Re-Roof Permit in Lamar, Colorado

Re-roofing work in Lamar requires a Building Permit under the general Building Permit Application (there is no separate re-roof-specific application or fee line item published by the City); reviewed under the 2018 IBC/IRC as adopted, subject to the City's Climatic and Geographic Design Criteria, including required ice barrier underlayment.

Verified 2026-07-23 · Source

When you need this permit

  • Building Permit Application (2026 form) required per LMC Sec. 6-2, since re-roofing is a structural alteration
  • Ice barrier underlayment required, per the City's Climatic and Geographic Design Criteria
  • City of Lamar Contractor's License required for the roofing contractor performing the work Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, same schedule as new construction)No separate flat re-roof fee is published; billed under the general valuation-based Building Permit Fee schedule. RE-CONFIRMED 2026-07-23: re-downloaded the live 2026 Rate and Fee Schedule PDF (27-page scanned document, no embedded text layer) and visually rendered and read every fee-bearing page (Zoning & Planning, Miscellaneous, Accessory Structures/License/Plumbing, Building Permits valuation table, Mechanical Permits, Demolition Permits) plus the live 2026 Building Permit Application form directly — no 'Deck,' 'Patio,' 'Porch,' 'Roof,' or 're-roof' line item or checkbox exists anywhere in either document; the general Type-of-Permit selector on the application form (Building/Mechanical/Demolition/Signage/Plumbing) has no roofing-specific category either, confirming re-roofs are billed as a standard Building Permit.
$33.00 minimum, scaling per the valuation tiers in the 2026 Rate and Fee Schedule
Use Tax
3% of materials value not already subject to sales tax collection

Review timeline

Plan review
Not published — contact the department

How long did your Re-Roof Permit permit actually take in Lamar?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (roof)

    Completed roof — material and ice barrier underlayment compliance verified

See the full Lamar inspection guide — scheduling & re-inspection fees →

Tips

  • Lamar requires ice barrier underlayment on roofs per its published Climatic and Geographic Design Criteria — confirm your roofing contractor is pricing this in.
  • There is no discounted or flat re-roof permit fee in Lamar's published fee schedule — re-roofs are billed under the same valuation-based Building Permit Fee table as new construction.

Frequently asked questions

Lamar requires a re-roof permit for: Building Permit Application (2026 form) required per LMC Sec. 6-2, since re-roofing is a structural alteration; Ice barrier underlayment required, per the City's Climatic and Geographic Design Criteria; City of Lamar Contractor's License required for the roofing contractor performing the work. If your project isn't listed, confirm with City of Lamar Building Department at 719-336-2085 before starting work.

In Lamar, the published Building Permit Fee (valuation-based, same schedule as new construction) is: $33.00 minimum, scaling per the valuation tiers in the 2026 Rate and Fee Schedule. Additional published fees: Use Tax — 3% of materials value not already subject to sales tax collection. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lamar does not publish a plan-review timeline for this permit. Contact City of Lamar Building Department at 719-336-2085 for current turnaround.

You'll need: Building Permit Application (2026) — Building/Residential scope. See the required-documents checklist on this page for details on each.

Lamar requires 1 inspection(s) for a re-roof permit, in order: Final Inspection (roof). Schedule each through City of Lamar Building Department (719-336-2085).

Apply through City of Lamar Building Department at Lamar Community Resource & Senior Center, 405/407 E. Olive, Lamar, CO (mailing: 102 E Parmenter St, Lamar, CO 81052). Phone: 719-336-2085, email: buildingcodes@ci.lamar.co.us. Office hours: Monday-Friday, 8:00 AM - 4:00 PM. Inspections conducted Monday-Friday between 9:00 AM and 3:00 PM; 24 hours advance notice required by calling 719-336-2085. Staff: Tony Gratta (Building Inspector) and Joy Dashner (Assistant Building Inspector), both reachable at 719-336-2085 / buildingcodes@ci.lamar.co.us.. Official information: https://ci.lamar.co.us/building-department.

Lamar, Colorado has adopted: 2018 International Building Code (IBC); 2018 International Residential Code (IRC); 2018 International Mechanical Code (IMC) (listed on the City's page as '2018 Mechanical Code'); 2018 International Plumbing Code (IPC); 2018 International Fire Code (IFC); 2018 International Fuel Gas Code (IFGC); 2018 International Existing Building Code (IEBC); 2018 International Energy Conservation Code (IECC) (listed on the City's page as '2018 International Energy Code'); 2015 International Energy Conservation Code (listed separately on the City's page as '2015 Energy Conservation Code' alongside the 2018 IECC entry — the page lists both without clarifying which governs; treated here as a verbatim-as-published discrepancy rather than resolved by assumption); 2015 International Swimming Pool and Spa Code (ISPSC); 2010 Americans with Disabilities Act (ADA) standards; 2006 International Property Maintenance Code (IPMC); Codes are enforced within Lamar city limits AND for any properties connected/connecting to City water/wastewater within a 3-mile radius of the City limits, per the Building Department's own scoping statement.; HB22-1362 (Colorado Building Greenhouse Gas Emissions Act) compliance note: Lamar's own Building Department webpage lists the 2018 IECC (plus a separately-listed 2015 Energy Conservation Code entry) as the currently enforced energy code, which pre-dates the 2021 IECC-family editions that HB22-1362 nominally directs Colorado jurisdictions to adopt on a phased statewide timeline. HB22-1362's own statutory carve-out mechanism is a 'rural county' exemption (grant-application-contingent, allowing continued use of one of the 3 most recent IECC editions in lieu of the model low-energy/electric-ready codes) that applies at the COUNTY level, not a flat municipal population threshold — Prowers County (est. population ~11,900-12,300) would plausibly qualify as rural under this mechanism, but the City's own webpage does not cite HB22-1362, a grant application, or any rural-county determination as the basis for its 2018 IECC adoption. This is reported as an honest as-published discrepancy, not resolved by assumption; confidence on code-currency is 'partial' for this reason alone (the codes-adopted list itself, as literally published by the City, is verified).. Local amendments apply — see the Lamar overview page for the full list.

No. The City of Lamar uses its general Building Permit Application for re-roofing work; there is no distinct re-roof-specific form or fee line item published.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lamar building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.