Loveland building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Loveland, Colorado.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
410 E. 5th Street, Loveland, CO 80537
Phone
(970) 962-2505
Office hours
Lobby Hours: Monday-Friday 7:30 AM-4:00 PM; Phone Hours: Monday-Friday 7:30 AM-3:30 PM. Inspection Line: (970) 962-2100

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation/Footing

    Before concrete pour — verify forms, rebar, and foundation depth meets the 30-inch minimum frost depth

  2. 2

    Water-Resistive Barrier

    House wrap: one inspection after windows/doors installed. Zip-wall systems: two inspections (sheathing nailing/shear, then seam taping), performed just before exterior covering is installed

  3. 3

    Framing

    Structural framing including enlarged crawlspace access for under-floor fire protection (effective July 1, 2026)

  4. 4

    Rough Radon / Final Radon

    Effective July 1, 2026, required for all new residential buildings under adopted IRC Appendix BE, concluding with a radon mitigation certificate

  5. 5

    Final Building Inspection

    All work complete per approved plans and applicable affidavits/certifications (exhaust test, vapor barrier, roofing) on file

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Footing/Foundation/UFER

    Building Inspectors collect the completed Foundation Setback and Elevation Certification on-site at this inspection

  2. 2

    Framing

    Verifies fire separation detail (Dwelling-Garage or Two-Family Dwelling separation) and structural framing per sealed engineer drawings

  3. 3

    Final Grade Certification

    Building Inspectors collect the completed Residential Certification of Lot Grading and Structure Elevation on-site at this inspection

  4. 4

    Final Building

    All work complete, energy code compliance verified by qualified third party

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts; a Vapor Barrier Affidavit is required for installations under any interior/heated concrete slab (effective January 1, 2026)

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected; water heater/furnace/boiler exhaust vents air-tested at 5 psi for a minimum of 15 minutes with installer certification submitted

Applies to: Residential Addition / Remodel / Alteration Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for deck posts, garage foundations, or addition footings

  2. 2

    Framing

    Structural framing, connections to existing structure

  3. 3

    Final

    All work complete per approved plans

Applies to: Complete Structure Demolition Permit

  1. 1

    Utility Disconnections

    Demo Water Service, Demo Fire Service, Demo WasteWater, and/or Demo Pre-treatment as applicable, performed/inspected by the Water Department (call 970-962-3721); must be completed prior to the Final Building inspection. Meter pit/vault abandonment, fire-line blank-flanging, and sewer tap abandonment each have detailed City specifications (referencing COL water/wastewater development standards 7.3.18 and 8.3.13)

  2. 2

    Final Building Inspection

    Confirms demolition is complete and no dangerous conditions exist (open holes, exposed/uncontained electrical wiring, etc.)

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Devices installed, panel labeled, protections verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In / Service Connection

    Wiring, breaker/panel capacity, and disconnect placement before energizing, same as any electrical service work

  2. 2

    Final

    Charger circuit installed, labeled, and energized per NEC/adopted electrical code

Applies to: Fence and Retaining Wall Standards

  1. 1

    Footing

    Required for engineered retaining walls before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans and UDC standards

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls closed; gas piping per submitted Gas Load Form drawing

  2. 2

    Final

    Equipment operational; exhaust vent tested and certified; smoke/CO alarms verified per code

Applies to: Re-Roofing Permit

  1. 1

    Mid-Roof (Photo-Documented)

    Effective January 1, 2026, performed via contractor-submitted photos (not an in-person city inspection) showing ice barrier measurement, valley/sidewall flashing, underlayment, drip edge, and nailing pattern

  2. 2

    Final Roof / Roofing Affidavit / Permit Completion

    All three must be called in; requires date/time-stamped photos of the whole house (showing address) submitted the day before, plus an on-site OSHA-approved ladder set provided by the contractor (waived for 2+ story or >6:12 pitch structures)

Applies to: Rooftop Solar Photovoltaic (PV) / DER Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, inverter, and interconnection point verified

Re-inspection fees

Residential Building Permit (New Construction)Re-Inspection Fee (per inspection, penalty) · City of Loveland 2026 Fee Schedule
$200.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Loveland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Loveland building permits

Get alerts for Loveland

We'll email you when Loveland's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.