Loveland building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Loveland, Colorado.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 410 E. 5th Street, Loveland, CO 80537
- Phone
- (970) 962-2505
- eplan-res@cityofloveland.org (residential); eplan-building@cityofloveland.org (non-residential)
- Office hours
- Lobby Hours: Monday-Friday 7:30 AM-4:00 PM; Phone Hours: Monday-Friday 7:30 AM-3:30 PM. Inspection Line: (970) 962-2100
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour — verify forms, rebar, and foundation depth meets the 30-inch minimum frost depth
- 2
Water-Resistive Barrier
House wrap: one inspection after windows/doors installed. Zip-wall systems: two inspections (sheathing nailing/shear, then seam taping), performed just before exterior covering is installed
- 3
Framing
Structural framing including enlarged crawlspace access for under-floor fire protection (effective July 1, 2026)
- 4
Rough Radon / Final Radon
Effective July 1, 2026, required for all new residential buildings under adopted IRC Appendix BE, concluding with a radon mitigation certificate
- 5
Final Building Inspection
All work complete per approved plans and applicable affidavits/certifications (exhaust test, vapor barrier, roofing) on file
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Footing/Foundation/UFER
Building Inspectors collect the completed Foundation Setback and Elevation Certification on-site at this inspection
- 2
Framing
Verifies fire separation detail (Dwelling-Garage or Two-Family Dwelling separation) and structural framing per sealed engineer drawings
- 3
Final Grade Certification
Building Inspectors collect the completed Residential Certification of Lot Grading and Structure Elevation on-site at this inspection
- 4
Final Building
All work complete, energy code compliance verified by qualified third party
Applies to: Plumbing Permit
- 1
Underground/Slab
Before concrete pour — verify pipe slope, materials, and cleanouts; a Vapor Barrier Affidavit is required for installations under any interior/heated concrete slab (effective January 1, 2026)
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected; water heater/furnace/boiler exhaust vents air-tested at 5 psi for a minimum of 15 minutes with installer certification submitted
Applies to: Residential Addition / Remodel / Alteration Permit
- 1
Footing/Foundation
Required before concrete pour for deck posts, garage foundations, or addition footings
- 2
Framing
Structural framing, connections to existing structure
- 3
Final
All work complete per approved plans
Applies to: Complete Structure Demolition Permit
- 1
Utility Disconnections
Demo Water Service, Demo Fire Service, Demo WasteWater, and/or Demo Pre-treatment as applicable, performed/inspected by the Water Department (call 970-962-3721); must be completed prior to the Final Building inspection. Meter pit/vault abandonment, fire-line blank-flanging, and sewer tap abandonment each have detailed City specifications (referencing COL water/wastewater development standards 7.3.18 and 8.3.13)
- 2
Final Building Inspection
Confirms demolition is complete and no dangerous conditions exist (open holes, exposed/uncontained electrical wiring, etc.)
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and service connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified
Applies to: EV Charger / EVSE Permit
- 1
Rough-In / Service Connection
Wiring, breaker/panel capacity, and disconnect placement before energizing, same as any electrical service work
- 2
Final
Charger circuit installed, labeled, and energized per NEC/adopted electrical code
Applies to: Fence and Retaining Wall Standards
- 1
Footing
Required for engineered retaining walls before backfill
- 2
Final
Completed fence/wall verified against approved plans and UDC standards
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and mechanical equipment rough-in before walls closed; gas piping per submitted Gas Load Form drawing
- 2
Final
Equipment operational; exhaust vent tested and certified; smoke/CO alarms verified per code
Applies to: Re-Roofing Permit
- 1
Mid-Roof (Photo-Documented)
Effective January 1, 2026, performed via contractor-submitted photos (not an in-person city inspection) showing ice barrier measurement, valley/sidewall flashing, underlayment, drip edge, and nailing pattern
- 2
Final Roof / Roofing Affidavit / Permit Completion
All three must be called in; requires date/time-stamped photos of the whole house (showing address) submitted the day before, plus an on-site OSHA-approved ladder set provided by the contractor (waived for 2+ story or >6:12 pitch structures)
Applies to: Rooftop Solar Photovoltaic (PV) / DER Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, inverter, and interconnection point verified
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Loveland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Loveland building permits