Commercial Building Permit (New Construction / Addition) — Loveland, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.lovgov.org/services/development-services/building-division/forms-and-applications/non-residential-and-multi-family-forms
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / Addition) in Loveland, Colorado
Required for new construction, additions, and new mezzanines in non-residential (commercial, industrial, institutional) and multi-unit dwelling buildings in Loveland, using the City's 'Non-Residential Building Permit Application - New Building/Addition' form. A Site Development Plan (reviewed by the Current Planning Division) and an associated Site Work Permit must be approved before the building permit can be submitted, unless the City's Development Review Team approves concurrent review. Partial build-outs of new core-and-shell buildings are not permitted — each tenant space requires a separate Tenant Finish permit. Submit electronically to eplan-building@cityofloveland.org.
Verified 2026-08-02 · Source
When you need this permit
- Building permit required for new non-residential buildings, building additions, and new mezzanines (explicitly listed as 'Non-Residential' examples on the City's Permitting FAQ's page, distinct from the Residential examples list)
- A Site Development Plan application must be submitted to and approved by the Current Planning Division, together with an associated Site Work Permit, before the building permit application can be submitted; concurrent site development plan and building permit review is possible only if approved by the City's Development Review Team
- Partial build-outs of new core-and-shell buildings or additions are not permitted; a separate Tenant Finish/Interior Remodel permit is required for each tenant space. For new builds with more than one tenant space, a core-and-shell permit is required first, followed by SEPARATE tenant finish permits per tenant space
- A complete application requires a set of Architectural/Structural/Engineered stamped drawings; drawings stamped 'Preliminary' or 'Not for Construction' are not accepted
- Drawing set must include architectural plans, current + proposed floor plans, building elevations (HVAC equipment shown shaded), code analysis, a Design Criteria List (occupancy group, construction type, seismic design category, design loads, structural systems, square footage/allowable floor area, exits, fire sprinkler/alarm systems, height/stories, occupant load), evidence of energy code compliance, parking analysis for each proposed use, structural plans, foundation plans stamped by a licensed Colorado engineer, electrical plans and 1-line diagram, mechanical/HVAC plans with equipment schedules, and plumbing plans
- For buildings proposing more than one tenant, an 11x17 detail showing tenant spaces is required
- A Traffic Impact Study (TIS) is required for new construction/expansion/addition/change-of-use applications generating more than 200 daily trips or 20 peak-hour trips, or a change of use resulting in more than a 20% increase in traffic from the prior use; otherwise, a completed Transportation Worksheet (Attachment C) is submitted so City staff can determine if a TIS waiver is justified
- A commercial Electric Service Worksheet (ESW) confirming whether the existing electric service is changing is required; if a new service is needed or the existing service is being upgraded, all items in Section 4.1 of the Requirements for Electric Service (RFES) must be provided with the permit application
- Water-Resistive Barrier inspection applies to new commercial buildings (as well as additions and new residences) per the City's Building FAQs
- Fire alarm, sprinkler, and hood suppression systems are permitted separately through the Loveland Fire Rescue Authority, not under the building permit itself
- A valid City of Loveland Contractor's License is required for structural, mechanical, electrical, or plumbing work on non-residential buildings; the self-perform homeowner exemption does not apply Owner-builderContractor
- Contractors and project valuations do not need to be provided at initial submittal/check-in, but must be provided before the permit can be approved
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation/Ufer
Before concrete pour (Inspection Type Code 2201)
- 2
Underground Plumbing / Underground Electric
Before backfill (Inspection Type Codes 5501 / 3301)
- 3
Water-Resistive Barrier
Added to all additions, new residences, and commercial buildings per the City's Building FAQs
- 4
Rough Electrical / Rough Mechanical / Rough Plumbing
Before walls/ceiling are closed (Inspection Type Codes 3305 / 4405 / 5505)
- 5
Above Ceiling Electrical / Mechanical / Plumbing
For commercial ceiling systems, before ceiling grid/tile installation (Inspection Type Codes 3335 / 4435 / 5535)
- 6
Fire-Rough/Hydro
Fire alarm, sprinkler, and hood suppression rough inspections, scheduled separately with Loveland Fire Rescue Authority (Inspection Type Code 8840)
- 7
Final Electrical / Final Mechanical / Final Plumbing / Final Building
All work complete per approved plans (Inspection Type Codes 3350 / 4450 / 5550 / 2250)
- 8
Certificate of Occupancy Issuance
Final step after all required finals and utility/planning sign-offs are complete (Inspection Type Code 6690)
See the full Loveland inspection guide — scheduling & re-inspection fees →
Tips
- The Site Development Plan and Site Work Permit process runs through the Current Planning Division and must be substantially complete before Building Division check-in will accept a new-construction commercial building permit application — budget time for this step separately from the 20-30 working-day building-permit plan-review estimate.
- Contractors and valuations do NOT need to be provided at time of submittal/check-in, but ARE required before the City will approve the permit, per the Non-Residential Checklist.
- A core-and-shell (new building) permit cannot be used to build out any tenant space — each tenant space needs its own, separate Tenant Finish/Interior Remodel permit.
- All permit submittals are processed electronically by email to eplan-building@cityofloveland.org; the City's Accela online portal is stated as 'Coming in 2026.'
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Loveland building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Loveland.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Loveland
Commercial Building Permit (New Construction / Addition) in other cities
Compare commercial building permit (new construction / addition) fees across Colorado →