New Residential Construction Building Permit (SFR Attached and Detached) in Silverthorne, Colorado
Required for new single-family residential construction (attached and detached) in Silverthorne. The Town's Planning, Engineering, and Water/Sewer Departments review for Town Code compliance while the Summit County Building Department conducts the Building Code plan review and performs inspections. Reviewed under the 2018 IBC/IRC package as locally amended.
Verified 2026-07-13 · Source
When you need this permit
- Site plan with topographical information; building height table per Town Code definition of building height
- Water and sewer service line details shown on site plans and mechanical plans
- Construction management plan; erosion control and grading plan
- Landscape plan (Town Code Section 4-6-14) including revegetation information and designated snow storage area(s)
- Tree conservation plan (Town Code Article VIII, Environmental Guidelines)
- Exterior lighting location on architectural elevations, plus exterior lighting spec sheet
- Architectural plans (floor plans, elevations, materials); elevations with USGS ties for height calculations
- Structural drawings stamped by a Colorado-licensed architect/engineer, including design loads, code versions, and project type; foundation plans; framing plans
- Soils report; HOA approval if applicable; warranty deed if applicable for new ownership
- Summit Fire & EMS fire mitigation permit required for all new construction; life-safety/sprinkler permit required for Eagles Nest Golf Course Filings 1-5 or homes over 6,000 SF
- Plan Review: Town of Silverthorne Planning, Engineering, and Water and Sewer departments review per Town Code; Summit County Building Department conducts the Building Code plan review
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Performed by Summit County Building Department; a stamped Setback ILC must be submitted to the Town Planning Department at least 24 hours before this inspection is requested
- 2
Foundation Drain / Damp-Proofing / Waterproofing / Foundation Insulation
Must be inspected separately per Town amendment
- 3
Framing
Performed by Summit County Building Department; a Height ILC is required 24 hours in advance for structures near maximum building height
- 4
Final Inspection (Town Engineering, Water/Sewer, Planning)
Town of Silverthorne conducts its own final inspections (Engineering, Water/Sewer, Planning) prior to Certificate of Occupancy; request by email at least two business days in advance
See the full Silverthorne inspection guide — scheduling & re-inspection fees →
Tips
- Two different governments touch this permit: the Town issues it and reviews for Town Code (planning, engineering, water/sewer), but Summit County Building Department does the actual IBC/IRC plan review and inspections — budget contact time with both.
- Building inspection requests go through the SmartGov portal by 5 p.m. the day before, but Town-specific final inspections (Engineering/Water-Sewer/Planning) must instead be emailed to buildinginfo@silverthorne.org at least 48 hours in advance — don't assume one channel covers both.
- Neither the Town nor Summit County publishes a numeric plan-review turnaround — ask the Building Division directly for a current-workload estimate before committing to a schedule.
- If your CO is targeted for November through April, budget for the 150% landscaping-security requirement before that inspection can be scheduled.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Silverthorne building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Silverthorne
New Residential Construction Building Permit (SFR Attached and Detached) in other cities
Look up this fee in a different city →
Now live
Build your Silverthorne project checklist
Describe your project once and get every permit, document, and fee it triggers in Silverthorne — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →