EV Charger / Electric Vehicle Charging Station Permit (State-Administered) — Federal Heights, Colorado · Requirements sheet
Verified 2026-07-23 · Source: https://www.fedheights.org/building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit (State-Administered) in Federal Heights, Colorado
Federal Heights has no dedicated EV charger permit — like all electrical work, an EV charging station (Level 1/2 EVSE) circuit is NOT permitted or inspected by the City. Per the City's own Building Department page, 'The State of Colorado Department of Regulatory Agencies (DORA) administers all electrical permits and inspections' for Federal Heights, exactly as documented in the electrical-permit entry. The City's standard Building Permit Application does not list electrical/EV charging as a category at all.
Verified 2026-07-23 · Source
When you need this permit
- Electrical permits for EV charger/EVSE circuits must be obtained directly from the Colorado State Electrical Board (DORA/Division of Professions and Occupations), not from the City of Federal Heights
- Contractors must hold a current Colorado Electrical license; the state permit and inspection process governs, per statewide licensure statutes (CRS Title 12, Article 23)
- The City of Federal Heights performs no separate local electrical permitting, plan review, or inspection function for EV charger installation, same as for any other electrical scope
- If the EV charger installation is paired with a solar/battery project, the roof/racking portion still goes through the City (Category 10 on the standard Building Permit Application) while the electrical interconnection portion goes to the State — see rooftop-solar-pv-permit and electrical-permit entries
- DISCOVERED 2026-07-23: separately from the electrical permit itself, the City now regulates WHERE and under what zoning conditions an EVCS may be sited, per Ordinance No. 25-17 (adopted 12/16/2025), codified as Chapter 70, Article XVII, Electric Vehicle Charging Stations, of the Federal Heights Municipal Code (enacted per Colorado HB24-1173). Level 1/2 EVCS (accessory or primary use) are permitted-by-right or require a Conditional Use Permit depending on zone district (R-1 through R-5, C-1, I-1) and are exempt from Site Development Plan and Landscape Plan review, subject only to Article XVII's own design standards plus the electrical/building permits described above; a NEW Level 3 (DC fast-charging) EVCS on a site without an existing Site Development Plan triggers an administrative SDP review, and adding Level 3 EVCS to an existing SDP site requires an administrative minor-SDP-modification submittal to the City (Sec. 70-470) — this is a real City-administered zoning approval step distinct from the DORA electrical permit.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed under the Colorado State Electrical Board's own inspection program, not by City of Federal Heights Building Department staff
See the full Federal Heights inspection guide — scheduling & re-inspection fees →
Tips
- Do not attempt to submit an EV charger circuit through the City of Federal Heights' Building Permit Application — electrical is not even a listed category on that form. Pursue the electrical permit directly through DORA's State Electrical Board.
- If the EV charger is installed alongside new roof-mounted solar or a structural carport/canopy modification, budget for two separate review tracks: City (structural) and State (electrical) — they are not on a unified schedule.
- A Level 3 (DC fast-charging) EVCS as a primary or accessory use requires a City-administered Site Development Plan review (new SDP or minor SDP modification) under Chapter 70, Article XVII — this zoning-level review is separate from and in addition to the DORA state electrical permit; Level 1/2 EVCS are exempt from SDP/landscape review under the same article.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Federal Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Federal Heights
EV Charger / Electric Vehicle Charging Station Permit (State-Administered) in other cities
Look up this fee in a different city →
Related guides
Now live
Build your Federal Heights project checklist
Describe your project once and get every permit, document, and fee it triggers in Federal Heights — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →