Residential Building Permit (New Construction) in Mountain View, Colorado

Required for new single-family or multi-family residential construction in the Town of Mountain View. Reviewed by SAFEbuilt on behalf of the Town's Building Department under the 2021 IRC (as referenced in the Town's current Helpful Building Permit Handouts and Building Permit Application) plus current-edition NEC and IPC for electrical/plumbing systems.

Verified 2026-07-23 · Source

When you need this permit

  • Submit a completed Town of Mountain View Building Permit Application (paper/PDF or via the CommunityCore online portal) with a Plot Plan and Use Tax Calculation valuation form
  • No Town of Mountain View contractor license or registration is required, but all work must meet applicable municipal and building code requirements; contractors must create a CommunityCore login for registration/user-interface purposes Contractor
  • A completed application, use-tax valuation form, copy of contractor's license (if applicable, from any surrounding municipality), and proof of contractor's liability insurance must be emailed to the Building Department to obtain a permit Contractor
  • Use Tax (50% of total project valuation x 3% Town use-tax rate) is due at time of permit issuance; project valuation is determined by the Town Building Inspector using the ICC Building Valuation Data table
  • A hard-stock permit card must be posted in the front window of the property, visible from the street, for the duration of construction
  • GOVERNING FIGURE (corrected 2026-07-23): per the Town's codified Municipal Code §18.02.040, work must commence within 60 days of permit issuance or the permit expires/is cancelled by the Town, and must be substantially completed within 2 years of issuance or it likewise expires. The Town's own Building Permit Application (page 2 Notice section, PDF 'Updated: 2022') separately states a conflicting 180-day commencement/work-stoppage figure ('In the event construction is not commenced within 180 days of issuance of this permit, then the same is automatically void. Cessation of work for a period of 180 continuous days shall also cause this permit to be void.'); the codified ordinance governs, but applicants should be aware the form itself prints the longer 180-day figure. Permits are not transferable.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit FeeGAP CLOSED 2026-07-23: full 'Total Valuation / Building Permit Fee' table transcribed verbatim from Resolution No. 2024-12-16H, Exhibit A 'Town of Mountain View Fee Schedule' (Chapter 18 - Building Regulations, 'Building Permit Fees Set By Resolution' table, updated 12/12/2024; fetched live at tomv.org/media/2046, HTTP 200, PDF text-extracted and verified). This is the Town's single, universal valuation-based Building Permit Fee schedule (no separate commercial/residential columns); it governs the Application's 'Permit Fee $___' line for every permit type. Supersedes prior 'no published dollar table' note, which reflected only the Building Department's public-facing webpages, not its Council resolution archive.
$40.00 for total valuation $1.00-$500.00; $40.00 for the first $500.00 plus $2.00 per additional $100.00 (or fraction) from $501.00-$2,000.00; $70.00 for the first $2,000.00 plus $14.00 per additional $1,000.00 (or fraction) from $2,001.00-$25,000.00; $391.25 for the first $25,000.00 plus $10.10 per additional $1,000.00 (or fraction) from $25,001.00-$50,000.00; $643.75 for the first $50,000.00 plus $7.00 per additional $1,000.00 (or fraction) from $50,001.00-$100,000.00; $993.75 for the first $100,000.00 plus $5.60 per additional $1,000.00 (or fraction) from $100,001.00-$500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 per additional $1,000.00 (or fraction) from $500,001.00-$1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 per additional $1,000.00 (or fraction) above $1,000,000.00
Plan Review FeeGAP CLOSED 2026-07-23: per Resolution No. 2024-12-16H, Exhibit A Fee Schedule ('Plan Review Fees by Resolution' table, updated 12/12/2024, tomv.org/media/2046). Must be paid up front, prior to plan review taking place, per the Building Department FAQ.
65% of the Building Permit Fee
Use Taxe.g. $100,000 valuation = $50,000 assumed materials x 3% = $1,500 use tax due at permit issuance; per the Town's Use Tax Guidelines PDF and Building Department FAQ (identical formula and worked example in both)
Total project valuation x 50% (assumed materials share) x 3% (Town use-tax rate)
DepositApplication form includes a 'Deposit $___' field distinct from the Permit Fee
Amount varies; listed as its own line item on the Building Permit Application

Review timeline

Plan reviewMountain View’s published plan-review target
5–10 business days

How long did your Residential Building Permit (New Construction) permit actually take in Mountain View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Setback

    Verifies footing/foundation placement and required setbacks before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment (insulation, drywall, etc.)

  4. 4

    Insulation / Drywall-Screw

    Per the Town's FAQ list of possible inspection types for a given permit

  5. 5

    Final Inspection

    All work complete per approved plans; permit card collected by inspector upon satisfactory completion

See the full Mountain View inspection guide — scheduling & re-inspection fees →

Tips

  • Mountain View does not require a Town contractor license, unlike several peer Colorado mountain-enclave towns in this corpus — but you must still create a CommunityCore login and provide any state or other-municipality contractor license you hold at submittal. Contractor
  • Call the inspection line ((303) 450-8748) by 4:00 p.m. to get an inspection scheduled for the next business day.
  • Use tax is calculated on 50% of your stated project valuation at a 3% rate — bring your completed, paid Building Permit Application to material vendors to avoid being double-charged municipal sales tax.

Frequently asked questions

Mountain View requires a residential building permit (new construction) for: Submit a completed Town of Mountain View Building Permit Application (paper/PDF or via the CommunityCore online portal) with a Plot Plan and Use Tax Calculation valuation form; No Town of Mountain View contractor license or registration is required, but all work must meet applicable municipal and building code requirements; contractors must create a CommunityCore login for registration/user-interface purposes; A completed application, use-tax valuation form, copy of contractor's license (if applicable, from any surrounding municipality), and proof of contractor's liability insurance must be emailed to the Building Department to obtain a permit; Use Tax (50% of total project valuation x 3% Town use-tax rate) is due at time of permit issuance; project valuation is determined by the Town Building Inspector using the ICC Building Valuation Data table; A hard-stock permit card must be posted in the front window of the property, visible from the street, for the duration of construction; GOVERNING FIGURE (corrected 2026-07-23): per the Town's codified Municipal Code §18.02.040, work must commence within 60 days of permit issuance or the permit expires/is cancelled by the Town, and must be substantially completed within 2 years of issuance or it likewise expires. The Town's own Building Permit Application (page 2 Notice section, PDF 'Updated: 2022') separately states a conflicting 180-day commencement/work-stoppage figure ('In the event construction is not commenced within 180 days of issuance of this permit, then the same is automatically void. Cessation of work for a period of 180 continuous days shall also cause this permit to be void.'); the codified ordinance governs, but applicants should be aware the form itself prints the longer 180-day figure. Permits are not transferable.. If your project isn't listed, confirm with Town of Mountain View Building Department (administered by SAFEbuilt under contract) at (303) 450-8746 before starting work.

In Mountain View, the published Permit Fee is: $40.00 for total valuation $1.00-$500.00; $40.00 for the first $500.00 plus $2.00 per additional $100.00 (or fraction) from $501.00-$2,000.00; $70.00 for the first $2,000.00 plus $14.00 per additional $1,000.00 (or fraction) from $2,001.00-$25,000.00; $391.25 for the first $25,000.00 plus $10.10 per additional $1,000.00 (or fraction) from $25,001.00-$50,000.00; $643.75 for the first $50,000.00 plus $7.00 per additional $1,000.00 (or fraction) from $50,001.00-$100,000.00; $993.75 for the first $100,000.00 plus $5.60 per additional $1,000.00 (or fraction) from $100,001.00-$500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 per additional $1,000.00 (or fraction) from $500,001.00-$1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 per additional $1,000.00 (or fraction) above $1,000,000.00. Additional published fees: Plan Review Fee — 65% of the Building Permit Fee; Use Tax — Total project valuation x 50% (assumed materials share) x 3% (Town use-tax rate); Deposit — Amount varies; listed as its own line item on the Building Permit Application. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The Town publishes a specific figure: 5-10 business days for residential plan review (Building Department review only; other department reviews such as Planning & Zoning or Fire may add time).

You'll need: Building Permit Application; Plot Plan; Use Tax Calculation; Proof of Liability Insurance. Depending on your project, Mountain View may also ask for: Contractor's License Copy. See the required-documents checklist on this page for details on each.

Mountain View requires 5 inspection(s) for a residential building permit (new construction), in order: Foundation/Setback, Rough Framing, Rough Electrical / Plumbing / Mechanical, Insulation / Drywall-Screw, Final Inspection. Schedule each through Town of Mountain View Building Department (administered by SAFEbuilt under contract) ((303) 450-8746).

Apply through Town of Mountain View Building Department (administered by SAFEbuilt under contract) at Mountain View Town Hall, 4176 Benton Street, Mountain View, CO 80212. Phone: (303) 450-8746, email: Buildingpermits@tomv.org. Office hours: Building division operates weekdays 8:00 a.m.-5:00 p.m. (Town's FAQ page prints this as '8:00 a.m. - 5:00 a.m.', which is evidently a typo for 5:00 p.m. given the Town Hall's own general business hours; noted honestly rather than silently corrected without flagging). Inspection request line (303) 450-8748 — call by 4:00 p.m. for next-business-day inspection. Town Hall main line (303) 421-7282.. Official information: https://www.tomv.org/building-department.

Mountain View, Colorado has adopted: 2021 International Residential Code (IRC) — referenced as the current adopted standard on the Town's 'Helpful Building Permit Handouts' page (page title/meta-description: 'Handouts developed by the Colorado Chapter of the International Code Council as a basic plan submittal under the 2021 International Residential Code') and cross-confirmed on the Town's own Building Permit Application (page 3, Homeowner Electrical/Plumbing certification): 'in accordance with the current edition of the National Electric Code, International Residential Code, and International Plumbing Code adopted by the Town of Mountain View as the minimum standard.'; National Electrical Code (NEC) — current edition, per the same Building Permit Application homeowner-certification language; the Town's live public-facing pages do not print the specific NEC year cycle (e.g. 2020 vs 2023) anywhere checked (Building Department page, Building Permits page, Handouts page, Application PDF) — noted as a gap rather than guessed.; International Plumbing Code (IPC), 2021 Edition — GAP CLOSED 2026-07-23: confirmed directly via the Town's own live, codified Municipal Code §18.08.010 ('International Plumbing Code adopted,' read live at mountainview.municipal.codes/Code/18.8): 'The International Plumbing Code, 2021 Edition ... is adopted by reference ... The provisions of the International Plumbing Code shall apply to the construction of, and renovations or additions to, all commercial and residential buildings within the Town.' (Ord. 2024-07-15A §17; Ord. 2019-02-11F §1; Ord. 2010-7 §4). This supersedes the prior 'specific year cycle not printed on any live Town page checked' note, which reflected only the Building Department's public-facing webpages, not the Municipal Code's own codified Article 8.; Note on code-currency and a superseded page: an older, still-live legacy page on the Town's prior CivicLive-hosted site (mountainviewco.hosted.civiclive.com/services/building_department_/building_permits, and its townofmountainviewcolorado.org mirror) states 'The 2015 International Building Code is the official adopted reference for building codes and applicable to Mountain View, effective March 28, 2019' — this page predates the Town's current SAFEbuilt-administered, tomv.org/Drupal-hosted site and its own CommunityCore permitting system, and the Town's live Helpful Building Permit Handouts page (referencing 2021 IRC-based ICC Colorado Chapter guides) is treated as the current, actively maintained source rather than this legacy 2015/2019 page. Flagged rather than silently discarded, consistent with this corpus's policy of noting superseded-but-still-indexed pages (cf. Vail's stale submittal-packet footer).; GAP CLOSED 2026-07-23 (all remaining Chapter 18 Articles read live, superseding the prior 'not printed anywhere' note below, which is preserved for the record): the Town's Municipal Code Chapter 18 (Building Regulations), previously reported as unreachable (mountainview.municipal.codes/Code/18 returned a Cloudflare bot-challenge 403 to every curl/WebFetch attempt), was successfully accessed live via the Browser pane after clearing the Cloudflare challenge, and this follow-up pass individually read Articles 5, 7, 8, 11, 12, and 4.5 in full (in addition to the previously-read Articles 1, 2, 4, and 13). Confirmed adopted editions, each quoted directly from its codified section: International Fire Code (IFC), 2021 Edition — §18.05.010 ('The International Fire Code, 2021 Edition ... is adopted by reference'; Ord. 2024-07-15A §11), further amended per West Metro Fire Protection District Resolution No. 2022-08 (§18.05.030). International Mechanical Code (IMC), 2021 Edition — §18.07.010 (Ord. 2024-07-15A §14; Ord. 2019-02-11E §1; Ord. 2010-7 §4). International Plumbing Code (IPC), 2021 Edition — §18.08.010 (Ord. 2024-07-15A §17; see also the dedicated IPC codesAdopted entry above). International Fuel Gas Code (IFGC), 2015 Edition — §18.11.010 ('The International Fuel Gas Code, 2015 Edition ... is adopted by reference'; Ord. 2019-02-11H §1) — notably NOT bumped to 2021 by the Town's 2024-07-15A omnibus code-update ordinance, unlike every other International code family in Chapter 18; this lag is a real, confirmed fact about the Town's current code, not an oversight in this file. International Existing Building Code (IEBC), 2021 Edition — §18.12.010 (Ord. 2024-07-15A §19; Ord. 2019-02-11G §1). International Energy Conservation Code (IECC), 2021 Edition — §18.045.010 (Ord. 2024-07-15A §9); see also the dedicated HB22-1362 entry below, which this same Article resolves. Every Article read states its provisions 'shall apply to the construction of, and renovations or additions to, all commercial and residential buildings within the Town' (near-identical boilerplate in each Article), confirming none of these adopted codes are residential- or commercial-only carve-outs.; SUPERSEDED 2026-07-23 (preserved for the record; see GAP CLOSED entry above for the current, correct figures): No IBC, IFC, IMC, IFGC, IECC, or IEBC edition is printed anywhere on the Town's live public-facing pages, its Building Permit Application, or its Use Tax Guidelines — Mountain View's public-facing materials remain IRC/NEC/IPC-focused. UPDATE 2026-07-23: the Town's Municipal Code Chapter 18 (Building Regulations), previously reported as unreachable (mountainview.municipal.codes/Code/18 returned a Cloudflare bot-challenge 403 to every curl/WebFetch attempt), was successfully accessed live via the Browser pane after clearing the Cloudflare challenge. Its Article list confirms Chapter 18 does include dedicated Articles for IBC (Art. 4, confirmed 2021 Edition, Ord. 2024-07-15A/2019-02-11A/2010-7), IRC (Art. 13, confirmed 2021 Edition, Ord. 2024-07-15A/2019-02-11I), Fire Code (Art. 5), Mechanical Code (Art. 7), Fuel Gas Code (Art. 11), Existing Building Code (Art. 12), and Energy Conservation Code (Art. 4.5) — this file's targeted 2026-07-23 chase read Articles 1, 2, 4, and 13 in full (fetching the specific reroof-timeline and fee-schedule figures it was scoped to close) but did NOT read Articles 5/7/8/11/12/4.5 for their specific edition years, so the IFC/IMC/IFGC/IECC/IEBC edition-year gap remains open pending a dedicated follow-up pass through those now-accessible Articles, rather than assumed.; GAP CLOSED 2026-07-23 (supersedes prior 'unresolved' note below, preserved for the record): the Town HAS taken its own HB22-1362 adoption action, codified directly in Municipal Code §18.045.010 (Article 4.5, Energy Conservation Code, read live 2026-07-23 at mountainview.municipal.codes/Code/18.4.5): 'In addition to the IECC, the Town of Mountain View will also be adopting the Colorado Model Electric Ready and Solar Ready Code as required by State law under HB22-1362. These requirements will be in addition to those found in this Code.' (Ord. 2024-07-15A §9). The same Article's amendments (§18.045.020) further amend IECC Sections C401.2 and R401.2 to require commercial and residential buildings, respectively, to 'comply with the Colorado Model Electric Ready and Solar Ready Code.' This directly and specifically confirms Town HB22-1362 compliance action, sourced from the codified ordinance itself rather than inferred.; SUPERSEDED 2026-07-23 (preserved for the record; see GAP CLOSED entry above): HB22-1362 (Colorado's statewide building energy code / greenhouse-gas-emissions law, requiring local governments to adopt an energy code and, per its later compliance milestones, the Colorado Electric and Solar Ready Code) is not mentioned anywhere on the Town's live Building Department, Building Permits, or Helpful Handouts pages as of this review. Given Mountain View's tiny size and thin published program (no separate energy-code page, no mechanical/energy-specific permit-type page), it is unclear from public sources whether the Town has taken its own HB22-1362 adoption action or is relying on some other mechanism; not stated as fact either way — flagged as unresolved rather than assumed.. Local amendments apply — see the Mountain View overview page for the full list.

The Town of Mountain View's own Building Department, administered under contract by SAFEbuilt (a national community-development-services company), issues all building, electrical, mechanical, and plumbing permits for the Town. This is not a Jefferson County unincorporated-area permit — Mountain View is a distinct incorporated home-rule town.