Commercial Building Permit (New Construction / CNEW) — Commerce City, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.c3gov.com/Business-Development/Building-Permits-Inspections
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / CNEW) in Commerce City, Colorado
Required for new commercial construction in Commerce City: new apartment buildings, condominiums, foundation-only construction, mixed-use buildings, core-and-shell buildings and other new commercial structures (eTRAKiT permit type CNEW). New or altered apartments and condominiums are always treated as commercial projects. Reviewed against the 2021 IBC as adopted by the City of Commerce City Building Code (C3BC) plus Local Design Criteria, entirely electronically through the eTRAKiT portal, by the Building Safety Division with parallel review by Planning and Public Works and separate submittals to outside agencies (South Adams County Fire Department, Adams County Health, South Adams County Water and Sanitation District).
Verified 2026-08-02 · Source
When you need this permit
- Commercial New Construction (CNEW) permit type in eTRAKiT covers new apartment buildings, condominiums, foundation-only construction, mixed-use buildings, core and shell buildings and other new commercial structures; apartments/condos are always commercial projects
- Plans reviewed against the 2021 IBC as adopted/amended by the C3BC (including Appendix Chapters C, E, F, G, H, I, J, K and N) and the Local Design Criteria: 35 psf ground snow load, 115 mph Vult wind speed, Seismic Design Category B, 36-inch frost line depth
- All submissions must be electronic via the eTRAKiT portal (ePlans); an incomplete submission package delays acceptance of the application
- Building plans must be electronically signed and sealed as required
- A Development Plan approval letter from the Planning Division is a minimum submission document — the land-development entitlement track (Development Plans/PUD Development Permits: 4-6 months administrative, 6-12 months public hearing) is upstream of and separate from the building permit
- Fire plan review is handled directly by the South Adams County Fire Department (303-288-0835) as a separate submittal
- Contractors must apply using the eTRAKiT account tied to their current Commerce City contractor license (Unlimited General Class A $120); a lapsed license delays issuance at the Pre-Issuance Review step Contractor
- Deferred submittals (e.g., trusses) must be submitted to the Building Division after permit issuance but prior to erection/installation, and must be approved before a Certificate of Occupancy
- Elevator installations require a separate submission to the Colorado Division of Oil and Public Safety; a Certificate of Operation from that division is a CO prerequisite
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 6 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Special Inspections (per SITA)
Special inspections and testing per the approved Statement of Special Inspections / SITA; the Special Inspections Final Certification Report must be uploaded to the parent permit and approved before a CO is issued
- 2
Building Safety Stage Inspections
The permit holder/contractor must notify the city when stages of construction requiring inspection are reached; inspections are scheduled in eTRAKiT with a deadline of 4 p.m. the business day before the desired date. City-approved site plan, building plans and shop drawings must be on the jobsite; ladders/scaffolds must be provided for inspector access. The city does not publish a fixed numbered commercial inspection sequence — required stages are per the C3BC/2021 IBC
- 3
Planning Inspection
If a planning inspection is required it can take up to five days after the date scheduled (Planning Division: cdplanner@c3gov.com, 303-227-8777)
- 4
Outside-Agency Inspections
South Adams County Fire Department, Public Works, Adams County Health and South Adams County Water and Sanitation District conduct their own inspections; all applicable agency finals must be approved before a CO
- 5
Final Inspection and Certificate of Occupancy
After the Building Safety Division final inspection is approved, a new building cannot be occupied until a CO or TCO is issued via a separate Certificate of Occupancy/Completion (CO) permit in eTRAKiT linked to the parent permit; core-and-shell buildings receive a Certificate of Completion instead. Prerequisites include approved deferred submittals, finaled linked permits (fire sprinklers, alarms), UFER certification, Improvement Location Certificate, Energy Compliance Certificate, and elevator Certificate of Operation where applicable
See the full Commerce City inspection guide — scheduling & re-inspection fees →
Tips
- Commerce City has NO separate industrial permitting track despite its refinery/logistics base — industrial and warehouse projects flow through the same commercial permit types, with Commercial Miscellaneous (CMISC) covering tanks, high-pile storage, fire sprinklers and similar industrial-adjacent work, and the South Adams County Fire Department handling fire plan review directly (303-288-0835)
- The Development Plan approval letter from Planning is a hard minimum submission document — secure your land-use entitlement (4-6 months administrative, 6-12 months with public hearing for Development Plans/PUDs) before applying for the building permit
- New or altered apartments and condominiums are ALWAYS commercial projects in Commerce City, including remodels of existing condo units
- Foundation-only permits are available (fee based on valuation) — useful for fast-tracking large warehouse/industrial starts while the full building review proceeds
- If you apply under the wrong permit type, staff will transfer the application (and fees already paid) to a new record under the correct type rather than rejecting it
- The 21-day commercial review clock starts AFTER the completeness review, which is usually completed the same day as submittal; upfront fees must be paid to advance to Gateway Review, and the balance is due at Pre-Issuance before the permit is released (downloadable within 24 hours of issuance)
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Commerce City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Commerce City.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Commerce City
Commercial Building Permit (New Construction / CNEW) in other cities
Compare commercial building permit (new construction / cnew) fees across Colorado →