Re-Roof Permit in Gilcrest, Colorado

Required for re-roofing work in Gilcrest. Billed as a flat 'Single Stop' fee. Reviewed under 2018 IRC Sections R806 (roof ventilation) and R908 (reroofing) per the Town's own SAFEbuilt-published 'Residential Re-roofing' guide (rev. 5.10.2019).

Verified 2026-07-06 · Source

When you need this permit

  • Owner may perform the re-roof personally as owner-builder Owner-builder
  • No more than two (2) layers of roofing are allowed upon completion of installation; roof replacement (tear-off to deck) is required where the existing roof is water-soaked/deteriorated, is wood shake/slate/clay/cement/asbestos-cement tile, or already has two or more layers, per IRC R908.3
  • For complete tear-offs: roof sheathing must provide a rigid surface; repair/replace warped, cracked, or delaminated boards; apply new minimum 15# asphalt-saturated felt underlayment on a dry deck (one layer for 4:12+ slopes; 19-inch laps for 2:12-4:12 slopes)
  • Fasteners must penetrate a minimum of 3/4 inch into decking material; nail guns permitted if properly adjusted
  • Existing roof jacks/vents must be replaced if in poor condition, badly rusted, or deteriorated
  • Asphalt shingles must be tested per ASTM D 7158 and meet IRC Table R905.2.4.1(1) classification requirements; check with the jurisdiction for Ice & Water Shield requirements specific to the project
  • A mid-roof inspection may be required in addition to the final inspection depending on scope — confirm with the Building Department when the permit is issued

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Roof (re-shingle) — Single Stop Projects Fee ScheduleTown of Gilcrest Building Inspection and Plan Review Fees handout, current per the Amended 2025 Fee Schedule effective 5/1/2025
$60.00 flat

Review timeline

Plan review
Not published — contact the department

How long did your Re-Roof Permit permit actually take in Gilcrest?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Mid-Roof Inspection (if required)

    Required for some scopes at Building Department discretion; consult the department when the permit is issued

  2. 2

    Final Roof Inspection

    Required for all re-roof permits; the permit holder must call for this inspection

See the full Gilcrest inspection guide — scheduling & re-inspection fees →

Tips

  • A re-roof in Gilcrest is billed as a flat $60.00 fee, not a valuation-based fee — one of the simplest and least expensive permit types the Town offers.
  • No more than two layers of roofing are allowed upon completion — if your roof already has two layers or is deteriorated/wood shake/tile, a full tear-off to the deck is required per IRC R908.3.
  • If your neighborhood has an HOA, the Town's own guide advises contacting them before changing roof covering materials, separate from the municipal permit process.

Frequently asked questions

Gilcrest requires a re-roof permit for: Owner may perform the re-roof personally as owner-builder; No more than two (2) layers of roofing are allowed upon completion of installation; roof replacement (tear-off to deck) is required where the existing roof is water-soaked/deteriorated, is wood shake/slate/clay/cement/asbestos-cement tile, or already has two or more layers, per IRC R908.3; For complete tear-offs: roof sheathing must provide a rigid surface; repair/replace warped, cracked, or delaminated boards; apply new minimum 15# asphalt-saturated felt underlayment on a dry deck (one layer for 4:12+ slopes; 19-inch laps for 2:12-4:12 slopes); Fasteners must penetrate a minimum of 3/4 inch into decking material; nail guns permitted if properly adjusted; Existing roof jacks/vents must be replaced if in poor condition, badly rusted, or deteriorated; Asphalt shingles must be tested per ASTM D 7158 and meet IRC Table R905.2.4.1(1) classification requirements; check with the jurisdiction for Ice & Water Shield requirements specific to the project; A mid-roof inspection may be required in addition to the final inspection depending on scope — confirm with the Building Department when the permit is issued. If your project isn't listed, confirm with Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 970-737-2426 before starting work.

In Gilcrest, the published Roof (re-shingle) — Single Stop Projects Fee Schedule is: $60.00 flat. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Gilcrest does not publish a plan-review timeline for this permit. Contact Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 970-737-2426 for current turnaround.

You'll need: Town of Gilcrest Building Permit Application. See the required-documents checklist on this page for details on each.

Gilcrest requires 2 inspection(s) for a re-roof permit, in order: Mid-Roof Inspection (if required), Final Roof Inspection. Schedule each through Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) (970-737-2426).

Apply through Town of Gilcrest Planning & Zoning / Building Department (building inspection services contracted to SAFEbuilt, Inc.) at 304 8th Street, Gilcrest, CO 80623. Phone: 970-737-2426, email: hana@townofgilcrest.org. Office hours: Monday-Friday 10:00 AM - 6:00 PM; Saturday 10:00 AM - 2:00 PM (Town Hall, 304 8th Street). Building inspection services are provided under contract by SAFEbuilt, Inc. (3755 Precision Drive, Suite 140, Loveland, CO 80538; main line 866-977-4111); inspection scheduling is handled via the inspection line printed on the issued permit card, not the Town's general office line.. Official information: https://townofgilcrest.org/departments/planning-zoning/.

Yes. The Town's own Residential Re-roofing guide explicitly confirms the owner may perform the re-roof personally as owner-builder.

No more than two (2) layers are allowed upon completion of installation, per the Town's Residential Re-roofing guide (2018 IRC Section R908.3).

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gilcrest building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.