Solar PV Permit in Lakewood, Colorado
Required for installation of rooftop or ground-mounted solar photovoltaic (PV) or thermal systems on residential and commercial properties in Lakewood. Applied for in eTRAKiT under Permit Type 'Alternative Energy' (New Residential / New Commercial / Remove and Reset PV / Remove and Reset Thermal / Wind or Other).
Verified 2026-07-01 · Source
When you need this permit
- eTRAKiT Permit Type 'Alternative Energy' with subtypes: New Commercial (PV or thermal system on commercial building), New Residential (PV or thermal system on residential building), Remove and Reset PV (for reroof/roof alteration or system repair), Remove and Reset Thermal, Wind or Other (wind tower, wind mill, or other alternative energy system)
- Electrical permit and inspection required for grid interconnection per the 2023 NEC (Article 690 solar-specific provisions)
- Structural adequacy of the roof for panel/racking loads must be demonstrated given Lakewood's 30 psf minimum roof snow/live load design criteria
- All solar contractors must be registered with the City of Lakewood via eTRAKiT
- Removing and resetting an existing PV system for a reroof or roof alteration uses the distinct 'Remove and Reset PV' subtype rather than a new-install subtype
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final — Structural / Electrical
Panel mounting, racking attachment, roof penetration sealing, and all electrical connections verified
See the full Lakewood inspection guide — scheduling & re-inspection fees →
Tips
- Lakewood's Alternative Energy permit type explicitly separates 'New' installs from 'Remove and Reset' (for reroofs/repairs) — apply for the correct subtype in eTRAKiT to avoid delays.
- Structural calculations must account for Lakewood's 30 psf minimum roof snow/live load and Seismic Design Category B (residential) per the City's Codes and Loads handout.
- Unlike Denver, which publishes a flat $50 solar PV fee, Lakewood has no Alternative-Energy line in its Flat Fee Permits table — solar/thermal is billed on the standard valuation-based Building Permit Fee schedule instead, plus a separate Electrical permit for grid interconnection.
- No Lakewood-specific SolarAPP+ (instant online solar permitting) reference was found on the City's own Building and Construction Permits page as of this verification — do not assume SolarAPP+ applies here without confirming directly with the Permit Counter (303-987-7500).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lakewood building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lakewood
Solar PV Permit in other cities
Compare solar pv permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Lakewood project checklist
Describe your project once and get every permit, document, and fee it triggers in Lakewood — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →