Commercial Building Permit (New Construction / Addition) in Loveland, Colorado

Required for new construction, additions, and new mezzanines in non-residential (commercial, industrial, institutional) and multi-unit dwelling buildings in Loveland, using the City's 'Non-Residential Building Permit Application - New Building/Addition' form. A Site Development Plan (reviewed by the Current Planning Division) and an associated Site Work Permit must be approved before the building permit can be submitted, unless the City's Development Review Team approves concurrent review. Partial build-outs of new core-and-shell buildings are not permitted — each tenant space requires a separate Tenant Finish permit. Submit electronically to eplan-building@cityofloveland.org.

Verified 2026-08-02 · Source

When you need this permit

  • Building permit required for new non-residential buildings, building additions, and new mezzanines (explicitly listed as 'Non-Residential' examples on the City's Permitting FAQ's page, distinct from the Residential examples list)
  • A Site Development Plan application must be submitted to and approved by the Current Planning Division, together with an associated Site Work Permit, before the building permit application can be submitted; concurrent site development plan and building permit review is possible only if approved by the City's Development Review Team
  • Partial build-outs of new core-and-shell buildings or additions are not permitted; a separate Tenant Finish/Interior Remodel permit is required for each tenant space. For new builds with more than one tenant space, a core-and-shell permit is required first, followed by SEPARATE tenant finish permits per tenant space
  • A complete application requires a set of Architectural/Structural/Engineered stamped drawings; drawings stamped 'Preliminary' or 'Not for Construction' are not accepted
  • Drawing set must include architectural plans, current + proposed floor plans, building elevations (HVAC equipment shown shaded), code analysis, a Design Criteria List (occupancy group, construction type, seismic design category, design loads, structural systems, square footage/allowable floor area, exits, fire sprinkler/alarm systems, height/stories, occupant load), evidence of energy code compliance, parking analysis for each proposed use, structural plans, foundation plans stamped by a licensed Colorado engineer, electrical plans and 1-line diagram, mechanical/HVAC plans with equipment schedules, and plumbing plans
  • For buildings proposing more than one tenant, an 11x17 detail showing tenant spaces is required
  • A Traffic Impact Study (TIS) is required for new construction/expansion/addition/change-of-use applications generating more than 200 daily trips or 20 peak-hour trips, or a change of use resulting in more than a 20% increase in traffic from the prior use; otherwise, a completed Transportation Worksheet (Attachment C) is submitted so City staff can determine if a TIS waiver is justified
  • A commercial Electric Service Worksheet (ESW) confirming whether the existing electric service is changing is required; if a new service is needed or the existing service is being upgraded, all items in Section 4.1 of the Requirements for Electric Service (RFES) must be provided with the permit application
  • Water-Resistive Barrier inspection applies to new commercial buildings (as well as additions and new residences) per the City's Building FAQs
  • Fire alarm, sprinkler, and hood suppression systems are permitted separately through the Loveland Fire Rescue Authority, not under the building permit itself
  • A valid City of Loveland Contractor's License is required for structural, mechanical, electrical, or plumbing work on non-residential buildings; the self-perform homeowner exemption does not apply Owner-builderContractor
  • Contractors and project valuations do not need to be provided at initial submittal/check-in, but must be provided before the permit can be approved

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeCity of Loveland Building Valuation Data Table (effective March 15, 2026) and 2026 Fee Schedule, which states 'Building permit fees are based on the current ICC Fees'
Based on the current ICC Building Valuation Data (square-foot construction cost by occupancy group/construction type) applied to project square footage; e.g., effective March 15, 2026, B (Business) Type VB is $213.27/sq ft and M (Mercantile) Type VB is $135.89/sq ft; for shell-only buildings, deduct 20 percent from the applicable valuation per the table's footnote
Commercial Plan Review FeeCity of Loveland 2026 Fee Schedule, 'Commercial Plan Review Fee, percentage of Building Permit Fee'
65% of the Building Permit Fee
New Technology Fee - Permit PortionCity of Loveland 2026 Fee Schedule
10% of the Building Permit Fee
New Technology Fee - Commercial Plan Check PortionCity of Loveland 2026 Fee Schedule
10% of the Commercial Plan Check Fee
Site Work Permit (Planning Division)City of Loveland 2026 Fee Schedule, Development Services/Planning section; required before the building permit is approved for new builds
$126.00
Site Development Plan for Use by Right and Limited Use (Planning Division)City of Loveland 2026 Fee Schedule, Development Services/Planning section
$840.00
Re-Inspection Fee (per inspection, penalty)City of Loveland 2026 Fee Schedule
$200.00
Inspections outside normal business hoursCity of Loveland 2026 Fee Schedule
$200.00 minimum (2-hour minimum), or total hourly City cost if greater
Additional Plan Review (changes/additions/revisions to approved plans)City of Loveland 2026 Fee Schedule
$150.00 per hour, 1-hour minimum
Review of Deferred Submittals (submitted after initial plan review)City of Loveland 2026 Fee Schedule
$100.00 per hour, per submittal
Occupancy Permit (per building or 'shell'), excludes single-family R-3City of Loveland 2026 Fee Schedule
$100.00, plus $50.00 for each additional non-residential improvement
Temporary, Partial, or Conditional Certificate of Occupancy / Certificate of CompletionCity of Loveland 2026 Fee Schedule
$1,000.00 for 30 days, unless otherwise approved by the Chief Building Official

Review timeline

Plan reviewLoveland’s published plan-review target
20–30 business days

How long did your Commercial Building Permit (New Construction / Addition) permit actually take in Loveland?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation/Ufer

    Before concrete pour (Inspection Type Code 2201)

  2. 2

    Underground Plumbing / Underground Electric

    Before backfill (Inspection Type Codes 5501 / 3301)

  3. 3

    Water-Resistive Barrier

    Added to all additions, new residences, and commercial buildings per the City's Building FAQs

  4. 4

    Rough Electrical / Rough Mechanical / Rough Plumbing

    Before walls/ceiling are closed (Inspection Type Codes 3305 / 4405 / 5505)

  5. 5

    Above Ceiling Electrical / Mechanical / Plumbing

    For commercial ceiling systems, before ceiling grid/tile installation (Inspection Type Codes 3335 / 4435 / 5535)

  6. 6

    Fire-Rough/Hydro

    Fire alarm, sprinkler, and hood suppression rough inspections, scheduled separately with Loveland Fire Rescue Authority (Inspection Type Code 8840)

  7. 7

    Final Electrical / Final Mechanical / Final Plumbing / Final Building

    All work complete per approved plans (Inspection Type Codes 3350 / 4450 / 5550 / 2250)

  8. 8

    Certificate of Occupancy Issuance

    Final step after all required finals and utility/planning sign-offs are complete (Inspection Type Code 6690)

See the full Loveland inspection guide — scheduling & re-inspection fees →

Tips

  • The Site Development Plan and Site Work Permit process runs through the Current Planning Division and must be substantially complete before Building Division check-in will accept a new-construction commercial building permit application — budget time for this step separately from the 20-30 working-day building-permit plan-review estimate.
  • Contractors and valuations do NOT need to be provided at time of submittal/check-in, but ARE required before the City will approve the permit, per the Non-Residential Checklist.
  • A core-and-shell (new building) permit cannot be used to build out any tenant space — each tenant space needs its own, separate Tenant Finish/Interior Remodel permit.
  • All permit submittals are processed electronically by email to eplan-building@cityofloveland.org; the City's Accela online portal is stated as 'Coming in 2026.'

Frequently asked questions

Loveland requires a commercial building permit (new construction / addition) for: Building permit required for new non-residential buildings, building additions, and new mezzanines (explicitly listed as 'Non-Residential' examples on the City's Permitting FAQ's page, distinct from the Residential examples list); A Site Development Plan application must be submitted to and approved by the Current Planning Division, together with an associated Site Work Permit, before the building permit application can be submitted; concurrent site development plan and building permit review is possible only if approved by the City's Development Review Team; Partial build-outs of new core-and-shell buildings or additions are not permitted; a separate Tenant Finish/Interior Remodel permit is required for each tenant space. For new builds with more than one tenant space, a core-and-shell permit is required first, followed by SEPARATE tenant finish permits per tenant space; A complete application requires a set of Architectural/Structural/Engineered stamped drawings; drawings stamped 'Preliminary' or 'Not for Construction' are not accepted; Drawing set must include architectural plans, current + proposed floor plans, building elevations (HVAC equipment shown shaded), code analysis, a Design Criteria List (occupancy group, construction type, seismic design category, design loads, structural systems, square footage/allowable floor area, exits, fire sprinkler/alarm systems, height/stories, occupant load), evidence of energy code compliance, parking analysis for each proposed use, structural plans, foundation plans stamped by a licensed Colorado engineer, electrical plans and 1-line diagram, mechanical/HVAC plans with equipment schedules, and plumbing plans; For buildings proposing more than one tenant, an 11x17 detail showing tenant spaces is required; A Traffic Impact Study (TIS) is required for new construction/expansion/addition/change-of-use applications generating more than 200 daily trips or 20 peak-hour trips, or a change of use resulting in more than a 20% increase in traffic from the prior use; otherwise, a completed Transportation Worksheet (Attachment C) is submitted so City staff can determine if a TIS waiver is justified; A commercial Electric Service Worksheet (ESW) confirming whether the existing electric service is changing is required; if a new service is needed or the existing service is being upgraded, all items in Section 4.1 of the Requirements for Electric Service (RFES) must be provided with the permit application; Water-Resistive Barrier inspection applies to new commercial buildings (as well as additions and new residences) per the City's Building FAQs; Fire alarm, sprinkler, and hood suppression systems are permitted separately through the Loveland Fire Rescue Authority, not under the building permit itself; A valid City of Loveland Contractor's License is required for structural, mechanical, electrical, or plumbing work on non-residential buildings; the self-perform homeowner exemption does not apply; Contractors and project valuations do not need to be provided at initial submittal/check-in, but must be provided before the permit can be approved. If your project isn't listed, confirm with City of Loveland Building Division (Development Services Department) at (970) 962-2505 before starting work.

Yes. The Planning Division's Site Work Permit is $126.00 per the City's 2026 Fee Schedule, separate from the Building Permit Fee, Commercial Plan Review Fee, and any Site Development Plan review fee.

The City of Loveland Building Division applies its single governing estimate of 20-30 working days per round of review (Permitting FAQ's page) to commercial/non-residential building permits; the Permitting FAQ's Non-Residential examples table explicitly lists 'New Buildings' and 'Building Additions' as covered by this estimate. A separate Site Development Plan/Site Work Permit review by the Current Planning Division must also be completed beforehand and is not included in this figure.

You'll need: Non-Residential Building Permit Application - New Building/Addition; Non-Residential and Multi-Unit Dwelling New Construction Building Permit Submittal Checklist; Site Development Plan Application; Site Work Permit; Electrical Worksheet / Commercial Electric Service Worksheet (Attachment B). Depending on your project, Loveland may also ask for: Wastewater Discharge Survey (Attachment A); Transportation Worksheet (Attachment C); Cross-Connection/Backflow Prevention Questionnaire (Attachment D); Foundation Setback and Elevation Certification; Food Service Establishment Application; Third Party Inspectors Policy and Approval Form. See the required-documents checklist on this page for details on each.

Loveland requires 8 inspection(s) for a commercial building permit (new construction / addition), in order: Footing/Foundation/Ufer, Underground Plumbing / Underground Electric, Water-Resistive Barrier, Rough Electrical / Rough Mechanical / Rough Plumbing, Above Ceiling Electrical / Mechanical / Plumbing, Fire-Rough/Hydro, Final Electrical / Final Mechanical / Final Plumbing / Final Building, Certificate of Occupancy Issuance. Schedule each through City of Loveland Building Division (Development Services Department) ((970) 962-2505).

Apply through City of Loveland Building Division (Development Services Department) at 410 E. 5th Street, Loveland, CO 80537. Phone: (970) 962-2505, email: eplan-res@cityofloveland.org (residential); eplan-building@cityofloveland.org (non-residential). Office hours: Lobby Hours: Monday-Friday 7:30 AM-4:00 PM; Phone Hours: Monday-Friday 7:30 AM-3:30 PM. Inspection Line: (970) 962-2100. Official information: https://www.lovgov.org/services/development-services/building-division.

Loveland, Colorado has adopted: Colorado has no statewide mandatory building code for municipalities; each home-rule or statutory city adopts and amends its own building code edition. Colorado's only statewide floor is an energy/greenhouse-gas standard: House Bill 22-1362 (2022), codified in relevant part at C.R.S. Title 24 and repealing portions of the prior C.R.S. 30-28-211 energy-code statute, directs the Colorado Energy Code Board to publish a Model Electric Ready and Solar Ready Code and a Model Low Energy and Carbon Code, which local governments (and certain state agencies) must adopt on their own timelines or otherwise demonstrate equivalent/greater stringency. Source: Colorado General Assembly, HB22-1362 (leg.colorado.gov/bills/hb22-1362); Colorado Energy Office Energy Code Board. Applicants should confirm the specific edition/amendments in effect for their city, since Colorado building codes vary by municipality.; City of Loveland runs its own Building Division and adopts/amends its own code within the Unified Development Code (Title 18) and Municipal Code (Title 15) framework — it is NOT a DOLA/state-administered program. Effective July 1, 2026, the City Council-adopted amendments move Loveland to the 2024 International Building Code (IBC) and 2024 International Residential Code (IRC) family (referenced in the City's 'Building Code adopted changes (ICC 2024)' notice, approved on second reading June 2, 2026); prior to that date the currently effective editions are the 2021 IRC, 2021 IMC (Mechanical), and 2021 IFGC (Fuel Gas), per City of Loveland Residential HVAC/Gas Load Fast Track forms dated 5/27/2026. Source: City of Loveland Building Division homepage and Loveland Building Code Amendments page (lovgov.org/services/development-services/building-division; lovgov.org/services/development-services/building-division/loveland-building-code).; Effective July 1, 2026, City of Loveland adopts the Colorado Model Low Energy and Carbon Code (combining the Colorado Model Electric Ready and Solar Ready Code with the 2024 International Energy Conservation Code (IECC)) to satisfy the HB22-1362 statewide energy-code floor. Source: City of Loveland 'City Council approves building-related code changes' notice (lovgov.org/home/showpublisheddocument/63720/639162471002370000).; Effective July 1, 2026, City of Loveland adopts Appendix BC (Accessory Dwelling Units) from the International Residential Code, with local amendments to align with the Unified Development Code, and now allows a property owner to act as general contractor on an ADU provided all subcontractors hold a valid City of Loveland contractor license. Source: City of Loveland code-changes notice.; Effective July 1, 2026, City of Loveland adopts Appendix BE from the International Residential Code (Radon Control Methods) for all new commercial and residential buildings, with new rough-radon, final-radon, and radon-mitigation-certificate inspections. Source: City of Loveland code-changes notice.; Building Valuation Data Table (square-foot construction costs by ICC occupancy group and construction type), effective March 15, 2026, is used by the City to calculate building-permit valuation; the City's fee schedule states 'Building permit fees are based on the current ICC Fees' via the ICC Building Valuation Data publication (iccsafe.org/products-and-services/i-codes/code-development-process/building-valuation-data/). Source: City of Loveland Building Valuation Data Table PDF (lovgov.org/home/showpublisheddocument/60277/639090010225200000) and 2026 Fee Schedule (lovgov.org/home/showpublisheddocument/60275/639089984528770000).. Local amendments apply — see the Loveland overview page for the full list.

No. Partial build-outs of new core-and-shell buildings or additions are not permitted under the new-construction permit. A separate Tenant Finish/Interior Remodel permit is required for each tenant space, per the City's Non-Residential Checklist.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Loveland.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.