Solar PV Permit — Lakewood, Colorado · Requirements sheet
Verified 2026-07-01 · Source: https://www.lakewoodco.gov/Local-Government/Departments/Public-Works/Building-and-Construction-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Lakewood, Colorado
Required for installation of rooftop or ground-mounted solar photovoltaic (PV) or thermal systems on residential and commercial properties in Lakewood. Applied for in eTRAKiT under Permit Type 'Alternative Energy' (New Residential / New Commercial / Remove and Reset PV / Remove and Reset Thermal / Wind or Other).
Verified 2026-07-01 · Source
When you need this permit
- eTRAKiT Permit Type 'Alternative Energy' with subtypes: New Commercial (PV or thermal system on commercial building), New Residential (PV or thermal system on residential building), Remove and Reset PV (for reroof/roof alteration or system repair), Remove and Reset Thermal, Wind or Other (wind tower, wind mill, or other alternative energy system)
- Electrical permit and inspection required for grid interconnection per the 2023 NEC (Article 690 solar-specific provisions)
- Structural adequacy of the roof for panel/racking loads must be demonstrated given Lakewood's 30 psf minimum roof snow/live load design criteria
- All solar contractors must be registered with the City of Lakewood via eTRAKiT
- Removing and resetting an existing PV system for a reroof or roof alteration uses the distinct 'Remove and Reset PV' subtype rather than a new-install subtype
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Unlike Denver, which publishes a flat $50 PV fee, Lakewood has no Alternative-Energy-specific line in its Flat Fee Permits table, so Solar PV and solar thermal fall under the fee schedule's own… Show full citationHide
Unlike Denver, which publishes a flat $50 PV fee, Lakewood has no Alternative-Energy-specific line in its Flat Fee Permits table, so Solar PV and solar thermal fall under the fee schedule's own governing rule: 'With the exception of the fees listed in the FLAT FEE PERMITS table, all building permit fees are based on total valuation including labor and materials.' Alternative Energy and Solar are absent from the Flat Fee list (fence, water heater, furnace, A/C, evaporative cooler, siding, reroof, temp trailer, demolition, move-and-set) and from any separate solar fee table in the 2-page schedule. A companion Electrical permit and inspection is also required for grid interconnection per 2023 NEC Article 690, separately fee-bearing on the same valuation-based schedule.Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final — Structural / Electrical
Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified
See the full Lakewood inspection guide — scheduling & re-inspection fees →
Tips
- Lakewood's Alternative Energy permit type explicitly separates 'New' installs from 'Remove and Reset' (for reroofs/repairs) — apply for the correct subtype in eTRAKiT to avoid delays.
- Structural calculations must account for Lakewood's 30 psf minimum roof snow/live load and Seismic Design Category B (residential) per the City's Codes and Loads handout.
- Unlike Denver, which publishes a flat $50 solar PV fee, Lakewood has no Alternative-Energy line in its Flat Fee Permits table — solar/thermal is billed on the standard valuation-based Building Permit Fee schedule instead, plus a separate Electrical permit for grid interconnection.
- The City's Building and Construction Permits page carries no Lakewood-specific SolarAPP+ (instant online solar permitting) reference — do not assume SolarAPP+ applies here without confirming with the Permit Counter (303-987-7500).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fee schedules
Checklists & handouts
Online permit portal
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lakewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lakewood's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Lakewood yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Lakewood lands. Privacy.
Other permits in Lakewood
Solar PV Permit in other cities
Compare solar pv permit fees across Colorado →
Look up this fee in a different city →