Commercial Tenant Improvement Permit — Westminster, Colorado · Requirements sheet
Verified 2026-06-30 · Source: https://www.westminsterco.gov/DocumentCenter/View/4587/2021-Commercial-Submittal-Documents
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement Permit in Westminster, Colorado
Required for interior remodels, additions, and tenant improvements in commercial buildings in Westminster. Reviewed against the 2021 IBC, IFC, IPC, IMC, IFGC, and IECC plus the 2023 NEC and ICC/ANSI A117.1-2017 accessibility standard, all with Westminster amendments. Submitted digitally via eTRAKiT with a published SLA.
Verified 2026-06-30 · Source
When you need this permit
- Properly completed online building permit application via eTRAKiT; incomplete applications are not accepted
- Scalable architectural site plan showing accessible routes, parking, curb ramps, and other ICC/ANSI A117.1-2017 compliance details
- Exterior elevations depicting all exposed mechanical/electrical equipment, meters, and gas lines, with screening methods per Planning Division review
- Digitally submitted plans must be signed and sealed by the design professional of record
- Site-specific soils report including foundation recommendations
- A licensed contractor must be signed onto the permit prior to issuance (design professionals may apply, but a licensed contractor must be added before issuance) Contractor
- Commercial building permit review timeline: 30 business days for initial review, 15 business days for subsequent reviews (published City SLA)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Framing / Structural
After framing complete before walls covered
- 2
MEP Rough-In
Mechanical, electrical, plumbing rough-in before walls closed
- 3
Final / Certificate of Occupancy
All work complete, life safety systems functional
See the full Westminster inspection guide — scheduling & re-inspection fees →
Tips
- Westminster publishes a firm commercial review SLA: 30 business days for the initial review and 15 business days for each subsequent review cycle — budget your project timeline accordingly.
- The Commercial Plan Review Submittal Guidelines list the complete adopted code set in one place: 2021 IBC/IFC/IRC/IPC/IMC/IFGC/IECC plus 2023 NEC and ICC/ANSI A117.1-2017 — use this as your single reference for code editions.
- A licensed contractor must be signed onto the permit before issuance, even if a design professional submitted the original application. Contractor
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Westminster building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Westminster.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Westminster
Commercial Tenant Improvement Permit in other cities
Compare commercial tenant improvement permit fees across Colorado →
Look up this fee in a different city →