Fire Sprinkler / Fire Alarm System Permit in Gilcrest, Colorado

Fire protection in Gilcrest is provided by the Platteville-Gilcrest Fire Protection District (PGFPD), which maintains a station at 14679 CR 42 in Gilcrest and issues permits for installation of any new, or modification to any existing, fire alarm or fire sprinkler system (including kitchen hood systems), per the District's own Plan Review Fee Schedule (effective January 1, 2022). These PGFPD permits are in addition to any permits required by the Town of Gilcrest. Fees are tiered by project site square footage, and all contractors installing or repairing fire protection systems within the District must hold an applicable Colorado Division of Fire Prevention and Control registration.

Verified 2026-08-13 · Source

When you need this permit

  • PGFPD issues permits for installation of any new, or modification to any existing, fire alarm or fire sprinkler system, including kitchen hood systems; these permits are in addition to any Town of Gilcrest municipal permits
  • Permits are issued only upon review of submitted plans; submittals for fire alarm and suppression systems require one complete set of drawings (including cut sheets and calculations) plus one electronic version, stamped by a NICET Level III or higher technician in the appropriate field of engineering
  • A copy of approved plans must be available at the job site during inspection
  • As of January 1, 2022, all contractors installing and/or repairing fire protection systems within PGFPD's jurisdiction must hold an applicable registration with the Colorado Division of Fire Prevention and Control
  • Every permit issued includes one inspection per project phase; additional inspections beyond that are billed at $75.00/hour (or fraction thereof), and re-inspection fees must be paid before the third inspection and any subsequent inspections
  • After-hours inspections (outside 7:00 AM-5:00 PM, Monday-Friday) are billed at $75.00/hour with a two-hour minimum
  • Submittals are delivered or sent to District Headquarters, Platteville Fire Station, 202 Main Street, Platteville, CO 80651 (Dave Sutton, 970-817-1416)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet — 0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire Sprinkler System Plan Review & Permit (tiered by site square footage)Per PGFPD's Plan Review Fee Schedule, effective January 1, 2022; e.g., $500.00 for 10,000-49,999 sq ft, $750.00 for 50,000-99,999 sq ft, $1,250.00 for 100,000-499,999 sq ft, $1,750.00 for 500,000-699,999 sq ft
$250.00 (0-9,999 sq ft) up to $2,000.00 (1,000,000+ sq ft)
Fire Alarm System Plan Review & Permit (tiered by site square footage)Same tier structure as Fire Sprinkler System fees, per the Fee Schedule
$250.00 (0-9,999 sq ft) up to $2,000.00 (1,000,000+ sq ft)
Kitchen Hood SystemPer the Fee Schedule
$300.00 flat, all site sizes
Additional Service or Re-inspectionApplies to re-inspections beyond the one included per project phase, and after-hours inspections (2-hour minimum)
$75.00/hour

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm System Permit permit actually take in Gilcrest?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Protection System Inspection

    One inspection per project phase is included with the permit; additional inspections beyond that are billed at $75.00/hour

See the full Gilcrest inspection guide — scheduling & re-inspection fees →

Tips

  • PGFPD's fire-protection-system permit is separate from, and in addition to, any Town of Gilcrest municipal building permit for the same project — budget for both.
  • Fees scale by site square footage, not by system complexity — a small sprinkler system in a large building is billed at the building's full-site tier, not a reduced tier for the system's own footprint.
  • Only one inspection per project phase is included in the base fee — plan for a $75.00/hour re-inspection charge if additional visits become necessary.

Frequently asked questions

Gilcrest requires a fire sprinkler / fire alarm system permit for: PGFPD issues permits for installation of any new, or modification to any existing, fire alarm or fire sprinkler system, including kitchen hood systems; these permits are in addition to any Town of Gilcrest municipal permits; Permits are issued only upon review of submitted plans; submittals for fire alarm and suppression systems require one complete set of drawings (including cut sheets and calculations) plus one electronic version, stamped by a NICET Level III or higher technician in the appropriate field of engineering; A copy of approved plans must be available at the job site during inspection; As of January 1, 2022, all contractors installing and/or repairing fire protection systems within PGFPD's jurisdiction must hold an applicable registration with the Colorado Division of Fire Prevention and Control; Every permit issued includes one inspection per project phase; additional inspections beyond that are billed at $75.00/hour (or fraction thereof), and re-inspection fees must be paid before the third inspection and any subsequent inspections; After-hours inspections (outside 7:00 AM-5:00 PM, Monday-Friday) are billed at $75.00/hour with a two-hour minimum; Submittals are delivered or sent to District Headquarters, Platteville Fire Station, 202 Main Street, Platteville, CO 80651 (Dave Sutton, 970-817-1416). If your project isn't listed, confirm with Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 970-737-2426 before starting work.

Fees are tiered by project site square footage, from $250.00 (under 10,000 sq ft) up to $2,000.00 (1,000,000+ sq ft), per PGFPD's Plan Review Fee Schedule, effective January 1, 2022.

Gilcrest does not publish a plan-review timeline for this permit. Contact Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 970-737-2426 for current turnaround.

You'll need: Plan Review Worksheet; Fire Alarm/Sprinkler System Drawings (1 physical set + 1 electronic copy). See the required-documents checklist on this page for details on each.

Gilcrest requires 1 inspection(s) for a fire sprinkler / fire alarm system permit, in order: Fire Protection System Inspection. Schedule each through Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) (970-737-2426).

Apply through Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 304 8th Street, Gilcrest, CO 80623. Phone: 970-737-2426, email: hana@townofgilcrest.org. Office hours: Monday-Friday 10:00 AM - 6:00 PM; Saturday 10:00 AM - 2:00 PM (Town Hall, 304 8th Street). Building inspection services are provided under contract by SAFEbuilt, Inc. (3755 Precision Drive, Suite 140, Loveland, CO 80538; main line 866-977-4111); inspection scheduling is handled via the inspection line printed on the issued permit card, not the Town's general office line.. Official information: https://townofgilcrest.org/departments/planning-zoning/.

Gilcrest, Colorado has adopted: 2018 International Residential Code (IRC) — confirmed as the operative residential code from the title block of the Town's own SAFEbuilt-published 'Building Guides for Homeowners' series (Re-Roofing, Additions to Single Family Dwellings, Accessory Structures, Patio Covers/Carports, Decks, Pole Barns, Window Replacement, Swimming Pools — all titled '2018 IRC' and published/revised 5.10.2019), which are the Town's own currently-linked permitting handouts as of the last verification; National Electrical Code: the Town's own 'Residential Electrical Wiring Guidelines' handout (SAFEbuilt Colorado, last revised 1/28/2010) cites 2008 NEC provisions such as tamper-resistant receptacle requirements, and the Manufactured Housing Installation Permits handout states that manufactured-home electric service 'shall be installed in accordance with 2008 National Electric Code (NEC)'. That is the most recent NEC edition cited in any Town-published document, and it is materially older than current practice — no more recent Town-published NEC citation exists after checking the Building Permit Application, the Electrical Permit Resolution (2016-12) and both Contemporaneous Review Guidelines documents, none of which state an edition. Confirm the enforced edition with the Town before designing.; Building Permit Fee valuation table: the Town's 'Building Inspection and Plan Review Fees' handout (undated, current as of the last verification since it is reproduced verbatim as an exhibit to the Amended 2025 Fee Schedule effective 5/1/2025) explicitly states fees are 'Based on Table 1A of the 97 Uniform Building Code' (i.e., the 1997 Uniform Building Code, a legacy pre-IRC/IBC code family) — this is a fee-calculation table only, not a statement that Gilcrest enforces 1997 UBC construction/life-safety provisions; the same handout separately states project valuations are based on 'the most current Building Valuation Data published by the International Code Council,' which is inconsistent with a static 1997-vintage fee table and is flagged here rather than silently reconciled; Colorado is a home-rule state with no statewide-mandated building code edition; Gilcrest is a statutory (non-home-rule) town, so its own municipal code and adopted-code ordinance govern. The Town's Municipal Code (hosted on Municode) is not independently confirmed here as a supplementary source for code-adoption ordinance language — see tipsAndGotchas.; HB22-1362 statewide energy code floor (2021 IECC + electric-readiness/EV-ready/solar-ready requirements, effective window July 2023-July 2026): no Town-published document reviewed states an adopted IECC edition or references HB22-1362 compliance; the 2018 IRC guide series (Home Additions, Accessory Structures) does reference 'Energy Code Compliance Report (www.energycodes.gov) or REScheck calculations' as a required submittal item, which points toward some energy-code enforcement in practice, but no specific IECC edition or HB22-1362 statement was found in any Gilcrest-published source. This should be treated as an open item pending direct confirmation from the Building Department (970-737-2426) rather than assumed either way.; International Building Code, 2018 edition — adopted at Municipal Code Sec. 18-1 (Chapters 1 through 35 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com, codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Residential Code, 2018 edition — adopted at Municipal Code Sec. 18-21 (Chapters 1 through 43 inclusive). See Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com. Codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Mechanical Code, 2018 edition — adopted at Municipal Code Sec. 18-61 (Chapters 1 through 15 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations), library.municode.com. Codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Plumbing Code, 2018 edition — adopted at Municipal Code Sec. 18-71 (Chapters 1 through 13 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com, codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Fuel Gas Code, 2018 edition — adopted at Municipal Code Sec. 18-101 (Chapters 1 through 8 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com, codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Fire Code, 2012 edition — adopted at Municipal Code Sec. 18-201, including Appendices. Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com, codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Existing Building Code, 2018 edition — adopted at Municipal Code Sec. 18-301 (Chapters 1 through 16 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations), on library.municode.com. Codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Property Maintenance Code, 2018 edition — adopted at Municipal Code Sec. 18-401 (Chapters 1 through 8 inclusive). Gilcrest Municipal Code Chapter 18 (Building Regulations) on library.municode.com, codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Energy Conservation Code, 2021 edition — adopted at Municipal Code Sec. 18-501, within Gilcrest Municipal Code Chapter 18 (Building Regulations) as codified on library.municode.com. Codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; International Swimming Pool and Spa Code, 2018 edition — adopted at Municipal Code Sec. 18-551 (Chapters 1 through 11 inclusive), Gilcrest Municipal Code Chapter 18 (Building Regulations). Codified through Ordinance No. 2023-06, adopted 2023-08-07 (Supplement 25).; The IBC, IECC, IMC, IPC, and IFGC are each adopted, by section, in Municipal Code Chapter 18 (library.municode.com). The Fire Code edition is worth noting separately: 2012, while every other adopted code is 2018 or 2021.. Local amendments apply — see the Gilcrest overview page for the full list.

The Platteville-Gilcrest Fire Protection District (PGFPD), which maintains a station in Gilcrest. PGFPD permits are separate from, and in addition to, any Town of Gilcrest municipal building permit for the same project.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gilcrest building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Gilcrest's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Gilcrest yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Gilcrest lands. Privacy.