Building Permit in Springfield, Colorado
Required for construction of houses, additions, remodels, accessory structures (porches, carports, decks, sheds, storage, garages, fences), and placement of tiny homes, modular homes, or manufactured/mobile homes within Springfield town limits. Issued directly by Town Hall (Town Clerk/Town Manager) under Springfield Municipal Code Chapter 16 (Zoning) — the Town's building code (originally the 2006 IBC) was repealed in its entirety by Ordinance No. 356 (July 2023) and has not been re-adopted, so this permit functions as a zoning/setback/land-use review rather than a model-code plan review. There is no distinct commercial/TI permit: this single Building Permit Application form (03.25.2025) IS the Town's commercial building permit — its 'CLASSIFICATION OF CONSTRUCTION' checkbox row on page 1 lists 'Commercial C-1, C-2' and 'Industrial M-1, M-2' as options alongside SFR/R-1/R-2/Other, using the identical application, review, and fee structure as a residential permit. The Town's Master Fee Schedule (Resolution No. 25-07) contains exactly one 'Building Permits' line item ($50.00 flat + $1.00/$1,000 building cost, capped at $2,000.00) with no commercial-tier surcharge and no separate tenant-improvement (TI) fee anywhere in the schedule. Neither the full 3-page Building Permit Application PDF nor the full 8-page Master Fee Schedule PDF contains a standalone commercial-building-permit or TI-permit application, ordinance provision, or fee line. The only commercial-specific requirement anywhere on the form is a landscaping note: 'Commercial Property: Needs to be 5% to 8% Landscaped or Xeriscape with weed barrier.'
Verified 2026-08-02 · Source
When you need this permit
- Complete Building Permit Application (3-page Town of Springfield form) including legal description (subdivision/block/lot or metes-and-bounds), classification of construction, and type of work
- Setback distances from all four lot lines (front, rear, and N/E/S/W side yards) must be provided; a drawing or survey may be attached
- Required submittal documents: photos, side view, front view, building plans, floor plan, and foundation plan
- Asbestos disturbance certification required on the application (three checkbox options: no inspection conducted, inspection not conducted, or inspection conducted with date)
- Applicant must certify compliance with Springfield Municipal Code Chapter 16 (Zoning); any violation results in immediate permit revocation
- Zoning review is conducted as part of permit issuance — the Town's internal review section checks the property's zoning district and notes whether a Variance from the Board or a Special Use Permit is required
- Water, sewer, electric, and gas service type/size must be documented on the permit with officer initials, but the Town does NOT independently inspect electrical or plumbing work — those inspections are performed by Colorado State Electrical and Plumbing Inspectors, per the permit form's own Inspections checklist ('State electrical', 'State plumbing') and Ordinance No. 355 Sec. 13-158
- For commercial (C-1/C-2) or industrial (M-1/M-2) classification of construction: same application, same review process, and same fee structure as residential — there is no separate commercial building permit or tenant-improvement (TI) permit. The one added requirement specific to commercial property is a landscaping/xeriscape standard: 5% to 8% of the site landscaped or xeriscaped with a weed barrier, stated directly on the Building Permit Application form
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Town zoning/setback review
Conducted by Town Hall staff as part of permit issuance; checks zoning district compliance, variance, or special use permit status
- 2
State Electrical Inspection
Performed by the Colorado State Electrical Inspector, not Town staff, per Ordinance No. 355 Sec. 13-158 and the permit application's own Inspections checklist
- 3
State Plumbing Inspection
Performed by Colorado state plumbing inspectors, not Town staff, per the permit application's Inspections checklist
See the full Springfield inspection guide — scheduling & re-inspection fees →
Tips
- Springfield repealed its entire building code (originally the 2006 IBC) via Ordinance No. 356 in July 2023 and has not re-adopted any model code since — do not assume a specific IBC/IRC edition governs construction in Springfield; the operative authority for this permit is Municipal Code Chapter 16 (Zoning), not a Chapter 18 building code.
- The Town does not inspect electrical or plumbing work itself — both trades are inspected by Colorado State Electrical and Plumbing Inspectors. Coordinate state inspection scheduling directly rather than expecting a Town building inspector to show up.
- The Building Cost Fee is capped at $2,000.00 regardless of project valuation above $2,000,000 — a useful ceiling for larger commercial or multi-unit projects.
- An asbestos certification is required on every application, even if no inspection has been conducted — the form provides an explicit checkbox for 'I do not know if an inspection has been conducted,' so don't assume this section is optional.
- Don't search for a separate 'commercial building permit' or 'tenant improvement permit' for Springfield — none exists. Commercial (C-1/C-2) and industrial (M-1/M-2) projects use this same Building Permit Application and the same flat-fee structure as a residential project; the only added requirement is a 5%-8% landscaping/xeriscape standard for commercial property, stated directly on the application form.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Springfield's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Springfield yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Springfield lands. Privacy.
Other permits in Springfield
Building Permit in other cities
Compare building permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Springfield project checklist
Describe your project once and get every permit, document, and fee it triggers in Springfield — in one checklist. Free, for any city and any number of projects.