Residential Building Permit (New Construction) — Federal Heights, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.fedheights.org/building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Federal Heights, Colorado
Required for new single-family homes and similar new residential construction in Federal Heights ('New Building' category on the City's Building Permit Application). Reviewed under the 2021 IRC/IBC as adopted by Ordinance 23-02 (effective April 15, 2023), with the 2018 IECC retained for energy compliance. Issued by the City Building Department.
Verified 2026-07-06 · Source
When you need this permit
- Plans must comply with the 2021 IRC/IBC as adopted and locally amended per Ordinance 23-02, and the 2018 IECC for energy compliance
- Classification of Work on the application must mark 'Residential' and category '1. New Building'
- All contractors must complete a City of Federal Heights Contractor Registration; subcontractors must be recorded via a Subcontractor License Form ($14.00 fee each) Contractor
- Plans requiring a design professional's stamp must meet the City's published Architect/Professional Engineer Seal Specifications
- A zoning-district-specific Plot Plan (R-1, R-4, or R-5 template) is required as part of submittal
- Multi-agency sign-off required on the application: Building, Public Works, Fire Dept., Storm Water, Engineering, and Zoning
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing complete before cover
- 3
Rough Mechanical/Plumbing
Trade rough-ins before concealment (plumbing subject to State DORA license verification at inspection)
- 4
Final Inspection
All work complete per approved plans and applicable codes; Certificate of Occupancy issued if checked on the application
See the full Federal Heights inspection guide — scheduling & re-inspection fees →
Tips
- Federal Heights retained the 2018 IECC even while updating most other codes to the 2021 cycle via Ordinance 23-02 (effective April 15, 2023) — confirm current energy-code compliance path directly with the Building Department (303-412-3526), especially given Colorado's HB22-1362 statewide energy-code floor that applies to the City's NEXT code update.
- Electrical work on this project is NOT permitted or inspected by the City — it is administered entirely by the State of Colorado DORA Electrical Board; budget for a separate state permit process.
- Plumbing is permitted locally by the City, but the City performs contemporaneous State Plumbing Board (DORA) license verification at inspection — ensure your Plumbing Contractor and Master Plumber licenses are current and listed on the permit before scheduling inspections.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Federal Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Federal Heights
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →