Fire protection for Silverthorne is provided by Summit Fire & EMS Fire Protection District (P.O. Box 4910, Frisco, CO 80443; (970) 262-5100; permits@summitfire.org) — the same district already referenced elsewhere in this file as the outside agency requiring fire-mitigation and life-safety/sprinkler permits alongside Town building permits. Summit Fire & EMS's own Permits page separately and explicitly lists sprinklers and monitored fire alarms as one of its permit-requiring categories, applied for and paid directly to the District (not the Town of Silverthorne). Governed by the International Fire Code as adopted by Summit Fire & EMS, plus current editions of NFPA 13/13R/13D (building fire sprinklers) and NFPA 72 (fire alarms).

Verified 2026-08-14 · Source

When you need this permit

  • A Summit Fire & EMS permit is required for sprinklers and monitored fire alarms, in addition to and separate from any Town of Silverthorne building permit
  • Governed by the International Fire Code as adopted by Summit Fire & EMS, plus current editions of NFPA 13, 13R, 13D (building fire sprinklers) and NFPA 72 (fire alarms)
  • Application submitted directly to Summit Fire & EMS via its online 'Apply for a Permit' portal; permit fees are due at time of application by electronic check or credit card
  • Drawings: one digital copy submitted as a PDF with the permit application; minimum acceptable scale 1/8 inch to the foot; owner/installing-contractor name, address, and phone furnished; contractor's license classification and number stamped on drawings; equipment data sheets for each device with applicable information highlighted; symbols per NFPA 170; ceiling heights/detail and square footage shown Contractor
  • No work shall be performed without an approved set of plans; missing or inaccurate information may lead to plan rejection and a resubmittal fee
  • Fire sprinkler and alarm final inspections must be coordinated and scheduled for the same time; inspections requested at least two business days in advance via the Inspection Request portal or (970) 262-5215
  • Certification letters are required before any system receives final approval
  • Work started without receipt of a permit results in the permit fee being doubled, per the District's Fee Schedule

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Sprinkler System Construction PermitSummit Fire & EMS Fee Schedule, Resolution 2024-06, effective 1/1/2025, Section II.6.B
$400.00 base fee, plus $4.00 per device
Fire Alarm System Construction PermitSummit Fire & EMS Fee Schedule, Resolution 2024-06, Section II.6.F
$400.00 base fee, plus $4.00 per device
Fire Alarm or Sprinkler System in One & Two Family Dwellings and Group R-3'sSummit Fire & EMS Fee Schedule, Resolution 2024-06, Section II.6.H
$400.00 base fee, plus $4.00 per device
Additional Plan Review / Resubmittal (incomplete or revised submittals)Summit Fire & EMS Fee Schedule, Resolution 2024-06, Section II.2
$150.00 per hour, one-hour minimum
Required Additional / Re-inspectionSummit Fire & EMS Fee Schedule, Resolution 2024-06, Section II.15
$200.00 for the first two hours (minimum), plus $75.00 for each additional hour or portion thereof

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm System Permit permit actually take in Silverthorne?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Sprinkler and Fire Alarm Final Inspections (coordinated)

    Fire sprinkler and alarm final inspections must be coordinated and scheduled for the same time; requested at least two business days in advance. Certification letters required before final approval.

See the full Silverthorne inspection guide — scheduling & re-inspection fees →

Tips

  • Summit Fire & EMS issues sprinkler and fire-alarm permits entirely separately from the Town of Silverthorne's building permit — apply through Summit Fire & EMS's own online portal (and pay its fee, due at application) in addition to, not instead of, your Town building permit.
  • Sprinkler and fire-alarm final inspections must be scheduled together, not separately — coordinate your contractors so both trades are ready for the same inspection date.
  • Starting sprinkler or alarm work without an approved permit doubles the fee under the District's own fee schedule — don't get ahead of plan approval.

Frequently asked questions

Silverthorne requires a fire sprinkler / fire alarm system permit for: A Summit Fire & EMS permit is required for sprinklers and monitored fire alarms, in addition to and separate from any Town of Silverthorne building permit; Governed by the International Fire Code as adopted by Summit Fire & EMS, plus current editions of NFPA 13, 13R, 13D (building fire sprinklers) and NFPA 72 (fire alarms); Application submitted directly to Summit Fire & EMS via its online 'Apply for a Permit' portal; permit fees are due at time of application by electronic check or credit card; Drawings: one digital copy submitted as a PDF with the permit application; minimum acceptable scale 1/8 inch to the foot; owner/installing-contractor name, address, and phone furnished; contractor's license classification and number stamped on drawings; equipment data sheets for each device with applicable information highlighted; symbols per NFPA 170; ceiling heights/detail and square footage shown; No work shall be performed without an approved set of plans; missing or inaccurate information may lead to plan rejection and a resubmittal fee; Fire sprinkler and alarm final inspections must be coordinated and scheduled for the same time; inspections requested at least two business days in advance via the Inspection Request portal or (970) 262-5215; Certification letters are required before any system receives final approval; Work started without receipt of a permit results in the permit fee being doubled, per the District's Fee Schedule. If your project isn't listed, confirm with Town of Silverthorne Community Development Department, Building Division at 970-262-7360 before starting work.

In Silverthorne, the published Sprinkler System Construction Permit is: $400.00 base fee, plus $4.00 per device. Additional published fees: Fire Alarm System Construction Permit — $400.00 base fee, plus $4.00 per device; Fire Alarm or Sprinkler System in One & Two Family Dwellings and Group R-3's — $400.00 base fee, plus $4.00 per device; Additional Plan Review / Resubmittal (incomplete or revised submittals) — $150.00 per hour, one-hour minimum; Required Additional / Re-inspection — $200.00 for the first two hours (minimum), plus $75.00 for each additional hour or portion thereof. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Silverthorne does not publish a plan-review timeline for this permit. Contact Town of Silverthorne Community Development Department, Building Division at 970-262-7360 for current turnaround.

You'll need: Summit Fire & EMS Permit Application (online portal); Stamped Drawings and Equipment Data Sheets. See the required-documents checklist on this page for details on each.

Silverthorne requires 1 inspection(s) for a fire sprinkler / fire alarm system permit, in order: Fire Sprinkler and Fire Alarm Final Inspections (coordinated). Schedule each through Town of Silverthorne Community Development Department, Building Division (970-262-7360).

Apply through Town of Silverthorne Community Development Department, Building Division at 601 Center Circle, P.O. Box 1309, Silverthorne, CO 80498. Phone: 970-262-7360, email: buildinginfo@silverthorne.org. Office hours: Monday through Friday, 8 a.m. to 5 p.m.; building permit submittal appointments required (per Community Development FAQ). Town Hall main line (970) 262-7300; Community Development/Building direct line (970) 262-7360. Electrical permits are handled separately by the Summit County Building Department, 0037 Peak One Drive / 37 S.C.R. 1005, Frisco, CO, (970) 668-3170.. Official information: https://www.silverthorne.org/town-government/community-development/building-copy.

Silverthorne, Colorado has adopted: 2018 International Building Code (IBC), with Town of Silverthorne local amendments — Town of Silverthorne Building Codes & Amendments page, https://www.silverthorne.org/town-government/community-development/building-copy/building-codes-construction-resources; 2018 International Fire Code (IFC), with Town of Silverthorne local amendments — same source; 2023 NFPA 70 National Electrical Code (NEC), adopted by Town Ordinance 2023-10 — the Town's own Building Codes & Amendments page attributes this specific adoption to the Summit County Building Department ('Ordinance 2023-10 2023 NFPA70 National Electrical Code Adoption - from the Summit County Building Department'), consistent with Summit County issuing and governing all electrical permits Town-wide; Underlying building-code plan review and inspection for all permit types is performed by the Summit County Building Department 'based on the Building Code most recently adopted by the Town' — Town of Silverthorne Plan Review page, https://www.silverthorne.org/town-government/community-development/building-copy/resubmittals-and-revisions; IRC Section 321.1 as locally amended (temporary/permanent address numbering requirements) and IBC Sections 105.4, 105.6, 109.1, 109.5, 109.7, 104.10, 104.11, and 3402.1 as locally amended (administrative provisions: permit suspension/revocation, inspection access, reinspection fees, code-modification authority, alternate materials/methods, and additions/alterations conforming to new-construction code) — Town of Silverthorne Building Codes & Construction Resources page, General Requirements / Administrative Requirements sections. Local amendments apply — see the Silverthorne overview page for the full list.

No. Summit Fire & EMS Fire Protection District issues these permits directly and separately from the Town's building permit process. Sprinkler and fire alarm systems are each billed at a $400 base fee plus $4.00 per device, per the District's own Fee Schedule (Resolution 2024-06).

Sources & verification

Verified against official sources. Last reviewed 2026-08-14.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Silverthorne building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.