Electric Vehicle Charging Station Permit in Commerce City, Colorado
Required for installation of Level 1, Level 2, or Level 3 (DC fast) electric vehicle charging stations in Commerce City. The City publishes a dedicated Electric Vehicle Charging Station Design Guide (Step 1: Project Design) distinguishing requirements by charger level. Permitted as a Residential Electrical (RELEC) or Commercial Electrical (CELEC) permit in eTRAKiT — Level 3 installations may also require a building permit depending on complexity (foundation/canopy work) — billed on the City's standard valuation-based Building Permit Fee Schedule (Table 1-A); no distinct flat EV-charger fee line is published separately from the general electrical permit fee.
Verified 2026-07-20 · Source
When you need this permit
- Level 1 EV charging: no permit needed if plugging into an existing outlet; a permit (no plan submission) is needed if a new outlet is installed
- Level 2 EV charging: a permit (no plan submission) is required if installing a new circuit and outlet
- Level 3 (DC fast) EV charging: requires an electrical or building permit depending on complexity, with a full plan submission (electrical plans, building plans for foundation/canopy if applicable, site plan)
- Applied for via eTRAKiT as Residential Electrical (RELEC) or Commercial Electrical (CELEC), the same permit types used for other electric-only work (service changes, solar, etc.)
- Public/commercial EV charging stations are explicitly listed under the Commercial Electrical (CELEC) permit-type description
- Governed by the 2023 NFPA 70 National Electrical Code (NEC) as adopted by the City of Commerce City Building Code (C3BC)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring and conduit before walls closed (new circuit/outlet installations)
- 2
Final
Charger installed, circuit/outlet verified, system energized
See the full Commerce City inspection guide — scheduling & re-inspection fees →
Tips
- Plugging a Level 1 charger into an existing outlet needs no permit at all in Commerce City — but installing any new outlet or circuit (Level 1 or Level 2) does require a permit, even though no plan submission is needed at that tier.
- Only Level 3 (DC fast) chargers trigger full plan review, and may require a building permit in addition to the electrical permit if a foundation or canopy structure is involved.
- There is no separate EV-specific fee schedule — EV charger electrical permits are billed on the same general valuation-based Table 1-A schedule as any other electrical permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Commerce City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Commerce City
Electric Vehicle Charging Station Permit in other cities
Compare electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →