Commercial Building Permit (New Construction & Additions) — Littleton, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.littletonco.gov/Building-Development/Permits-Review-Guides-and-Requirements/Commercial-Submittal-Requirements
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction & Additions) in Littleton, Colorado
Required for new commercial buildings and commercial additions in Littleton. Reviewed under the 2024 IBC, IECC, IMC, IPC, IFC and related I-codes as locally amended, plus the 2026 NEC. Issued and inspected by the City of Littleton Building and Code Compliance Division (Permit Center) — the City runs one unified in-house building department for all parcels within city limits, including the small portions of Littleton that extend into Douglas and Jefferson Counties beyond its Arapahoe County core. Fire/life-safety construction documents must be submitted separately and in parallel to South Metro Fire Rescue.
Verified 2026-08-02 · Source
When you need this permit
- Plans must comply with the 2024 I-codes as adopted by the City of Littleton, and the applicable code versions must be notated on the plans
- Seal of a Colorado Registered Architect required on architectural plans; a Colorado Professional Engineer seal required on structural, mechanical, electrical, and plumbing components — size/span/spacing of structural and framing members must be sealed by a Colorado PE only (an architect seal is not accepted for structural framing)
- Full code analysis required on the plans: sheet index on the title sheet, statement of code versions used, Use and Occupancy Classification, Construction Type, occupant load with calculations, number of stories and building height, allowable area calculations (with justification for any area increases), plumbing fixture counts with spacing diagrams, identification of new and existing fire suppression systems, plan of exiting conditions, and a Life Safety Plan showing exit routes, lengths, exits, exit discharges, stairs, ramps, and elevators
- Intended energy compliance path per IECC Chapter 4 must be identified: Prescriptive R-Value/U-Factor, Prescriptive Component Performance Alternative, Simulated Building Performance, or Energy Rating Index; IECC C406 additional efficiency requirements must be identified
- Electrical plans (PE-sealed) must include a one-line diagram with load and fault current calculations, service panel location and load calcs, emergency/exit lighting layout, photometric study and cut sheets for exterior fixtures, and service entrance details for new construction
- Mechanical and plumbing plans (PE-sealed) must include isometric drawings for plumbing and gas piping, equipment schedules with performance data, Manuals J, S, and D, and — for rooftop units — structural details confirming load and screening compliance with Municipal Code Title 10
- Plans must be submitted separately to South Metro Fire Rescue for fire review
- Projects including restaurants/grocery/food service, childcare facilities or schools, swimming pools, or body art facilities must also be submitted to the appropriate county health department (Arapahoe, Jefferson, or Douglas County depending on parcel location)
- Site Plan (with north arrow) required for changes in use, exterior changes, street access modifications, or curb cuts
- Community Development Engineering Division (303-795-3868) handles grading, right-of-way, sewer, traffic, and floodplain; for a new sewer tap, the Sanitation District is paid first, then the City of Littleton; Denver Water fees/application: 303-893-2444
- All documents must be submitted electronically via the eTRAKiT portal; 'preliminary' or 'Not for Construction' plan sets are not accepted
- General contractor must hold a current City of Littleton Contractor's License with $1,000,000/$2,000,000 Commercial General Liability insurance naming the City as Certificate Holder; electrical and plumbing subcontractors additionally need active Colorado DORA licenses Contractor
- Permit must be commenced within 180 days of issuance and expires 365 days after issuance unless extended by the Building Official
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 8 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing
All waste/vent piping, water pipe, and gas piping installed and tested; must be approved before the rough framing inspection is requested
- 2
Rough Electrical
Rough wiring inspection; must be approved before the rough framing inspection is requested
- 3
Rough Heating / Mechanical
Rough mechanical inspection; must be approved before the rough framing inspection is requested
- 4
Rough Framing
Requested only after rough plumbing, rough electric, and rough heating are inspected and approved, per the City's Building Inspections page
- 5
Final Inspections / Certificate of Occupancy
All trade finals plus building final; a Temporary Certificate of Occupancy ($400) is available. The complete required-inspection set for a given commercial project follows the 2024 IBC as adopted and is listed on the permit record in eTRAKiT
See the full Littleton inspection guide — scheduling & re-inspection fees →
Tips
- South Metro Fire Rescue plan review is a separate, parallel submittal through SMFR's own portal — submit at the same time as your eTRAKiT application rather than sequentially, or fire review can become the critical path.
- Budget for the full fee stack: valuation-based permit fee + 65% plan review fee + 1.969% City use tax deposit + 0.125% Arapahoe County Open Space Tax + per-square-foot Land Development Impact Fees ($3.44-$6.51/sq ft by use) all collected at issuance.
- Littleton runs one unified in-house building department for the entire city — even for parcels in the Douglas or Jefferson County slivers, the City of Littleton Permit Center (not the county) issues the permit; the county only matters for choosing which health department reviews food/childcare/pool projects.
- No same-day inspections: requests submitted by 4:00 p.m. Monday-Friday are scheduled for the next business day, and inspections can be booked up to seven business days out; during peak activity the schedule can run a few days behind.
- For buildings built before 1988, contact CDPHE (303-692-2000) about asbestos requirements before demolition or alteration work.
- For a new sewer tap, pay the Sanitation District first, then the City of Littleton — and coordinate Denver Water fees (303-893-2444) separately.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Littleton.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Littleton
Commercial Building Permit (New Construction & Additions) in other cities
Compare commercial building permit (new construction & additions) fees across Colorado →
Look up this fee in a different city →
Now live
Build your Littleton project checklist
Describe your project once and get every permit, document, and fee it triggers in Littleton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.