Demolition Permit in Englewood, Colorado
Required before any structure within the City may be demolished; issued by the City's own Building & Codes Division under Englewood Municipal Code (EMC) Title 8, Chapter 6. A separate demolition permit is required for each structure demolished. Fees are flat amounts set by structure type rather than the valuation table used for general building permits.
Verified 2026-07-19 · Source
When you need this permit
- No structure within the City shall be demolished unless and until a permit has been issued, per EMC § 8-6-1(A).
- A separate demolition permit is required for each structure to be demolished; the permit must be kept on the premises during demolition and shown on demand to any authorized City agent, per EMC § 8-6-1(B).
- A Colorado State Demolition Approval notice is required for each structure being demolished (include the asbestos abatement report if available), per the City's Demolition of Structures guidance.
- Pre-demolition: all power, gas, water, steam, sewer, and other service lines must be shut off/disconnected and capped as directed by the service provider outside the property lines, with advance notification to and approval from all affected utility companies, per EMC § 8-6-3 and the Demolition of Structures guidance.
- The site must be cleaned, filled, and leveled within 48 hours after demolition is completed, per the Demolition of Structures guidance (Ord. 82, Series 1985).
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Englewood inspection guide — scheduling & re-inspection fees →
Tips
- Demolition permits expire 60 days after the date of issuance, per EMC § 8-6-1(D).
- The flat $50/$200 demolition fee amounts were codified directly in EMC § 8-6-1(C) as of the 2020-dated 'Demolition of Structures' guidance PDF, but the current codified ordinance text (as amended by Ord. 2023-67, per Municode) has removed the specific dollar figures from the ordinance itself, leaving only the no-fee exemption language. Those same $50/$200 amounts are still confirmed current via the separate 2025 Schedule of Service, License and Permit Fees and Utility Rates (citing EMC 8-6-1 as the authorizing code section) — i.e., the fee moved from the ordinance text into the standalone fee-schedule resolution rather than changing in amount.
- A minimum $1,000 surety bond and a Certificate of Insurance (minimum $50,000/$300,000/$50,000 coverage) are both required before a demolition permit is issued — budget for these in addition to the flat permit fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Englewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Englewood
Demolition Permit in other cities
Compare demolition permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Englewood project checklist
Describe your project once and get every permit, document, and fee it triggers in Englewood — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →