Required for new commercial construction, shell buildings, and commercial remodels/additions in the Town of Mountain View. Researched 2026-08-02 to determine whether Mountain View issues its own commercial permits or routes them through Jefferson County or a regional/shared building department (the pattern used by several peer small Jefferson County towns) — it does NOT route out: the Town's own live Building Department page states directly, 'The Town of Mountain View contracts with an independent company, called SAFEbuilt, to help with new construction, remodeling and development projects for both Residential and Commercial work within the Town of Mountain View' (read live at tomv.org/building-department, 2026-08-02). Mountain View runs the same in-house (SAFEbuilt-administered) Building Department program for commercial work that it uses for residential work — commercial permits are not a Jefferson County unincorporated-area function and are not contracted out to a different peer town's department. Reviewed under the 2021 IBC (Municipal Code Chapter 18, Article 4, already confirmed live elsewhere in this record, whose text states its provisions 'shall apply to the construction of, and renovations or additions to, all commercial and residential buildings within the Town') plus the same current-edition NEC/IPC/IMC/IFC provisions documented in the codesAdopted. The Town's own Building Permit Application (tomv.org/media/11, read directly 2026-08-02) has a dedicated 'Commercial' block under Section (B) Proposed Use with 'Shell Only,' 'Remodel/Addition,' 'New Building,' and 'Sign' checkboxes, distinct from the Residential block above it. 'Tenant Finish' — also checkboxed in that same Commercial block — is modeled as its own separate permitType (see tenant-improvement-permit) since the Town's own form treats it as a distinct project type from new construction/shell/remodel work.

Verified 2026-08-02 · Source

When you need this permit

  • Submit the same combined Town of Mountain View Building Permit Application used for all Building Department permits (paper/PDF or CommunityCore), checking 'Commercial' under Proposed Use and the applicable Shell Only / Remodel-Addition / New Building box
  • Section (G) Occupancy of the Application requires stating an Occupancy Classification, a Construction Type, and whether uses are Separated or Non-Separated — standard IBC commercial-occupancy fields that do not appear on the Residential portion of the form
  • No Town of Mountain View contractor license or registration is required (same policy as residential work), but contractors must create a CommunityCore login and supply any state or other-municipality license they hold Contractor
  • Use Tax (job-materials valuation x 50% x 4% Town use-tax rate) is due at permit issuance, calculated the same way as residential projects; project valuation is determined by the Town Building Inspector using the ICC Building Valuation Data table — see the fees[] note below on the resolution of a rate discrepancy between two live Town-sourced documents
  • GOVERNING FIGURE: per Municipal Code §18.02.040 (already confirmed live elsewhere in this record), work must commence within 60 days of permit issuance and be substantially completed within 2 years, or the permit expires/is cancelled by the Town; the Building Permit Application's own printed Notice section separately states a conflicting 180-day figure — the same documented discrepancy that applies to every other Town permit type in this record
  • Commercial construction is also subject to the 2021 International Fire Code (Municipal Code Chapter 18, Article 5, as amended by West Metro Fire Protection District Resolution No. 2022-08, already confirmed live elsewhere in this record); the Town's Building Department FAQ states its published review timeframes reflect Building Department plan review only and explicitly exclude Planning & Zoning, Engineering/ROW, and Fire Department review time

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Permit Fee
Resolution No. 2024-12-16H, Exhibit A, 'Town of Mountain View Fee Schedule' (tomv.org/media/2046, PDF, 'Updated 12/12/2024'): the 'BUILDING PERMIT FEES SET BY RESOLUTION' table is a single, universal… Show full citationResolution No. 2024-12-16H, Exhibit A, 'Town of Mountain View Fee Schedule' (tomv.org/media/2046, PDF, 'Updated 12/12/2024'): the 'BUILDING PERMIT FEES SET BY RESOLUTION' table is a single, universal valuation-based schedule with NO separate residential/commercial columns, so it governs commercial project valuations exactly as it does residential ones.
$40.00 for total valuation $1.00-$500.00; $40.00 for the first $500.00 plus $2.00 per additional $100.00 (or fraction) from $501.00-$2,000.00; $70.00 for the first $2,000.00 plus $14.00 per additional $1,000.00 (or fraction) from $2,001.00-$25,000.00; $391.25 for the first $25,000.00 plus $10.10 per additional $1,000.00 (or fraction) from $25,001.00-$50,000.00; $643.75 for the first $50,000.00 plus $7.00 per additional $1,000.00 (or fraction) from $50,001.00-$100,000.00; $993.75 for the first $100,000.00 plus $5.60 per additional $1,000.00 (or fraction) from $100,001.00-$500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 per additional $1,000.00 (or fraction) from $500,001.00-$1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 per additional $1,000.00 (or fraction) above $1,000,000.00
Plan Review FeeExhibit A Fee Schedule, 'Plan Review Fees by Resolution' table: 'Plan Review Fee — 65% of the Building Permit Fee'. Must be paid up front, prior to plan review, per the Building Department FAQ.
65% of the Building Permit Fee
Use Tax
The Town's live Building Department FAQ page states: 'Use Tax = total valuation x 50 percent x 4 percent.' The Town's dedicated Use Tax Guidelines PDF ('Last Updated 2022', tomv.org/media/26) states… Show full citationThe Town's live Building Department FAQ page states: 'Use Tax = total valuation x 50 percent x 4 percent.' The Town's dedicated Use Tax Guidelines PDF ('Last Updated 2022', tomv.org/media/26) states and worked-examples an older 3% rate: 'Town tax rate (3%) X 3%... Use tax due at time of permit $1,500' (on a $100,000 job). Because the current tomv.org page governs over an older/superseded document (see tipsAndGotchas regarding the conflicting legacy review-timeline page), the live FAQ's 4% figure is treated as governing; the Guidelines PDF's 3% figure and undated 'Last Updated 2022' stamp mark it as the stale document. On a $100,000 job: $50,000 assumed materials x 4% = $2,000 use tax due at permit issuance.
Total project valuation x 50% (assumed materials share) x 4% (Town use-tax rate)
Commercial Sewer Tap Fee (new/upsized taps only)
Found 2026-08-02 directly in Resolution No. Show full citationFound 2026-08-02 directly in Resolution No. 2024-12-16H, Exhibit A Fee Schedule, Chapter 13 - Municipal Utilities section ('Sewer Connection tap fees for Commercial Sewer Taps'). Applies only when a project requires a new or upsized sewer tap (typically new commercial construction) — not a general commercial-building-permit line item and not applicable to remodels/tenant finishes reusing an existing tap.
Town Fees: 3/4-inch tap $2,445.00; 1-inch tap $5,831.00. Metro Water Recovery Fees (separate, pass-through): 3/4-inch tap $8,680.00; 1-inch tap $20,832.00

Review timeline

Plan reviewMountain View’s published plan-review target
10–30 business days

How long did your Commercial Building Permit (New Construction / Shell / Remodel / Addition) permit actually take in Mountain View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Setback

    Verifies footing/foundation placement and required setbacks before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Fire/Life-Safety (if applicable)

    Coordination with West Metro Fire Protection District under the Town's adopted 2021 IFC (Chapter 18, Article 5) for occupancies requiring fire-suppression/alarm review; not separately itemized by the Building Department's own inspection list

  5. 5

    Final Inspection / Certificate of Occupancy

    All work complete per approved plans; Municipal Code Chapter 18, Article 2 governs Building Permits and Certificates of Occupancy together

See the full Mountain View inspection guide — scheduling & re-inspection fees →

Tips

  • No dedicated commercial submittal checklist/handout is published — the Town's Helpful Building Permit Handouts page lists only residential guides (Garage, Additions, Basement Finish, Decks, Patio Cover, Enclosing a Patio Cover, Single Family Ramps, Residential Re-roof); commercial applicants should contact SAFEbuilt's Chief Building Official or Planning & Zoning staff directly for submittal requirements.
  • Mountain View is a very small (~530-resident, twelve-block) town, but it does have an active local commercial corridor (the Town's own 'Local Businesses' page lists over 15 businesses along Sheridan Blvd, including a fitness studio, dental office, vision center, liquor store, and auto-service shop) — commercial permitting is a real, active category here, not a purely theoretical one.
  • A new or upsized sewer tap for commercial construction carries its own separate Town + Metro Water Recovery tap fee, well above the general valuation-based Building Permit Fee — confirm tap sizing needs with the Building Department/Public Works before budgeting.

Frequently asked questions

Mountain View requires a commercial building permit (new construction / shell / remodel / addition) for: Submit the same combined Town of Mountain View Building Permit Application used for all Building Department permits (paper/PDF or CommunityCore), checking 'Commercial' under Proposed Use and the applicable Shell Only / Remodel-Addition / New Building box; Section (G) Occupancy of the Application requires stating an Occupancy Classification, a Construction Type, and whether uses are Separated or Non-Separated — standard IBC commercial-occupancy fields that do not appear on the Residential portion of the form; No Town of Mountain View contractor license or registration is required (same policy as residential work), but contractors must create a CommunityCore login and supply any state or other-municipality license they hold; Use Tax (job-materials valuation x 50% x 4% Town use-tax rate) is due at permit issuance, calculated the same way as residential projects; project valuation is determined by the Town Building Inspector using the ICC Building Valuation Data table — see the fees[] note below on the resolution of a rate discrepancy between two live Town-sourced documents; GOVERNING FIGURE: per Municipal Code §18.02.040 (already confirmed live elsewhere in this record), work must commence within 60 days of permit issuance and be substantially completed within 2 years, or the permit expires/is cancelled by the Town; the Building Permit Application's own printed Notice section separately states a conflicting 180-day figure — the same documented discrepancy that applies to every other Town permit type in this record; Commercial construction is also subject to the 2021 International Fire Code (Municipal Code Chapter 18, Article 5, as amended by West Metro Fire Protection District Resolution No. 2022-08, already confirmed live elsewhere in this record); the Town's Building Department FAQ states its published review timeframes reflect Building Department plan review only and explicitly exclude Planning & Zoning, Engineering/ROW, and Fire Department review time. If your project isn't listed, confirm with Town of Mountain View Building Department (administered by SAFEbuilt under contract) at (303) 450-8746 before starting work.

In Mountain View, the published Permit Fee is: $40.00 for total valuation $1.00-$500.00; $40.00 for the first $500.00 plus $2.00 per additional $100.00 (or fraction) from $501.00-$2,000.00; $70.00 for the first $2,000.00 plus $14.00 per additional $1,000.00 (or fraction) from $2,001.00-$25,000.00; $391.25 for the first $25,000.00 plus $10.10 per additional $1,000.00 (or fraction) from $25,001.00-$50,000.00; $643.75 for the first $50,000.00 plus $7.00 per additional $1,000.00 (or fraction) from $50,001.00-$100,000.00; $993.75 for the first $100,000.00 plus $5.60 per additional $1,000.00 (or fraction) from $100,001.00-$500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 per additional $1,000.00 (or fraction) from $500,001.00-$1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 per additional $1,000.00 (or fraction) above $1,000,000.00. Additional published fees: Plan Review Fee — 65% of the Building Permit Fee; Use Tax — Total project valuation x 50% (assumed materials share) x 4% (Town use-tax rate); Commercial Sewer Tap Fee (new/upsized taps only) — Town Fees: 3/4-inch tap $2,445.00; 1-inch tap $5,831.00. Metro Water Recovery Fees (separate, pass-through): 3/4-inch tap $8,680.00; 1-inch tap $20,832.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town publishes a two-tier figure by project valuation: 10-20 business days for a commercial job under $1 million, and 21-30 business days for a commercial job over $1 million (Building Department review only; Planning & Zoning, Engineering, or Fire Department review may add time).

You'll need: Building Permit Application (Commercial Proposed Use + Occupancy sections); Plot Plan / Site Plan; Use Tax Calculation; Proof of Liability Insurance. Depending on your project, Mountain View may also ask for: Contractor's License Copy. See the required-documents checklist on this page for details on each.

Mountain View requires 5 inspection(s) for a commercial building permit (new construction / shell / remodel / addition), in order: Foundation/Setback, Rough Framing, Rough Electrical / Plumbing / Mechanical, Fire/Life-Safety (if applicable), Final Inspection / Certificate of Occupancy. Schedule each through Town of Mountain View Building Department (administered by SAFEbuilt under contract) ((303) 450-8746).

Apply through Town of Mountain View Building Department (administered by SAFEbuilt under contract) at Mountain View Town Hall, 4176 Benton Street, Mountain View, CO 80212. Phone: (303) 450-8746, email: Buildingpermits@tomv.org. Office hours: Building division operates weekdays 8:00 a.m.-5:00 p.m. (Town's FAQ page prints this as '8:00 a.m. - 5:00 a.m.', which is evidently a typo for 5:00 p.m. given the Town Hall's own general business hours; noted honestly rather than silently corrected without flagging). Inspection request line (303) 450-8748 — call by 4:00 p.m. for next-business-day inspection. Town Hall main line (303) 421-7282.. Official information: https://www.tomv.org/building-department.

Mountain View, Colorado has adopted: 2021 International Residential Code (IRC) — referenced as the current adopted standard on the Town's 'Helpful Building Permit Handouts' page (page title/meta-description: 'Handouts developed by the Colorado Chapter of the International Code Council as a basic plan submittal under the 2021 International Residential Code') and cross-confirmed on the Town's own Building Permit Application (page 3, Homeowner Electrical/Plumbing certification): 'in accordance with the current edition of the National Electric Code, International Residential Code, and International Plumbing Code adopted by the Town of Mountain View as the minimum standard.'; National Electrical Code (NEC) — current edition, per the same Building Permit Application homeowner-certification language; the Town's live public-facing pages do not print the specific NEC year cycle (e.g. 2020 vs 2023) anywhere checked (Building Department page, Building Permits page, Handouts page, Application PDF) — noted as a gap rather than guessed.; International Plumbing Code (IPC), 2021 Edition — per the Town's own codified Municipal Code §18.08.010 ('International Plumbing Code adopted,' mountainview.municipal.codes/Code/18.8): 'The International Plumbing Code, 2021 Edition... is adopted by reference... The provisions of the International Plumbing Code shall apply to the construction of, and renovations or additions to, all commercial and residential buildings within the Town.' (Ord. 2024-07-15A §17; Ord. 2019-02-11F §1; Ord. 2010-7 §4). The Building Department's public-facing webpages do not print the specific year cycle; the Municipal Code's own codified Article 8 does.; An older page is still online from the Town's previous CivicLive-hosted site (mountainviewco.hosted.civiclive.com/services/building_department_/building_permits, and its townofmountainviewcolorado.org mirror) stating that 'The 2015 International Building Code is the official adopted reference for building codes and applicable to Mountain View, effective March 28, 2019.' That page predates the Town's current SAFEbuilt-administered site at tomv.org and its CommunityCore permitting system. Work from the Town's live Helpful Building Permit Handouts page, which references the 2021 IRC-based ICC Colorado Chapter guides, and confirm the adopted edition with the Building Department before designing to the older page.; The Town's Municipal Code Chapter 18 (Building Regulations, mountainview.municipal.codes/Code/18) adopts the following editions, each quoted directly from its codified section: International Fire Code (IFC), 2021 Edition — §18.05.010 ('The International Fire Code, 2021 Edition... is adopted by reference'; Ord. 2024-07-15A §11), further amended per West Metro Fire Protection District Resolution No. 2022-08 (§18.05.030). International Mechanical Code (IMC), 2021 Edition — §18.07.010 (Ord. 2024-07-15A §14; Ord. 2019-02-11E §1; Ord. 2010-7 §4). International Plumbing Code (IPC), 2021 Edition — §18.08.010 (Ord. 2024-07-15A §17; see also the dedicated IPC codesAdopted entry above). International Fuel Gas Code (IFGC), 2015 Edition — §18.11.010 ('The International Fuel Gas Code, 2015 Edition... is adopted by reference'; Ord. 2019-02-11H §1) — notably NOT bumped to 2021 by the Town's 2024-07-15A omnibus code-update ordinance, unlike every other International code family in Chapter 18; this lag is a real, confirmed feature of the Town's current code. International Existing Building Code (IEBC), 2021 Edition — §18.12.010 (Ord. 2024-07-15A §19; Ord. 2019-02-11G §1). International Energy Conservation Code (IECC), 2021 Edition — §18.045.010 (Ord. 2024-07-15A §9); see also the dedicated HB22-1362 entry below, which this same Article resolves. Every Article states its provisions 'shall apply to the construction of, and renovations or additions to, all commercial and residential buildings within the Town' (near-identical boilerplate in each Article), so none of these adopted codes are residential- or commercial-only carve-outs.; No IBC, IFC, IMC, IFGC, IECC, or IEBC edition is printed anywhere on the Town's live public-facing pages, its Building Permit Application, or its Use Tax Guidelines — Mountain View's public-facing materials are IRC/NEC/IPC-focused. The Town's Municipal Code Chapter 18 (Building Regulations, mountainview.municipal.codes/Code/18) does, however, include dedicated Articles for the IBC (Art. 4, 2021 Edition, Ord. 2024-07-15A/2019-02-11A/2010-7), IRC (Art. 13, 2021 Edition, Ord. 2024-07-15A/2019-02-11I), Fire Code (Art. 5), Mechanical Code (Art. 7), Fuel Gas Code (Art. 11), Existing Building Code (Art. 12), and Energy Conservation Code (Art. 4.5). The IBC and IRC edition years (2021) are confirmed from Articles 4 and 13; the specific edition years adopted in Articles 5/7/8/11/12/4.5 (covering the IFC, IMC, IFGC, IEBC, and IECC) are not stated in the Town's public-facing materials and are not recorded here rather than assumed — see the entry above for the confirmed figures.; The Town has taken its own HB22-1362 adoption action, codified directly in Municipal Code §18.045.010 (Article 4.5, Energy Conservation Code, mountainview.municipal.codes/Code/18.4.5): 'In addition to the IECC, the Town of Mountain View will also be adopting the Colorado Model Electric Ready and Solar Ready Code as required by State law under HB22-1362. These requirements will be in addition to those found in this Code.' (Ord. 2024-07-15A §9). The same Article's amendments (§18.045.020) further amend IECC Sections C401.2 and R401.2 to require commercial and residential buildings, respectively, to 'comply with the Colorado Model Electric Ready and Solar Ready Code.' The codified ordinance itself thus directly and specifically confirms the Town's HB22-1362 compliance action.; Superseded by the entry above; retained for the record. HB22-1362 (Colorado's statewide building energy code / greenhouse-gas-emissions law, requiring local governments to adopt an energy code and, per its later compliance milestones, the Colorado Electric and Solar Ready Code) is not mentioned anywhere on the Town's live Building Department, Building Permits, or Helpful Handouts pages. Given Mountain View's tiny size and thin published program (no separate energy-code page, no mechanical/energy-specific permit-type page), public sources do not establish whether the Town has taken its own HB22-1362 adoption action or is relying on some other mechanism; this is left unresolved rather than stated as fact either way.. Local amendments apply — see the Mountain View overview page for the full list.

Mountain View issues its own commercial building permits directly, administered under contract by SAFEbuilt — the same arrangement used for the Town's residential permits. The Town's Building Department page states this explicitly: SAFEbuilt helps with 'new construction, remodeling and development projects for both Residential and Commercial work within the Town of Mountain View.' Commercial permitting is not a Jefferson County unincorporated-area function, and Mountain View does not share a building department with any peer town.

Sources & verification

Verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Mountain View building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Mountain View.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Mountain View's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Mountain View yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Mountain View lands. Privacy.