Fire Sprinkler / Fire Alarm System Permit in Littleton, Colorado

Fire protection for Littleton is provided by South Metro Fire Rescue (SMFR), which took over the Littleton Fire Department's duties in 2019. SMFR's Development & Construction Section publishes a detailed 'Systems and Other Fees' schedule (effective January 1, 2026) with itemized Plan Check, Inspection, and Total costs for fire protection system work, e.g.: NFPA 13 sprinkler system modification of ≤50 heads ($344.57 total), 51-300 heads ($414.31), >300 heads ($843.98); Fire Alarm System Modification Base Fee ($461.12, plus $6.12 per additional device); Fire Alarm Control Panel Replacement ($651.92). New fire sprinkler/alarm systems installed as part of new construction or tenant improvements are billed on a separate IBC-occupancy-classification table (base cost plus a per-100-sq-ft increment) rather than the flat modification fees.

Verified 2026-08-14 · Source

When you need this permit

  • Plans submitted via SMFR's Accela Permit Portal; over-the-counter review is available for alterations to existing wet-pipe fire sprinkler systems (light/ordinary hazard, up to 50 sprinkler heads, no hydraulic design impact) and for fire alarm system alterations involving substitution/relocation of up to 25 devices or addition of up to 10 new devices, when submitted by 11:00 a.m.
  • New fire sprinkler and fire alarm systems installed as part of new construction or tenant improvements are billed on SMFR's IBC-occupancy-classification-based fee table (base cost + cost per additional 100 sq ft), not the flat modification fees
  • All SMFR-issued permits and approved plans must remain on-site for the duration of the project; inspections will not be performed without them, and re-inspection fees may apply

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

NFPA 13 Sprinkler System Modification — ≤50 Sprinkler HeadsSMFR Systems and Other Fees, effective 1/1/2026
$344.57 total ($104.61 plan check + $239.96 inspection)
NFPA 13 Sprinkler System Modification — 51-300 Sprinkler HeadsSMFR Systems and Other Fees, effective 1/1/2026
$414.31 total ($174.35 plan check + $239.96 inspection)
NFPA 13 Sprinkler System Modification — >300 Sprinkler HeadsSMFR Systems and Other Fees, effective 1/1/2026
$843.98 total ($244.07 plan check + $599.91 inspection)
Fire Alarm System Modification Base FeeSMFR Systems and Other Fees, effective 1/1/2026
$461.12 total, plus $6.12 per additional device
Fire Alarm Control Panel ReplacementSMFR Systems and Other Fees, effective 1/1/2026
$651.92 total, plus $6.12 per additional device
Fire Alarm System (Sprinkler Monitoring Only)SMFR Systems and Other Fees, effective 1/1/2026
$434.29 total ($153.84 plan check + $280.45 inspection)
Change of Use (fire review)SMFR Systems and Other Fees, effective 1/1/2026 — a fire-code compliance review fee, separate from any City of Littleton building/zoning change-of-use process
$587.99 total ($174.24 plan check + $413.75 inspection)
Re-Inspection Fee / Release of Stop Work OrderSMFR Systems and Other Fees, effective 1/1/2026
$284.63

Review timeline

Plan reviewLittleton’s published plan-review target
Up to 1 business days

How long did your Fire Sprinkler / Fire Alarm System Permit permit actually take in Littleton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Littleton inspection guide — scheduling & re-inspection fees →

    Tips

    • South Metro Fire Rescue's fee schedule prices sprinkler/alarm MODIFICATIONS to an existing system very differently from NEW systems installed with new construction — modifications use flat/tiered fees (e.g., $344.57 for ≤50 heads), while new systems in new construction/tenant improvements are billed on an IBC-occupancy-classification table.
    • SMFR has its own 'Change of Use' fire-review fee ($587.99) separate from whatever change-of-use process the City of Littleton's own Building Division runs — budget for both if your project involves a fire-code-relevant occupancy change.

    Frequently asked questions

    Littleton requires a fire sprinkler / fire alarm system permit for: Plans submitted via SMFR's Accela Permit Portal; over-the-counter review is available for alterations to existing wet-pipe fire sprinkler systems (light/ordinary hazard, up to 50 sprinkler heads, no hydraulic design impact) and for fire alarm system alterations involving substitution/relocation of up to 25 devices or addition of up to 10 new devices, when submitted by 11:00 a.m.; New fire sprinkler and fire alarm systems installed as part of new construction or tenant improvements are billed on SMFR's IBC-occupancy-classification-based fee table (base cost + cost per additional 100 sq ft), not the flat modification fees; All SMFR-issued permits and approved plans must remain on-site for the duration of the project; inspections will not be performed without them, and re-inspection fees may apply. If your project isn't listed, confirm with City of Littleton Building and Code Compliance Division (Community Development Department, Permit Center) at 303-795-3751 before starting work.

    South Metro Fire Rescue (which has served Littleton since absorbing its fire department in 2019) charges tiered flat fees for sprinkler system MODIFICATIONS ($344.57 for up to 50 heads, up to $843.98 for over 300 heads) and a $461.12 base fee (plus $6.12/device) for fire alarm modifications, per its Systems and Other Fees schedule effective 1/1/2026. New systems installed with new construction use a different, IBC-occupancy-based fee table.

    Littleton's published plan-review target for a fire sprinkler / fire alarm system permit is Up to 1 business days.

    You'll need: SMFR Fire Protection System Permit Application (via Accela Permit Portal). See the required-documents checklist on this page for details on each.

    Apply through City of Littleton Building and Code Compliance Division (Community Development Department, Permit Center) at Littleton Center, 2255 W. Berry Avenue, Littleton, CO 80120. Phone: 303-795-3751, email: permits@littletonco.gov. Office hours: Permit Center: Monday-Thursday 8:00 a.m.-4:30 p.m., Fridays closed; in-person walk-in hours limited to Monday 1:00-4:30 p.m. (no walk-ins after 4:15 p.m.) and Thursday 8:00-11:30 a.m.; Building Inspections staff hours 7:30 a.m.-4:30 p.m. Monday-Friday. FAX 720-741-0210, eFax 720-384-0601.. Official information: https://www.littletonco.gov/Building-Development.

    Littleton, Colorado has adopted: 2024 International Building Code (IBC) — City of Littleton Building Codes and Amendments page; 2024 International Residential Code (IRC); 2024 International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC); 2024 International Fuel Gas Code (IFGC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — Littleton uses the International Plumbing Code, not the Uniform Plumbing Code; 2024 International Property Maintenance Code (IPMC); 2024 International Swimming Pool and Spa Code (ISPSC); 2024 International Wildland-Urban Interface Code (IWUIC); 2024 International Fire Code (IFC); ICC A117.1-2017 Standard with Supplement 1 — Accessible and Usable Buildings and Facilities; NFPA 70 National Electrical Code, 2026 Edition ("2026 NEC"); 1997 Uniform Code for the Abatement of Dangerous Buildings (International Conference of Building Officials); Colorado Model Electric Ready and Solar Ready Code, adopted by the Colorado Department of Local Affairs and Colorado Energy Office effective June 1, 2023; Littleton City Code Title 4, Chapter 1 — local IRC amendments including adopted Climatic and Geographic Design Criteria (Table R301.2): Ground Snow Load 40 psf (non-reducible), Ultimate Design Wind Speed 136 mph; Littleton City Code Title 3, Chapter 16 — Contractor Licensing (license/registration required to obtain permits within city limits, effective July 1, 1985). Local amendments apply — see the Littleton overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-08-14.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Littleton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.