How to schedule
Inspections are requested through the building department below.
- Address
- 50 Lundgren Blvd, Gypsum, CO 81637 (mailing: PO Box 130, Gypsum, CO 81637)
- Phone
- 970-524-1731
- Office hours
- Building Department Staff available Monday-Friday, 8 a.m.-5 p.m., per the Building Permit Application page. Primary staff contact listed: Stephanie Roybal, Building Department Administrative Assistant. General Town phone line also published as 970-524-7514 on several Building Department sub-pages (DRB/HOA Review, Hours & Site Conditions).
- Website
- Official site
Published scheduling rules
- A 24-hour advance notice is required to schedule any inspection, and the base permit fee only covers four inspections — plan your inspection sequence to avoid the $60 additional-inspection fee stacking up. (Residential Building Permit (New Construction))
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing
Before concrete placement; minimum 42-inch depth below finish grade, soils report required
- 2
Foundation Wall
Before concrete placement, forms and reinforcing steel in place
- 3
Groundwork
Before base course installation; water service lines inspected by Public Works
- 4
Backfill
Before foundation backfilling; drainage and waterproofing compliance
- 5
Rough-in/Framing
Before installation of insulating material
- 6
Electric & Gas Service
After all installations and pressure testing
- 7
Lath/Insulation/Drywall
During finishing stages
- 8
Planning and Engineering Department Inspection (commercial/multi-family only)
A completed and approved inspection by the Planning and Engineering Department is required for commercial projects before CO — a commercial-specific step not applied to single-family residential
- 9
Fire Department Review/Approval (where required)
Fire Department review and approval of commercial or multi-family projects where required, per the Inspections page
- 10
TCO/COO
Commercial TCO requires a $3,000 deposit, runs max 90 days, extension not past July 1st of the following year; Improvement Location Survey required before final CO
Applies to: Residential Building Permit (New Construction)
- 1
Footing
Before concrete placement
- 2
Foundation Wall
Before concrete placement
- 3
Groundwork
Before base course installation
- 4
Backfill
Before foundation backfilling
- 5
Rough-in/Framing
Before insulation and wall covering
- 6
Electric & Gas Service
After utilities are installed
- 7
Lath/Insulation/Drywall
During finishing stages
- 8
TCO/COO (Temporary/Final Certificate of Occupancy)
Improvement Location Survey required before Certificate of Occupancy is issued
Applies to: Residential Addition / Remodel Permit
- 1
Footing/Foundation (additions with new footings only)
Before concrete placement, per 42-inch minimum frost depth
- 2
Rough-in/Framing
Framing complete, connection to existing structure verified, before insulation and wall covering
- 3
Electric & Gas Service
After utilities are installed
- 4
Lath/Insulation/Drywall
During finishing stages
- 5
TCO/COO
Final inspection and occupancy certificate
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment (part of the general Rough-in inspection)
- 2
Electric & Gas Service
For gas-fired equipment, coordinated with the gas service inspection
- 3
TCO/COO
Final inspection, equipment operational
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Standard Building Permit Inspection Sequence
Follows the same footing/foundation/rough-in/final sequence as new construction or an addition, depending on ADU type (detached, attached, garage conversion, etc.)
- 2
Re-inspection (ADU transfer)
Required when an existing approved ADU transfers to a new owner
Applies to: Electrical Permit
- 1
Electric & Gas Service
Rough and/or service inspection after wiring and panel installed, before concealment
- 2
TCO/COO
Final inspection, devices and panel verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment (part of the general Rough-in inspection)
- 2
TCO/COO
Final inspection, fixtures connected, no leaks
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement verified before energizing
- 2
Final Inspection
Racking/roof-penetration attachment, electrical connections, and interconnection point verified
Final inspection only: EV Charger / Electric Vehicle Charging Station Permit, Roofing Permit (Re-Roof)
Re-inspection fees
Plumbing Permit Fee · Sec. 15.02.030, Table 3 ("Plumbing permit and related inspection fees"). Show full citationHide
Plumbing Permit Fee · Sec. 15.02.030, Table 3 ("Plumbing permit and related inspection fees"). Worked example quoted verbatim from the code: "The plumbing permit fee for an installation with a total value of $8,400.00 would be $204.00, calculated as a $60.00 base fee + (9 x $16.00 additional fee)." Fees include three inspections (underground, rough-in, final); re-inspection fees are set out in the same section. Sec. 15.01.100 additionally provides that "Minimum permit and inspection fees shall comply with the minimum stated in Table 3 of this chapter", so Table 3 sets the floor for other permit types too. The full tier table is not reproduced here, so the increment boundary is not asserted. Town of Gypsum Code of Ordinances, Title 15 (BUILDINGS AND CONSTRUCTION), Chapter 15.02 (TABLES). Title 15 was repealed and re-enacted in full by Ord. No. 2023-08, § 1(Exh. A), 2023-06-27; code current through Ord. No. 2025-18, enacted 2026-01-13 (Supp. No. 22). Code text as published on library.municode.com (accessed 2026-08-17).Mechanical Permit Fee · Sec. 15.02.020, Table 2 ("Mechanical permit and related inspection fees"). Show full citationHide
Mechanical Permit Fee · Sec. 15.02.020, Table 2 ("Mechanical permit and related inspection fees"). The code states the fee "include[s] three inspections — underground, rough-in and final inspections — and additional fees for re-inspections are as set forth in the table below", and gives this worked example verbatim: "The mechanical permit fee for an installation with a total value of $8,400 would be $204. [$60 base fee + (9 x $16 additional fee)]". The formula and worked example are quoted directly from the code, but the full tier table is not reproduced here, so the increment boundary is not asserted — confirm the exact bracket with the Building Official for a specific valuation. Town of Gypsum Code of Ordinances, Title 15 (BUILDINGS AND CONSTRUCTION), Chapter 15.02 (TABLES). Title 15 was repealed and re-enacted in full by Ord. No. 2023-08, § 1(Exh. A), 2023-06-27; code current through Ord. No. 2025-18, enacted 2026-01-13 (Supp. No. 22). Code text as published on library.municode.com (accessed 2026-08-17).Utility Connection Inspection - Commercial (charged with building permit) · New fact confirmed 2026-08-02 via Resolution No. Show full citationHide
Utility Connection Inspection - Commercial (charged with building permit) · New fact confirmed 2026-08-02 via Resolution No. 29 (Series 2025), Exhibit A, Community Development section: 'Utility Connection Inspection - Commercial (charged with building permit)' rose from $300 (2025) to $400 (2026), effective 1/1/2026. Distinct from the general Additional/Re-inspection Fee below; corresponds to the utility-connection inspection required at TCO/CO stage per Gypsum Municipal Code Sec. 15.01.080(16)/15.01.090(12).Sources & verification
Verified against official sources. Last reviewed 2026-08-17.
Fee schedules
Applications & forms
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gypsum building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Gypsum building permits
Get alerts for Gypsum
We'll email you when Gypsum's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.