Residential Building Permit (New Construction) in Lakewood, Colorado

Required for new single-family detached homes, duplexes, townhomes, and new multi-family buildings in the City of Lakewood, plus new accessory dwelling units and modular/move-set residential buildings. Reviewed against the 2021 IRC/IBC with Lakewood Municipal Code Title 14 amendments. Applied for as 'Building Residential New' in eTRAKiT.

Verified 2026-06-30 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building Permit Fee — valuation $1.00 to $500.00$26.00City of Lakewood Building Permit & Inspection Fee Schedule, effective Jan 1, 2021 (current published schedule as of 2026-06-30; the source document itself notes fees 'change periodically' — call 303-987-7500 to verify current amount)
Building Permit Fee — valuation $501.00 to $2,000.00$26.00 for the first $500.00 plus $3.45 for each additional $100.00 or fraction thereof
Building Permit Fee — valuation $2,001.00 to $25,000.00$77.75 for the first $2,000.00 plus $13.80 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $25,001.00 to $50,000.00$395.15 for the first $25,000.00 plus $9.20 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $50,001.00 to $100,000.00$625.15 for the first $50,000.00 plus $6.90 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $100,001.00 to $500,000.00$970.15 for the first $100,000.00 plus $5.75 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $500,001.00 to $1,000,000.00$3,270.15 for the first $500,000.00 plus $4.60 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $1,000,001.00 and up$5,570.15 for the first $1,000,000.00 plus $3.45 for each additional $1,000.00 or fraction thereof
Plan Review Fee65% of the building permit feeMasterplan for single-family: initial use = 65% of permit fee; second and subsequent use of same masterplan = $325.00 each use
Estimated Use Tax3% of 50% of the project valuationCollected in addition to permit and plan review fees; valuation/use tax/permit fees are subject to audit
Temporary Certificate of Occupancy$1,000.00 initial issuance or extension ($500.00 refunded if converted to Final CO before TCO expiration)

Review timeline

~00 business days

Typical estimate — confirm current times with the Lakewood building department

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend below 36-inch frost depth

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Final

    All work complete; City issues Certificate of Occupancy for new home projects once all required inspections pass

Tips

Frequently asked questions

What building code edition does Lakewood, Colorado use?
The City of Lakewood has adopted the 2021 International Building Code (IBC), 2021 IRC, and related 2021 I-Codes (IPC, IMC, IFGC, IECC, IEBC, IFC, ISPSC, IPMC), plus the 2023 National Electrical Code, per the City of Lakewood Codes and Loads permit handout. Local amendments are codified in Lakewood Municipal Code Title 14, adopted by City Council on May 8, 2023, effective June 30, 2023.
Can a homeowner pull their own building permit in Lakewood?
Yes, if you are the owner and occupant of a single-family DETACHED home performing the work yourself. You must establish an eTRAKiT account and complete a Homeowner Permit Agreement. Owner-occupants of townhomes/duplexes may qualify in some circumstances; LLCs, trusts, and corporations are never issued homeowner permits.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lakewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Lakewood

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.