Lamar building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Lamar, Colorado.
Verified 2026-07-23 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Lamar Community Resource & Senior Center, 405/407 E. Olive, Lamar, CO (mailing: 102 E Parmenter St, Lamar, CO 81052)
- Phone
- 719-336-2085
- Office hours
- Monday-Friday, 8:00 AM - 4:00 PM. Inspections conducted Monday-Friday between 9:00 AM and 3:00 PM; 24 hours advance notice required by calling 719-336-2085. Staff: Tony Gratta (Building Inspector) and Joy Dashner (Assistant Building Inspector), both reachable at 719-336-2085 / buildingcodes@ci.lamar.co.us.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Foundation
Before concrete pour, per 36-inch minimum frost depth; scheduled 24 hours in advance, Monday-Friday 9:00 AM-3:00 PM
- 2
Framing
Structural framing complete before cover
- 3
Final Inspection (Building)
All Building Department-inspected work complete per approved plans and adopted codes. Electrical, interior plumbing, and gas-line inspections are separately conducted by Colorado DORA, not the City.
Applies to: Commercial Tenant Improvement / Plan Review
- 1
Rough Inspections (per trade, as applicable)
Building/mechanical rough-ins before concealment; electrical/interior plumbing inspected separately by Colorado DORA
- 2
Final Inspection
All City-inspected work complete per approved plans and adopted codes
Applies to: Deck / Covered Patio Permit
- 1
Footing/Foundation
Before concrete pour, per 36-inch minimum frost depth
- 2
Final Inspection
Completed deck/patio/covered structure verified per approved plans
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified by City of Lamar Building Department staff
Applies to: Residential Addition / Remodel Permit
- 1
Rough Framing
Framing complete, connection to existing structure verified before cover
- 2
Final Inspection (Building)
All work complete per approved plans; electrical/plumbing inspected separately by Colorado DORA if applicable
Applies to: Rooftop Solar / Photovoltaic Permit
- 1
Final Inspection (mounting/structural)
Roof penetrations and racking verified by City of Lamar Building Department
- 2
State Electrical Inspection (interconnection)
Conducted by the Colorado DORA State Electrical Board, not the City of Lamar
Final inspection only: Demolition Permit, Electrical Permit (State-Administered), EV Charger / EVSE Permit, Plumbing Permit, Re-Roof Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lamar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lamar building permits
Get alerts for Lamar