Commercial Building Permit (New Construction & Additions) in Littleton, Colorado

Required for new commercial buildings and commercial additions in Littleton. Reviewed under the 2024 IBC, IECC, IMC, IPC, IFC and related I-codes as locally amended, plus the 2026 NEC. Issued and inspected by the City of Littleton Building and Code Compliance Division (Permit Center) — the City runs one unified in-house building department for all parcels within city limits, including the small portions of Littleton that extend into Douglas and Jefferson Counties beyond its Arapahoe County core. Fire/life-safety construction documents must be submitted separately and in parallel to South Metro Fire Rescue.

Verified 2026-08-02 · Source

When you need this permit

  • Plans must comply with the 2024 I-codes as adopted by the City of Littleton, and the applicable code versions must be notated on the plans
  • Seal of a Colorado Registered Architect required on architectural plans; a Colorado Professional Engineer seal required on structural, mechanical, electrical, and plumbing components — size/span/spacing of structural and framing members must be sealed by a Colorado PE only (an architect seal is not accepted for structural framing)
  • Full code analysis required on the plans: sheet index on the title sheet, statement of code versions used, Use and Occupancy Classification, Construction Type, occupant load with calculations, number of stories and building height, allowable area calculations (with justification for any area increases), plumbing fixture counts with spacing diagrams, identification of new and existing fire suppression systems, plan of exiting conditions, and a Life Safety Plan showing exit routes, lengths, exits, exit discharges, stairs, ramps, and elevators
  • Intended energy compliance path per IECC Chapter 4 must be identified: Prescriptive R-Value/U-Factor, Prescriptive Component Performance Alternative, Simulated Building Performance, or Energy Rating Index; IECC C406 additional efficiency requirements must be identified
  • Electrical plans (PE-sealed) must include a one-line diagram with load and fault current calculations, service panel location and load calcs, emergency/exit lighting layout, photometric study and cut sheets for exterior fixtures, and service entrance details for new construction
  • Mechanical and plumbing plans (PE-sealed) must include isometric drawings for plumbing and gas piping, equipment schedules with performance data, Manuals J, S, and D, and — for rooftop units — structural details confirming load and screening compliance with Municipal Code Title 10
  • Plans must be submitted separately to South Metro Fire Rescue for fire review
  • Projects including restaurants/grocery/food service, childcare facilities or schools, swimming pools, or body art facilities must also be submitted to the appropriate county health department (Arapahoe, Jefferson, or Douglas County depending on parcel location)
  • Site Plan (with north arrow) required for changes in use, exterior changes, street access modifications, or curb cuts
  • Community Development Engineering Division (303-795-3868) handles grading, right-of-way, sewer, traffic, and floodplain; for a new sewer tap, the Sanitation District is paid first, then the City of Littleton; Denver Water fees/application: 303-893-2444
  • All documents must be submitted electronically via the eTRAKiT portal; 'preliminary' or 'Not for Construction' plan sets are not accepted
  • General contractor must hold a current City of Littleton Contractor's License with $1,000,000/$2,000,000 Commercial General Liability insurance naming the City as Certificate Holder; electrical and plumbing subcontractors additionally need active Colorado DORA licenses Contractor
  • Permit must be commenced within 180 days of issuance and expires 365 days after issuance unless extended by the Building Official

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 8 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based)Per Resolution 2025-105 (approved December 21, 2025): $25.85 up to $500; $25.85 + $3.35/$100 from $500.01-$2,000; $76.17 + $15.40/$1,000 to $25,000; $430.37 + $11.11/$1,000 to $50,000; $708.12 + $7.70/$1,000 to $100,000; $1,093.12 + $6.16/$1,000 to $500,000; $3,557.12 + $5.23/$1,000 to $1,000,000; $6,172.12 + $4.02/$1,000 above $1,000,000
$25.85 minimum; sliding scale by total valuation
Plan Review FeeApplicable when blueprints/construction documents are reviewed for municipal and adopted building codes — effectively always for commercial new construction
65% of the Building Permit Fee
City Use Tax Deposit0.01969 x Total Job Valuation ((Total Job Valuation x 52.5%) x 3.75% City use tax rate); assessed and collected at permit issuance
1.969% of total job valuation
Arapahoe County Open Space Tax0.00125 x Total Valuation ((Total Job Valuation x 50%) x 0.25%); charged on the building permit
0.125% of total valuation
Land Development Impact Fee (new development, per square foot)Per Ordinance No. 04-2026, effective February 17, 2026, paid at building permit issuance: Retail/Commercial $6.51, Auto Dealership $6.51, Lodging $4.52, Office $4.31, Industrial $3.79, Warehouse/Storage $3.44 per sq ft; rates adjusted annually for inflation (Littleton City Code Title 1, Chapter 14)
$3.44-$6.51 per sq ft by use category
Temporary Certificate of OccupancyPer the Permit Fee Schedules page
$400 first issuance; $200 each renewal
Plan Revision / Resubmittal ReviewOr the total hourly cost to the jurisdiction, whichever is greater
$160 minimum (first two hours), then $80/hour

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit (New Construction & Additions) permit actually take in Littleton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Plumbing

    All waste/vent piping, water pipe, and gas piping installed and tested; must be approved before the rough framing inspection is requested

  2. 2

    Rough Electrical

    Rough wiring inspection; must be approved before the rough framing inspection is requested

  3. 3

    Rough Heating / Mechanical

    Rough mechanical inspection; must be approved before the rough framing inspection is requested

  4. 4

    Rough Framing

    Requested only after rough plumbing, rough electric, and rough heating are inspected and approved, per the City's Building Inspections page

  5. 5

    Final Inspections / Certificate of Occupancy

    All trade finals plus building final; a Temporary Certificate of Occupancy ($400) is available. The complete required-inspection set for a given commercial project follows the 2024 IBC as adopted and is listed on the permit record in eTRAKiT

See the full Littleton inspection guide — scheduling & re-inspection fees →

Tips

  • South Metro Fire Rescue plan review is a separate, parallel submittal through SMFR's own portal — submit at the same time as your eTRAKiT application rather than sequentially, or fire review can become the critical path.
  • Budget for the full fee stack: valuation-based permit fee + 65% plan review fee + 1.969% City use tax deposit + 0.125% Arapahoe County Open Space Tax + per-square-foot Land Development Impact Fees ($3.44-$6.51/sq ft by use) all collected at issuance.
  • Littleton runs one unified in-house building department for the entire city — even for parcels in the Douglas or Jefferson County slivers, the City of Littleton Permit Center (not the county) issues the permit; the county only matters for choosing which health department reviews food/childcare/pool projects.
  • No same-day inspections: requests submitted by 4:00 p.m. Monday-Friday are scheduled for the next business day, and inspections can be booked up to seven business days out; during peak activity the schedule can run a few days behind.
  • For buildings built before 1988, contact CDPHE (303-692-2000) about asbestos requirements before demolition or alteration work.
  • For a new sewer tap, pay the Sanitation District first, then the City of Littleton — and coordinate Denver Water fees (303-893-2444) separately.

Frequently asked questions

Littleton requires a commercial building permit (new construction & additions) for: Plans must comply with the 2024 I-codes as adopted by the City of Littleton, and the applicable code versions must be notated on the plans; Seal of a Colorado Registered Architect required on architectural plans; a Colorado Professional Engineer seal required on structural, mechanical, electrical, and plumbing components — size/span/spacing of structural and framing members must be sealed by a Colorado PE only (an architect seal is not accepted for structural framing); Full code analysis required on the plans: sheet index on the title sheet, statement of code versions used, Use and Occupancy Classification, Construction Type, occupant load with calculations, number of stories and building height, allowable area calculations (with justification for any area increases), plumbing fixture counts with spacing diagrams, identification of new and existing fire suppression systems, plan of exiting conditions, and a Life Safety Plan showing exit routes, lengths, exits, exit discharges, stairs, ramps, and elevators; Intended energy compliance path per IECC Chapter 4 must be identified: Prescriptive R-Value/U-Factor, Prescriptive Component Performance Alternative, Simulated Building Performance, or Energy Rating Index; IECC C406 additional efficiency requirements must be identified; Electrical plans (PE-sealed) must include a one-line diagram with load and fault current calculations, service panel location and load calcs, emergency/exit lighting layout, photometric study and cut sheets for exterior fixtures, and service entrance details for new construction; Mechanical and plumbing plans (PE-sealed) must include isometric drawings for plumbing and gas piping, equipment schedules with performance data, Manuals J, S, and D, and — for rooftop units — structural details confirming load and screening compliance with Municipal Code Title 10; Plans must be submitted separately to South Metro Fire Rescue for fire review; Projects including restaurants/grocery/food service, childcare facilities or schools, swimming pools, or body art facilities must also be submitted to the appropriate county health department (Arapahoe, Jefferson, or Douglas County depending on parcel location); Site Plan (with north arrow) required for changes in use, exterior changes, street access modifications, or curb cuts; Community Development Engineering Division (303-795-3868) handles grading, right-of-way, sewer, traffic, and floodplain; for a new sewer tap, the Sanitation District is paid first, then the City of Littleton; Denver Water fees/application: 303-893-2444; All documents must be submitted electronically via the eTRAKiT portal; 'preliminary' or 'Not for Construction' plan sets are not accepted; General contractor must hold a current City of Littleton Contractor's License with $1,000,000/$2,000,000 Commercial General Liability insurance naming the City as Certificate Holder; electrical and plumbing subcontractors additionally need active Colorado DORA licenses; Permit must be commenced within 180 days of issuance and expires 365 days after issuance unless extended by the Building Official. If your project isn't listed, confirm with City of Littleton Building and Code Compliance Division (Community Development Department, Permit Center) at 303-795-3751 before starting work.

Fees are valuation-based per Resolution 2025-105. Example: a $1,000,000 project pays a $6,172.12 permit fee, plus a 65% plan review fee (~$4,012), a City use tax deposit of 1.969% of valuation (~$19,690), an Arapahoe County Open Space Tax of 0.125% (~$1,250), and — for new development — Land Development Impact Fees of $3.44-$6.51 per square foot depending on use category.

The City does not publish a fixed commercial plan-review turnaround. After submitting through eTRAKiT you can view the anticipated permit-issuance date on your project record; confirm current review timing with the Permit Center (303-795-3751, permits@littletonco.gov) before committing to a construction schedule.

You'll need: Commercial Building Permit Application (eTRAKiT Online System); Architectural Plans (sealed by Colorado Registered Architect); Structural Plans (sealed by Colorado PE); Code Analysis & Life Safety Plan; Electrical Plans (sealed by Colorado PE); Mechanical & Plumbing Plans (sealed by Colorado PE); IECC Energy Compliance Documentation; South Metro Fire Rescue Plan Submittal. Depending on your project, Littleton may also ask for: Site Plan; County Health Department Submittal. See the required-documents checklist on this page for details on each.

Littleton requires 5 inspection(s) for a commercial building permit (new construction & additions), in order: Rough Plumbing, Rough Electrical, Rough Heating / Mechanical, Rough Framing, Final Inspections / Certificate of Occupancy. Schedule each through City of Littleton Building and Code Compliance Division (Community Development Department, Permit Center) (303-795-3751).

Apply through City of Littleton Building and Code Compliance Division (Community Development Department, Permit Center) at Littleton Center, 2255 W. Berry Avenue, Littleton, CO 80120. Phone: 303-795-3751, email: permits@littletonco.gov. Office hours: Permit Center: Monday-Thursday 8:00 a.m.-4:30 p.m., Fridays closed; in-person walk-in hours limited to Monday 1:00-4:30 p.m. (no walk-ins after 4:15 p.m.) and Thursday 8:00-11:30 a.m.; Building Inspections staff hours 7:30 a.m.-4:30 p.m. Monday-Friday. FAX 720-741-0210, eFax 720-384-0601.. Official information: https://www.littletonco.gov/Building-Development.

Littleton, Colorado has adopted: 2024 International Building Code (IBC) — City of Littleton Building Codes and Amendments page; 2024 International Residential Code (IRC); 2024 International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC); 2024 International Fuel Gas Code (IFGC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — Littleton uses the International Plumbing Code, not the Uniform Plumbing Code; 2024 International Property Maintenance Code (IPMC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Wildland-Urban Interface Code (IWUIC); 2024 International Fire Code (IFC); ICC A117.1-2017 Standard with Supplement 1 — Accessible and Usable Buildings and Facilities; NFPA 70 National Electrical Code, 2026 Edition ("2026 NEC"); 1997 Uniform Code for the Abatement of Dangerous Buildings (International Conference of Building Officials); Colorado Model Electric Ready and Solar Ready Code, adopted by the Colorado Department of Local Affairs and Colorado Energy Office effective June 1, 2023; Littleton City Code Title 4, Chapter 1 — local IRC amendments including adopted Climatic and Geographic Design Criteria (Table R301.2): Ground Snow Load 40 psf (non-reducible), Ultimate Design Wind Speed 136 mph; Littleton City Code Title 3, Chapter 16 — Contractor Licensing (license/registration required to obtain permits within city limits, effective July 1, 1985). Local amendments apply — see the Littleton overview page for the full list.

The City of Littleton's own Building and Code Compliance Division issues all building permits within city limits, regardless of whether the parcel sits in Arapahoe, Douglas, or Jefferson County. Fire review is handled separately by South Metro Fire Rescue, and health-regulated uses (food service, childcare, pools, body art) are reviewed by the relevant county health department.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Littleton.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.