Residential Building Permit (New Single-Family, Townhouse, Two-Family Dwelling) in Littleton, Colorado
Required for new single-family homes, townhouses, and two-family dwellings within Littleton. Reviewed under the 2024 IRC/IBC as locally amended, plus Littleton's adopted structural design criteria (ground snow load, wind speed) under City Code Title 4, Chapter 1. Issued and inspected by the City of Littleton Building and Code Compliance Division.
Verified 2026-07-05 · Source
When you need this permit
- Plans must comply with the 2024 IRC/IBC as adopted by the City of Littleton
- Must meet Littleton's adopted Climatic and Geographic Design Criteria (City Code Title 4, Ch. 1 amending IRC Table R301.2): Ground Snow Load 40 psf (non-reducible), Ultimate Design Wind Speed 136 mph
- Structural plans must be stamped and signed by a Licensed Colorado Structural Engineer; architectural plans must be stamped and signed by a Colorado Design Professional
- Site plan required showing dimensions to property lines, all easements, and existing/proposed structures with a landscaping plan
- Energy Conservation Code compliance required via one of: Prescriptive R-Value/U-Factor, Prescriptive Component Performance Alternative, Simulated Building Performance, or Energy Rating Index
- All contractors working on the project must hold a current City of Littleton Contractor's License and be identified on the permit Contractor
- All documents must be submitted electronically via the eTRAKiT portal; 'preliminary' or 'not for construction' plan sets are not accepted
- Permit must be commenced within 180 days and expires 365 days after issuance unless extended by the Building Official
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour; structural engineer of record (or representative) must inspect and verify any foundation alteration prior to Building Division final approval
- 2
Rough Plumbing / Rough Electrical / Rough Heating
Rough-in of plumbing (waste/vent/water/gas piping, tested), electrical (panel and wiring), and heating (ductwork) before concealment; all three must be inspected and approved before a rough framing inspection can be requested
- 3
Rough Framing
Framing, sub-flooring, stairs; requires prior approval of rough plumbing, rough electrical, and rough heating inspections
- 4
Final Inspection
All work complete per approved plans and applicable codes; owner or contractor must request in advance and ensure site access (no rear/fenced-yard entry without permission, no unoccupied-residence entry)
See the full Littleton inspection guide — scheduling & re-inspection fees →
Tips
- Littleton's adopted design snow load (40 psf) is notably LOWER than several neighboring Front Range jurisdictions (e.g., Golden's 69-83 psf) but its wind speed (136 mph Ultimate Design Wind Speed) still requires code-listed roofing materials rated to specific ASTM/UL standards — don't assume a generic regional design assumption applies.
- Structural and architectural plan sets MUST be stamped by a Colorado-licensed Structural Engineer / Design Professional respectively for new single-family, townhouse, two-family, addition, and ADU submittals — electrical, mechanical, and plumbing plans are not required to be stamped.
- Budget for THREE tax/fee layers beyond the base permit fee: the 65% Plan Review Fee, the City Use Tax Deposit (3.75% City sales/use tax rate applied to 52.5% of valuation), and the Arapahoe County Open Space Tax (0.25% applied to 50% of valuation).
- A permit must be commenced within 180 days and expires 365 days after issuance regardless of activity — track your schedule against these hard deadlines.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Littleton
Residential Building Permit (New Single-Family, Townhouse, Two-Family Dwelling) in other cities
Look up this fee in a different city →
Now live
Build your Littleton project checklist
Describe your project once and get every permit, document, and fee it triggers in Littleton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →