Silverthorne building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Silverthorne, Colorado.
Verified 2026-07-13 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 601 Center Circle, P.O. Box 1309, Silverthorne, CO 80498
- Phone
- 970-262-7360
- Office hours
- Monday through Friday, 8 a.m. to 5 p.m.; building permit submittal appointments required (per Community Development FAQ). Town Hall main line (970) 262-7300; Community Development/Building direct line (970) 262-7360. Electrical permits are handled separately by the Summit County Building Department, 0037 Peak One Drive / 37 S.C.R. 1005, Frisco, CO, (970) 668-3170.
- Website
- Official site
Published scheduling rules
- Building inspection requests go through the SmartGov portal by 5 p.m. the day before, but Town-specific final inspections (Engineering/Water-Sewer/Planning) must instead be emailed to buildinginfo@silverthorne.org at least 48 hours in advance — don't assume one channel covers both. (New Residential Construction Building Permit (SFR Attached and Detached))
- If your CO is targeted for November through April, budget for the 150% landscaping-security requirement before that inspection can be scheduled. (New Residential Construction Building Permit (SFR Attached and Detached))
- Two separate advance-notice windows apply to inspections: SmartGov-portal building inspection requests need to be made by 5 p.m. the prior business day, but Town-specific final inspections (Engineering, Water/Sewer, Planning) must be emailed to buildinginfo@silverthorne.org at least 48 hours (two business days) in advance — a stricter, separate lead time from the general inspection-request channel. (General)
Inspection sequence
Applies to: New Residential Construction Building Permit (SFR Attached and Detached)
- 1
Foundation / Footing
Performed by Summit County Building Department; a stamped Setback ILC must be submitted to the Town Planning Department at least 24 hours before this inspection is requested
- 2
Foundation Drain / Damp-Proofing / Waterproofing / Foundation Insulation
Must be inspected separately per Town amendment
- 3
Framing
Performed by Summit County Building Department; a Height ILC is required 24 hours in advance for structures near maximum building height
- 4
Final Inspection (Town Engineering, Water/Sewer, Planning)
Town of Silverthorne conducts its own final inspections (Engineering, Water/Sewer, Planning) prior to Certificate of Occupancy; request by email at least two business days in advance
Applies to: Accessory Dwelling Unit / Single Apartment Building Permit
- 1
Foundation (attached/detached new construction)
Performed by Summit County Building Department; not applicable to the remodel-of-existing-home ADU sub-type unless new footings are involved
- 2
Rough Frame / Rough Trades
Framing and trade rough-ins before concealment
- 3
Final Inspection
Town final inspections (Planning/Engineering as applicable) plus Summit County final building inspection
Applies to: Residential Addition / Remodel Building Permit
- 1
Foundation (additions with new footings)
Performed by Summit County Building Department
- 2
Rough Frame / Rough Trades
Framing, electrical, plumbing, mechanical rough-ins before concealment
- 3
Final Inspection
Town final inspections (Engineering/Water-Sewer/Planning where applicable) plus Summit County final building inspection
Applies to: Electrical Permit
- 1
Rough Electrical
Performed by Summit County Building Department before concealment
- 2
Final Electrical
Performed by Summit County Building Department; system energized and verified
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical (if applicable)
Performed by Summit County Building Department before concealment
- 2
Final Electrical
Performed by Summit County Building Department; charging circuit energized and verified
Applies to: Residential Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Residential Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment; manufacturer specs must be posted on-site
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Demolition Permit, Retaining Wall (Standalone) Permit, Solar Photovoltaic (PV) Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Silverthorne building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Silverthorne building permits
Get alerts for Silverthorne
We'll email you when Silverthorne's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.