EV Charger / EVSE Permit in Loveland, Colorado

Loveland has no standalone EV-charger permit form or fee line item. A residential or commercial Level 1/Level 2 EV charging circuit is ordinary electrical work processed through the same Residential Electrical Fast Track (Service Upgrade/Alteration or Electrical Work application types) as any other panel or circuit change, with the valuation-based Building Permit Fee from the City's 2026 Fee Schedule. Separately, as a Colorado municipality with a 2020 Census population over 10,000, Loveland is a jurisdiction covered by HB24-1173 (Electric Vehicle Charging System Permits), which sets a statutory 3-business-day decision turnaround for EV charging system permit applications, and the City's Unified Development Code was amended in the 2025-2026 cycle to add a distinct 'EV Charging Project' land-use category (Primary/Accessory) with streamlined administrative review for stand-alone or larger commercial charging installations under the State's EV Charging Model Land Use Code (EV MLUC).

Verified 2026-07-20 · Source

When you need this permit

  • Electrical contractor must hold a valid City of Loveland contractor license prior to applying, same as any other electrical permit Contractor
  • For a service equipment change/amp increase to support EV charging, an Electric Service Worksheet (ESW) signed by a Loveland Water and Power Distribution Designer is required before permit issuance (same rule that applies to any service upgrade)
  • Apply via the Residential Electrical Fast Track Permit Application (Service Upgrade, Service Alteration, or Electrical Work types) to eplan-buildingfasttrack@cityofloveland.org; no separate EV-specific application form was found
  • Under HB24-1173 (effective statewide August 7, 2024; compliance required of covered jurisdictions by December 31, 2025), the permitting agency must notify the applicant of approval, conditional approval, or denial within 3 business days of making its determination, and denials may be based only on non-compliance with published objective standards or health/safety
  • Stand-alone or primary-use EV charging stations (as opposed to an accessory charger at a home or business) are reviewed under the City's new UDC 'EV Charging Project' use category, which the Loveland Planning Commission and City Council considered through public hearings in fall 2025 (Planning Commission hearing October 27, 2025; City Council hearing scheduled November 18, 2025) to align local code with the State's EV MLUC and HB24-1173/HB24-1304
  • Effective February 2026 (Ordinance No. 6816, second reading February 17, 2026, adopting Loveland Municipal Code Chapter 15.50), new buildings must be designed per the Colorado Model Electric Ready and Solar Ready Code, which sets EV-charging-infrastructure-readiness requirements (e.g., raceway/panel capacity) for qualifying new construction — this affects what a future EV charger install will connect to, but is a new-construction requirement, not a fee for the charger permit itself

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based)City of Loveland 2026 Fee Schedule; no EV-charger/EVSE-specific fee line item was found. Exhaustive re-chase 2026-07-20: the City's Fees page and its linked '2026 Fee Schedule' PDF (lovgov.org, document ID 60275) both return HTTP 403 to automated fetch (direct WebFetch and browser-header curl alike), and no Wayback Machine snapshot of that specific document ID exists (only a 2021 snapshot of an older Exhibit A fee-schedule document ID was found, too outdated to cite as current). The governing mechanism itself -- ICC Building Valuation Data applied per square foot/valuation, not a fixed per-project dollar table -- is confirmed via the City's own Electrical Fast Track application instructions, but a specific current per-tier dollar figure could not be independently pulled this session. Confirm exact current cost with Building Division, (970) 962-2505.
Based on the current ICC Building Valuation Data applied to the stated project valuation on the Electrical Fast Track application

Review timeline

Plan reviewLoveland’s published plan-review target
3–3 business days

How long did your EV Charger / EVSE Permit permit actually take in Loveland?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Service Connection

    Wiring, breaker/panel capacity, and disconnect placement before energizing, same as any electrical service work

  2. 2

    Final

    Charger circuit installed, labeled, and energized per NEC/adopted electrical code

See the full Loveland inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated 'EV charger permit' form in Loveland — apply through the same Residential (or non-residential) Electrical Fast Track process used for any panel or circuit change.
  • If adding a charger requires a panel/service upgrade, budget time for the Electric Service Worksheet (ESW) step with Loveland Water and Power's Distribution Design division before the electrical permit can be issued.
  • Larger, stand-alone commercial EV charging stations (not accessory to an existing use) fall under the City's newer UDC 'EV Charging Project' land-use category, which is a separate track from the building/electrical permit and was moving through Planning Commission/City Council adoption in the 2025-2026 UDC update cycle.
  • Colorado has no dedicated statewide EV-charger fee schedule; HB24-1173 governs permitting timeline/process, not fee amounts, which remain locally set.

Frequently asked questions

Loveland requires an ev charger / evse permit for: Electrical contractor must hold a valid City of Loveland contractor license prior to applying, same as any other electrical permit; For a service equipment change/amp increase to support EV charging, an Electric Service Worksheet (ESW) signed by a Loveland Water and Power Distribution Designer is required before permit issuance (same rule that applies to any service upgrade); Apply via the Residential Electrical Fast Track Permit Application (Service Upgrade, Service Alteration, or Electrical Work types) to eplan-buildingfasttrack@cityofloveland.org; no separate EV-specific application form was found; Under HB24-1173 (effective statewide August 7, 2024; compliance required of covered jurisdictions by December 31, 2025), the permitting agency must notify the applicant of approval, conditional approval, or denial within 3 business days of making its determination, and denials may be based only on non-compliance with published objective standards or health/safety; Stand-alone or primary-use EV charging stations (as opposed to an accessory charger at a home or business) are reviewed under the City's new UDC 'EV Charging Project' use category, which the Loveland Planning Commission and City Council considered through public hearings in fall 2025 (Planning Commission hearing October 27, 2025; City Council hearing scheduled November 18, 2025) to align local code with the State's EV MLUC and HB24-1173/HB24-1304; Effective February 2026 (Ordinance No. 6816, second reading February 17, 2026, adopting Loveland Municipal Code Chapter 15.50), new buildings must be designed per the Colorado Model Electric Ready and Solar Ready Code, which sets EV-charging-infrastructure-readiness requirements (e.g., raceway/panel capacity) for qualifying new construction — this affects what a future EV charger install will connect to, but is a new-construction requirement, not a fee for the charger permit itself. If your project isn't listed, confirm with City of Loveland Building Division (Development Services Department) at (970) 962-2505 before starting work.

No dedicated fee line item was found. An EV charger circuit is billed like any other electrical work under the City's valuation-based Building Permit Fee via the Residential Electrical Fast Track process.

Loveland's published plan-review target for an ev charger / evse permit is 3–3 business days.

You'll need: Residential Electrical Fast Track Permit Application. Depending on your project, Loveland may also ask for: Electric Service Worksheet (ESW). See the required-documents checklist on this page for details on each.

Loveland requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In / Service Connection, Final. Schedule each through City of Loveland Building Division (Development Services Department) ((970) 962-2505).

Apply through City of Loveland Building Division (Development Services Department) at 410 E. 5th Street, Loveland, CO 80537. Phone: (970) 962-2505, email: eplan-res@cityofloveland.org (residential); eplan-building@cityofloveland.org (non-residential). Office hours: Lobby Hours: Monday-Friday 7:30 AM-4:00 PM; Phone Hours: Monday-Friday 7:30 AM-3:30 PM. Inspection Line: (970) 962-2100. Official information: https://www.lovgov.org/services/development-services/building-division.

Loveland, Colorado has adopted: Colorado has no statewide mandatory building code for municipalities; each home-rule or statutory city adopts and amends its own building code edition. Colorado's only statewide floor is an energy/greenhouse-gas standard: House Bill 22-1362 (2022), codified in relevant part at C.R.S. Title 24 and repealing portions of the prior C.R.S. 30-28-211 energy-code statute, directs the Colorado Energy Code Board to publish a Model Electric Ready and Solar Ready Code and a Model Low Energy and Carbon Code, which local governments (and certain state agencies) must adopt on their own timelines or otherwise demonstrate equivalent/greater stringency. Source: Colorado General Assembly, HB22-1362 (leg.colorado.gov/bills/hb22-1362); Colorado Energy Office Energy Code Board. Applicants should confirm the specific edition/amendments in effect for their city, since Colorado building codes vary by municipality.; City of Loveland runs its own Building Division and adopts/amends its own code within the Unified Development Code (Title 18) and Municipal Code (Title 15) framework — it is NOT a DOLA/state-administered program. Effective July 1, 2026, the City Council-adopted amendments move Loveland to the 2024 International Building Code (IBC) and 2024 International Residential Code (IRC) family (referenced in the City's 'Building Code adopted changes (ICC 2024)' notice, approved on second reading June 2, 2026); prior to that date the currently effective editions are the 2021 IRC, 2021 IMC (Mechanical), and 2021 IFGC (Fuel Gas), per City of Loveland Residential HVAC/Gas Load Fast Track forms dated 5/27/2026. Source: City of Loveland Building Division homepage and Loveland Building Code Amendments page (lovgov.org/services/development-services/building-division; lovgov.org/services/development-services/building-division/loveland-building-code).; Effective July 1, 2026, City of Loveland adopts the Colorado Model Low Energy and Carbon Code (combining the Colorado Model Electric Ready and Solar Ready Code with the 2024 International Energy Conservation Code (IECC)) to satisfy the HB22-1362 statewide energy-code floor. Source: City of Loveland 'City Council approves building-related code changes' notice (lovgov.org/home/showpublisheddocument/63720/639162471002370000).; Effective July 1, 2026, City of Loveland adopts Appendix BC (Accessory Dwelling Units) from the International Residential Code, with local amendments to align with the Unified Development Code, and now allows a property owner to act as general contractor on an ADU provided all subcontractors hold a valid City of Loveland contractor license. Source: City of Loveland code-changes notice.; Effective July 1, 2026, City of Loveland adopts Appendix BE from the International Residential Code (Radon Control Methods) for all new commercial and residential buildings, with new rough-radon, final-radon, and radon-mitigation-certificate inspections. Source: City of Loveland code-changes notice.; Building Valuation Data Table (square-foot construction costs by ICC occupancy group and construction type), effective March 15, 2026, is used by the City to calculate building-permit valuation; the City's fee schedule states 'Building permit fees are based on the current ICC Fees' via the ICC Building Valuation Data publication (iccsafe.org/products-and-services/i-codes/code-development-process/building-valuation-data/). Source: City of Loveland Building Valuation Data Table PDF (lovgov.org/home/showpublisheddocument/60277/639090010225200000) and 2026 Fee Schedule (lovgov.org/home/showpublisheddocument/60275/639089984528770000).. Local amendments apply — see the Loveland overview page for the full list.

Colorado HB24-1173 requires covered jurisdictions (municipalities with population 10,000+, which includes Loveland) to notify applicants of approval, conditional approval, or denial within 3 business days of making that determination for EV charging system permits.