The Town of Saguache has no dedicated solar/photovoltaic permit type, no adopted model building code, and no dedicated Building Department — but a solar installation within Town limits is still subject to the Town's general Building Permit requirement (per the Town's own 'Licenses and Permits' page and the downloadable 'Application for Building Site Permit'), administered by the Town Clerk/Deputy Clerk. Regardless of the Town's minimal local process, Colorado state law caps what ANY local government (including a small statutory town like Saguache) may charge in aggregate fees for a solar installation, and the electrical-connection scope is handled entirely by the State of Colorado, not the Town.

Verified 2026-07-23 · Source

When you need this permit

  • Contact the Town Clerk or Deputy Clerk at Saguache Town Hall (504 San Juan Avenue, P.O. Box 417, Saguache, CO 81149; 719-655-2232) — the Town's Application for Building Site Permit form does not list a dedicated 'Solar' checkbox among its project-type options (New Construction, Addition, Bridges/Walkways/Driveways, Roof Replacement, Fence or Deck, Demolition, Mobile Home, Single/Multi Unit Residence, Lot Level Change, Commercial); a solar installation likely falls under 'New Construction,' 'Addition,' or 'Commercial/Industrial' depending on scope — confirm with the Town Clerk which category to select
  • No adopted model building code (IBC/IRC) governs technical plan review, per ColoradoEnergy.org's independently-verified 'No Building Codes' finding for the Town and Municipal Code Chapter 18 itself (which contains no code adoption)
  • Electrical-connection work is NOT administered by the Town — apply directly to the Colorado State Electrical Board (DORA, Division of Professions and Occupations), consistent with the general Colorado pattern of small statutory towns without their own trade-permitting programs
  • Statewide fee cap under C.R.S. § 24-48.5-113 (enacted by HB21-1284): the AGGREGATE of all charges/fees ANY Colorado governmental body — including a small statutory town like Saguache — may impose to install an active solar energy system is capped at $500 for a residential system under 10kW and $1,000 for a commercial system or a residential system 10kW or over; this statute contains no population-based exemption, so it applies to Saguache's Town fee (whatever that fee turns out to be, since none is published) exactly as it would to a larger city
  • HB25-1096's automated-permitting mandate (requiring an automated platform such as SolarAPP+) applies only to municipalities with population over 5,000 — Saguache's population (539) is well under that threshold, so the Town is NOT required to offer automated solar permitting under that statute

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Town of Saguache Building Permit Fee (structural/general scope)
Per the Town's own codified Municipal Code, Appendix 2-F (Consolidated Fee Schedule, library.municode.com, 'VERSION: FEB 1, 2024 (CURRENT)'), which states verbatim under 'BUILDING PERMITS': 'Building… Show full citationPer the Town's own codified Municipal Code, Appendix 2-F (Consolidated Fee Schedule, library.municode.com, 'VERSION: FEB 1, 2024 (CURRENT)'), which states verbatim under 'BUILDING PERMITS': 'Building Permit (valid for 1 year from date of issue)... $20.00.' This is the same general Building Permit fee documented in the residential-building-permit entry; a solar installation using the Town's general Building Permit is subject to this same $20.00 fee (plus the separate State electrical-connection fee below), well within the $500/$1,000 statutory cap of C.R.S. § 24-48.5-113 (HB21-1284), which applies to every Colorado local government regardless of population or whether it has adopted a model building code.
$20.00
State of Colorado electrical permit fees (electrical-connection scope)
Confirmed 2026-07-20 against the DORA State Electrical Board's own live fee-schedule document (hosted by the Town of Larkspur, CO, at townoflarkspur.org/media/2901, printed with DORA's own Denver… Show full citationConfirmed 2026-07-20 against the DORA State Electrical Board's own live fee-schedule document (hosted by the Town of Larkspur, CO, at townoflarkspur.org/media/2901, printed with DORA's own Denver address/phone: 1560 Broadway Suite 1350, Denver, 303.894.2300), Section B "Commercial and other fees." Larimer County's current equivalent (Table 1-E, larimer.org/sites/default/files/2020_electrical_fee_table.pdf) explicitly confirms solar falls under this same valuation-based bracket and cites the identical $500/$1,000 statutory cap. Since Saguache has no local electrical inspection program (electrical is a matter of statewide concern per C.R.S. § 12-23-117, and no local government may charge more than 1.15x this state schedule), this state schedule governs the electrical scope of a Saguache solar installation directly.
Statewide valuation-based schedule under C.R.S. § 12-23-117: base fee ~$100-$120 for job valuation up to $2,000, plus roughly $10-$11.50 per $1,000 of valuation above that — capped in aggregate (with the Town's building-permit fee) at $500 residential/$1,000 commercial by C.R.S. § 24-48.5-113

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit (Town Building Permit, Statewide Fee Cap) permit actually take in Saguache?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Town Hall Review (Clerk / Deputy Clerk)

    Same generalist review process as the Town's general Building Permit — no dedicated Building Official or technical plan-review process is documented for the Town

  2. 2

    State of Colorado Electrical Inspection(s)

    Scheduled directly with the Colorado State Electrical Board (DORA), not through the Town

See the full Saguache inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated solar permit or checkbox in Saguache — use the Town's general 'Application for Building Site Permit' and confirm with the Town Clerk (719-655-2232) which project-type box to check.
  • Even though the Town has adopted no building code at all and charges no published fee, Colorado's statewide solar-fee cap (C.R.S. § 24-48.5-113) still legally limits whatever the Town ultimately charges to $500 (residential under 10kW) or $1,000 (commercial/larger residential) in aggregate — this statute has no small-town population exemption.
  • Electrical work is handled entirely by the State of Colorado (DORA State Electrical Board), not the Town — apply and schedule inspections directly with the State.
  • Because Saguache's population (539) is far below HB25-1096's 5,000-person threshold, don't expect an automated/instant permitting portal here the way a larger Colorado city might offer.

Frequently asked questions

Saguache requires a solar pv permit (town building permit, statewide fee cap) for: Contact the Town Clerk or Deputy Clerk at Saguache Town Hall (504 San Juan Avenue, P.O. Box 417, Saguache, CO 81149; 719-655-2232) — the Town's Application for Building Site Permit form does not list a dedicated 'Solar' checkbox among its project-type options (New Construction, Addition, Bridges/Walkways/Driveways, Roof Replacement, Fence or Deck, Demolition, Mobile Home, Single/Multi Unit Residence, Lot Level Change, Commercial); a solar installation likely falls under 'New Construction,' 'Addition,' or 'Commercial/Industrial' depending on scope — confirm with the Town Clerk which category to select; No adopted model building code (IBC/IRC) governs technical plan review, per ColoradoEnergy.org's independently-verified 'No Building Codes' finding for the Town and Municipal Code Chapter 18 itself (which contains no code adoption); Electrical-connection work is NOT administered by the Town — apply directly to the Colorado State Electrical Board (DORA, Division of Professions and Occupations), consistent with the general Colorado pattern of small statutory towns without their own trade-permitting programs; Statewide fee cap under C.R.S. § 24-48.5-113 (enacted by HB21-1284): the AGGREGATE of all charges/fees ANY Colorado governmental body — including a small statutory town like Saguache — may impose to install an active solar energy system is capped at $500 for a residential system under 10kW and $1,000 for a commercial system or a residential system 10kW or over; this statute contains no population-based exemption, so it applies to Saguache's Town fee (whatever that fee turns out to be, since none is published) exactly as it would to a larger city; HB25-1096's automated-permitting mandate (requiring an automated platform such as SolarAPP+) applies only to municipalities with population over 5,000 — Saguache's population (539) is well under that threshold, so the Town is NOT required to offer automated solar permitting under that statute. If your project isn't listed, confirm with Town of Saguache Town Hall (Town Clerk / Deputy Clerk administer Building Permit applications; no dedicated Building Department) at 719-655-2232 before starting work.

No fee amount is published by the Town, but Colorado state law (C.R.S. § 24-48.5-113, enacted by HB21-1284) caps the aggregate of all local-government fees for a solar installation at $500 for a residential system under 10kW, or $1,000 for a commercial system or a residential system 10kW or larger — this cap applies to every Colorado local government, including small statutory towns like Saguache, with no population-based exemption.

Saguache does not publish a plan-review timeline for this permit. Contact Town of Saguache Town Hall (Town Clerk / Deputy Clerk administer Building Permit applications; no dedicated Building Department) at 719-655-2232 for current turnaround.

You'll need: Application for Building Site Permit. See the required-documents checklist on this page for details on each.

Saguache requires 2 inspection(s) for a solar pv permit (town building permit, statewide fee cap), in order: Town Hall Review (Clerk / Deputy Clerk), State of Colorado Electrical Inspection(s). Schedule each through Town of Saguache Town Hall (Town Clerk / Deputy Clerk administer Building Permit applications; no dedicated Building Department) (719-655-2232).

Apply through Town of Saguache Town Hall (Town Clerk / Deputy Clerk administer Building Permit applications; no dedicated Building Department) at 504 San Juan Avenue, P.O. Box 417, Saguache, CO 81149. Phone: 719-655-2232, email: townclerk@townofsaguache.org. Office hours: Monday through Friday, 8:00 a.m. to 4:30 p.m., per the Town Hall page as preserved by the Wayback Machine (townofsaguache.org/town-hall-546.htm, captured 2025-12-10). NOTE: the Town's website has been migrated/rebuilt on Netlify and no longer publishes this page or most of its prior content (see sources note below); hours/contact are carried forward from the last-known-good archived capture, cross-verified independently against ColoradoEnergy.org's own listed Town Clerk contact (matches exactly: 504 San Juan Ave, Saguache, CO 81149, 719-655-2232).. Official information: https://www.townofsaguache.org/.

Saguache, Colorado has adopted: NONE — ColoradoEnergy.org, a statewide Colorado building/energy code-adoption tracking directory maintained independently of any single jurisdiction, lists the Town of Saguache's Building Code status explicitly as 'No Building Codes' (coloradoenergy.org/codes/codes.aspx?City=Saguache), with a Town Clerk contact (504 San Juan Ave, Saguache, CO 81149, 719-655-2232) matching the Town Hall contact exactly — confirming this listing is genuinely about the Town, not Saguache County. NOTE: coloradoenergy.org's HTTPS endpoint has been intermittently unresponsive, and its own Wayback captures for this exact page stop at 2010; the 'No Building Codes' finding rests on the independent Town Clerk contact match above, not the ColoradoEnergy.org citation alone — and it is corroborated by the Town's own Municipal Code (see the next note).; The Town's Municode Chapter 18 (library.municode.com/co/saguache/codes/municipal_code?nodeId=CD_ORD_CH18BURE), 'CHAPTER 18 - Building Regulations,' is codified through Ordinance No. 2023-2 (enacted March 13, 2023) and contains exactly three articles, none of which adopt a model construction code: Article 1 (Sec. 18-1-10 through 18-1-90), Dangerous Buildings — an unsafe-structure abatement/demolition procedure whose text references 'the adopted building code' only as hypothetical boilerplate (comparing a damaged structure's remaining strength to what a new building would need), never naming or adopting the IBC/IRC/any specific code; Article 2 (Sec. 18-2-10 through 18-2-80), Flood Damage Prevention — a FEMA/NFIP floodplain-management ordinance adopted under Title 29 C.R.S. authority, unrelated to general construction permitting; Article 3 (Sec. 18-3-10 through 18-3-50), Manufactured Homes, Mobile Homes, Mobile Home Parks and RV Parks — zoning/prohibition rules, not a construction code adoption. This confirms, from the Town's own primary source rather than the third-party ColoradoEnergy.org directory alone, that the Town has NOT adopted the IBC/IRC or any other model building code.; Chapter 18's verbatim text is published only through Municode's client-rendered viewer (library.municode.com/co/saguache); the chapter contains no fee schedule, permit-issuance procedure, or code-edition citation beyond the three articles described above.; No adopted electrical code (NEC) or plumbing code (IPC) edition is attributable to the Town specifically; per Colorado's standard structure for small statutory towns without their own trade-permitting programs, electrical and plumbing work is presumed to fall to Colorado DORA state board licensing/permitting rather than a Town-run trade-permit program, but no Town electrical or plumbing permit process is asserted here given the complete absence of any Town-published fee, form, or procedure for either trade (see localAmendments).. Local amendments apply — see the Saguache overview page for the full list.

No dedicated solar permit exists — a solar installation uses the Town's general Building Permit (Application for Building Site Permit), administered by the Town Clerk/Deputy Clerk, since the Town has no dedicated Building Department and has adopted no model building code.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Saguache building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Property Access

Saguache's permit history is searchable by address

46 permits on record for Saguache, 2025–2025 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free