Solar Photovoltaic (PV) Permit — Silverthorne, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.summitcountyco.gov/1442/Photovoltaic-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Silverthorne, Colorado
Required for installing a rooftop or ground-mount photovoltaic system in Silverthorne. Applications are submitted through the Town of Silverthorne (Community Development Technician intake, with Town Planning, Engineering, and Water & Sewer departments reviewing per Town Code), but the substantive building/electrical code plan review, PV-specific fee, permit issuance, and inspections for the photovoltaic system are performed by the Summit County Building Department — the same county department that handles ALL electrical permits for Silverthorne, since the Town does not intake, fee, or issue electrical/PV permits itself.
Verified 2026-07-20 · Source
When you need this permit
- Submit through the Town of Silverthorne; the Community Development Technician reviews for completeness, then routes to Town Planning, Engineering, and Water & Sewer for Town Code compliance
- Summit County Building Department separately reviews the PV system against the Building Code and issues the actual Photovoltaic Permit
- Residential roof-mounted systems under 15 kW may be issued over the counter if all submittal materials are provided
- Plan review is mandatory for residential systems over 15 kW, all ground-mounted systems, and all commercial systems
- Payment for plan review is required at the time of submittal for any system requiring review
- Applicants must submit in person with a representative, per Summit County's PV submittal process
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Summit County PV Inspection(s)
Performed by the Summit County Building Department under the Photovoltaic Permit
See the full Silverthorne inspection guide — scheduling & re-inspection fees →
Tips
- Silverthorne's solar fee structure lands exactly on Colorado's statewide caps: $175 plan review + $325 permit = $500.00 total residential (the maximum allowed under HB21-1284), and $350 + $650 = $1,000.00 total commercial (also the maximum allowed) — Summit County appears to have set these fees to exactly match the state cap.
- A residential roof-mounted system under 15kW with a complete submittal can be issued over the counter — no plan review wait required — while anything over 15kW, any ground-mounted system, and all commercial systems require a full plan review.
- Even though the Town of Silverthorne intakes the application and its own departments (Planning, Engineering, Water & Sewer) review for Town Code compliance, the PV-specific permit, fee, and inspections are entirely a Summit County Building Department function — budget for coordination between two agencies.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Silverthorne building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Silverthorne
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Colorado →
Look up this fee in a different city →