit.pdf, combined with the statewide Colorado Fair Permit Act cap, which overrides the valuation-based calculation for solar specificallyReview timeline
Inspection process
- 1
Electrical Inspection
City electrical inspector verifies the installation against the completed Solar Installation Certificate, which must be available onsite at the time of inspection
See the full Commerce City inspection guide — scheduling & re-inspection fees →
Tips
- Commerce City requires BOTH a Building Permit and an Electrical Permit for rooftop solar — this is not a single combined solar permit type.
- The Solar Installation Certificate is a distinct, solar-specific self-certification requirement unique to Commerce City's Building Safety Division: it must be completed by a licensed journeyman or master electrician employed by a City-licensed electrical contractor, uploaded to eTRAKiT, and kept onsite for the inspector.
- The certificate must be submitted within six months of project completion — don't let this deadline lapse after the installation passes inspection.
- Regardless of how the City's standard Table 1-A valuation-based building fee schedule calculates, Colorado's Fair Permit Act (C.R.S. 24-48.5-113 / HB21-1284) caps the total of all City fees for the permit at $500 for residential and $1,000 for commercial systems under 2 MW DC.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Commerce City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Commerce City's permit history is searchable by address
38,070 permits on record for Commerce City, 2016–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Commerce City
Solar PV Permit in other cities
Compare solar pv permit fees across Colorado →
Look up this fee in a different city →