Littleton building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Littleton, Colorado.
Verified 2026-07-05 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Littleton Center, 2255 W. Berry Avenue, Littleton, CO 80120
- Phone
- 303-795-3751
- Office hours
- Permit Center: Monday-Thursday 8:00 a.m.-4:30 p.m., Fridays closed; in-person walk-in hours limited to Monday 1:00-4:30 p.m. (no walk-ins after 4:15 p.m.) and Thursday 8:00-11:30 a.m.; Building Inspections staff hours 7:30 a.m.-4:30 p.m. Monday-Friday. FAX 720-741-0210, eFax 720-384-0601.
- Website
- Official site
Published scheduling rules
- The Permit Center's walk-in hours are unusually limited: Monday 1:00-4:30 p.m. and Thursday 8:00-11:30 a.m. ONLY (closed Fridays) — email/phone is the primary channel outside those windows, with a stated 24-hour response target on the next business day. (General)
- No numeric plan-review or permit-issuance turnaround is published for ANY permit type covered in this file — Colorado's home-rule status means there is no statewide clock, and Littleton's own site publishes only post-issuance inspection-scheduling SLAs (next business day, up to 7 days out), not a pre-issuance plan-review timeline. Confirm current caseload timing directly with the Permit Center (303-795-3751 / permits@littletonco.gov) before committing to a client-facing schedule. (General)
Inspection sequence
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings/alteration)
Structural engineer of record must verify any foundation alteration before Building Division final approval
- 2
Rough Plumbing / Electrical / Heating
Trade rough-ins before concealment; all must be approved before rough framing inspection
- 3
Rough Framing
Framing, sub-flooring, stairs complete before cover
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Single-Family, Townhouse, Two-Family Dwelling)
- 1
Foundation
Before concrete pour; structural engineer of record (or representative) must inspect and verify any foundation alteration prior to Building Division final approval
- 2
Rough Plumbing / Rough Electrical / Rough Heating
Rough-in of plumbing (waste/vent/water/gas piping, tested), electrical (panel and wiring), and heating (ductwork) before concealment; all three must be inspected and approved before a rough framing inspection can be requested
- 3
Rough Framing
Framing, sub-flooring, stairs; requires prior approval of rough plumbing, rough electrical, and rough heating inspections
- 4
Final Inspection
All work complete per approved plans and applicable codes; owner or contractor must request in advance and ensure site access (no rear/fenced-yard entry without permission, no unoccupied-residence entry)
Applies to: Electrical Permit
- 1
Rough Electrical
Panel and wiring installed before concealment; must be approved (along with rough plumbing and rough heating) before rough framing inspection is requested
- 2
Final Inspection
All devices installed, panel labeled, system energized and verified
Applies to: Mechanical / HVAC Permit
- 1
Rough Heating
Ductwork, flues, and equipment installed before concealment; must be approved (with rough plumbing and rough electrical) before rough framing inspection
- 2
Final Inspection
Equipment operational; combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Waste/vent/water/gas piping installed and tested before concealment; must be approved (with rough electrical and rough heating) before rough framing inspection
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Applies to: Residential Rooftop Solar (PV) and Energy Storage System (ESS) Permit
- 1
Rough Frame / Rough Electrical
Only 25% of panels may be installed prior to these inspections being completed
- 2
Final Inspection
Racking, roof penetrations, grounding, and electrical connections verified against stamped plans
Applies to: Roofing Permit (Reroof)
- 1
Sheathing Fastening Inspection (if sheathing overlaid/replaced)
Required by Building Division staff before installation of roof underlayment or coverings, when deck sheathing gaps exceed 1/2 inch
- 2
Final Roof Inspection
An OSHA-compliant ladder rated for 250+ lb capacity, extending 3 feet above the roof eave, must be provided and secured; roof must be free of rain, frost, ice, and snow on inspection day; inspectors will not enter fenced/rear yards without permission
Final inspection only: Demolition Permit, EV Charger / Electric Vehicle Charging Station Permit, Fence Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Littleton building permits
Get alerts for Littleton
We'll email you when Littleton's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.