EV Charger / Electric Vehicle Charging Station Permit — Littleton, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.littletonco.gov/Building-Development/Permits-Review-Guides-and-Requirements/Permit-Fee-Schedules
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Littleton, Colorado
The City of Littleton has no dedicated EV-charger or EVSE permit type or fee line. Installing a Level 2 (240V) home EV charger -- whether a hardwired unit or a new NEMA 14-50 outlet -- requires a standard City of Littleton Electrical Permit, billed under the City's general valuation-based Permit Fee Schedule (Resolution 2025-105), reviewed against the locally-adopted 2026 edition of NFPA 70 (National Electrical Code).
Verified 2026-07-20 · Source
When you need this permit
- Electrical work must be performed by a contractor holding an active Colorado DORA Master's/Journeyman's Electrical License and a Colorado State Electrical Contractor's License, in addition to City of Littleton contractor licensing Contractor
- Reviewed against the locally-adopted 2026 edition of NFPA 70 (NEC)
- No EV-specific application, checkbox, or fee category exists; the permit is billed under the same general valuation-based electrical permit fee schedule used for any electrical installation, alteration, or repair
- If the installation requires a panel upgrade or new/upsized electrical service, that work is valued and permitted the same way, at a higher valuation tier
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
New circuit, breaker sizing, and disconnect (if required by the charger manufacturer) verified by City of Littleton Building Development before energizing
See the full Littleton inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'EV charger' or 'EVSE' fee line on Littleton's Permit Fee Schedule -- a home Level 2 charger circuit is billed under the general valuation-based electrical permit fee like any other electrical installation.
- A licensed installer typically pulls the permit and schedules the inspection on your behalf, so most homeowners never visit Building Development in person.
- Confirm your electrical contractor holds both the Colorado DORA Master's/Journeyman's Electrical License and a Colorado State Electrical Contractor's License, plus City of Littleton contractor registration, before work begins. Contractor
- If your installation also requires a panel or service upgrade, expect a higher valuation-tier fee than a simple new-circuit addition.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Littleton
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →