Residential Addition / Remodel Permit — Littleton, Colorado · Requirements sheet
Verified 2026-07-05 · Source: https://www.littletonco.gov/Building-Development/Permits-Review-Guides-and-Requirements/Residential-Submittal-Requirements
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel Permit in Littleton, Colorado
Required for room additions, basement finishes, and structural modifications to existing residential dwellings in Littleton. Reviewed under the 2024 IRC as locally amended, using the City's Residential Remodel submittal track (distinct from the New SFD/Addition/ADU track for ground-up structural work).
Verified 2026-07-05 · Source
When you need this permit
- Applicable codes must be notated on plans; 'preliminary' or 'not for construction' plans are not accepted
- Existing and proposed floor plans required, including north arrow, room use/size, ceiling heights, door/window sizes and locations, stairway rise/run/handrail/headroom details
- Any alteration of foundation or structural components requires a plan/detailed drawing stamped by a structural engineer at time of application; the engineer of record (or representative) must inspect and verify the alteration prior to final Building Division approval
- Basement finishes must show beam/ductwork locations and finished-floor-to-beam/ductwork clearance heights
- Electrical plans must show receptacles, switches, lighting, smoke alarms, ventilation fans, and service size/location
- Manual J, S, and D calculations required if the heating system is replaced or ductwork is replaced/relocated/altered
- IECC compliance documentation may be required depending on scope (thermal envelope, mechanical, or electrical system impact)
- All documents submitted electronically via eTRAKiT
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation (if new footings/alteration)
Structural engineer of record must verify any foundation alteration before Building Division final approval
- 2
Rough Plumbing / Electrical / Heating
Trade rough-ins before concealment; all must be approved before rough framing inspection
- 3
Rough Framing
Framing, sub-flooring, stairs complete before cover
- 4
Final Inspection
All work complete per approved plans
See the full Littleton inspection guide — scheduling & re-inspection fees →
Tips
- Basement finishes require a permit in Littleton and must document beam/ductwork clearance heights on the plan set — don't treat interior remodels as automatically exempt.
- If your remodel replaces or relocates the heating system or ductwork, budget time to produce Manual J/S/D calculations before submittal — the City requires these up front, not after review comments.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Littleton
Residential Addition / Remodel Permit in other cities
Compare residential addition / remodel permit fees across Colorado →
Look up this fee in a different city →