Required for installation of new or modified automatic fire sprinkler systems, fire alarm systems, and commercial hood fire suppression systems in Santa Fe. Plans are reviewed and stamped by the City of Santa Fe Fire Department Fire Marshal's Office (SFFD FMO) under the 2021 International Fire Code (as amended statewide, per this file's codesAdopted list), either alongside the primary building permit or as a deferred submittal.

Verified 2026-07-22 · Source

When you need this permit

  • Fire protection system plans (sprinkler, alarm, and/or hood suppression) submitted to the SFFD Fire Marshal's Office for review and stamping, either with the primary building permit or as a deferred submittal using the Fire Marshal's Deferred Submittal requirements if plans are not ready at initial building permit submittal
  • Correct plan review fee from the SFFD Fire Prevention and Protection Fees Invoice (fee code #11001.430210) must accompany the submittal, forwarded to cashier@santafenm.gov
  • The installed system must be tested by the installing contractor BEFORE calling for a rough-in or final acceptance inspection; the installing contractor must be on site for the SFFD FMO acceptance/commissioning inspection
  • SFFD FMO-stamped and approved plans, plus required signage (FDC, Fire Riser Room, Fire Alarm Control Panel — labeled all-weather and reflective) must be present on site at acceptance
  • Fire sprinkler systems: above-ground test certificate, FDC caps labeled for the specific building (Santa Fe thread), PIV (Post Indicator Valve) handles locked off, and hydraulic calculation tags on risers required at acceptance
  • Fire alarm systems: alarm certificate of completion, verified reporting to Santa Fe Regional Dispatch, lock-out/tag-out on the fire alarm circuit, a document cabinet, and labeled initiating devices (batteries, smoke detectors, pull stations) required at acceptance
  • Hood fire suppression systems: system tied to the building fire alarm (if one is provided), appliances in place as designed, all power/gas shut off except exhaust on activation, and a Class K extinguisher located within 30 feet of cooking surfaces
  • Ongoing compliance for Certificate of Compliance/business-licensing purposes: sprinkler risers require a tag documenting quarterly inspections; alarm systems require documentation of annual inspection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Residential Automatic Fire Sprinkler System PlansSFFD Fire Prevention and Protection Fees Invoice, fee code #11001.430210
$50.00
Commercial Automatic Fire Sprinkler System PlansSFFD Fire Prevention and Protection Fees Invoice, fee code #11001.430210
$150.00
Commercial Automatic Fire Sprinkler System Modification PlansSFFD Fire Prevention and Protection Fees Invoice, fee code #11001.430210
$50.00
Commercial Fire Alarm System PlansSFFD Fire Prevention and Protection Fees Invoice, fee code #11001.430210
$50.00
Commercial Hood Fire Suppression System PlansSFFD Fire Prevention and Protection Fees Invoice, fee code #11001.430210
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler & Fire Alarm System Permit permit actually take in Santa Fe?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Contractor Self-Test (Pre-Rough-In)

    The installing contractor must test the system before calling SFFD for a rough-in inspection, per the Acceptance/Commissioning of Life Safety Equipment Requirements

  2. 2

    SFFD Acceptance/Commissioning Final Inspection

    SFFD FMO verifies stamped plans, required signage, and system-specific completion documentation (test certificate/PIV/hydraulic tags for sprinklers; certificate of completion and Regional Dispatch reporting for alarms; Class K extinguisher placement for hood systems) with the installing contractor on site

See the full Santa Fe inspection guide — scheduling & re-inspection fees →

Tips

  • Fees are itemized per system type on the SFFD Fire Prevention and Protection Fees Invoice — commercial sprinkler plan review ($150) costs three times residential ($50); a project with both a sprinkler system and a fire alarm needs to budget for both line items separately.
  • Test the system yourself before calling for a rough-in or final acceptance inspection — SFFD's Acceptance/Commissioning requirements are explicit that this must happen first, with the installing contractor present on site.
  • If fire protection system plans aren't ready when the main building permit is filed, they can be submitted later as a deferred submittal — check the Fire Marshal's Forms & Applications page for the Deferred Submittal requirements document.

Frequently asked questions

Santa Fe requires a fire sprinkler & fire alarm system permit for: Fire protection system plans (sprinkler, alarm, and/or hood suppression) submitted to the SFFD Fire Marshal's Office for review and stamping, either with the primary building permit or as a deferred submittal using the Fire Marshal's Deferred Submittal requirements if plans are not ready at initial building permit submittal; Correct plan review fee from the SFFD Fire Prevention and Protection Fees Invoice (fee code #11001.430210) must accompany the submittal, forwarded to cashier@santafenm.gov; The installed system must be tested by the installing contractor BEFORE calling for a rough-in or final acceptance inspection; the installing contractor must be on site for the SFFD FMO acceptance/commissioning inspection; SFFD FMO-stamped and approved plans, plus required signage (FDC, Fire Riser Room, Fire Alarm Control Panel — labeled all-weather and reflective) must be present on site at acceptance; Fire sprinkler systems: above-ground test certificate, FDC caps labeled for the specific building (Santa Fe thread), PIV (Post Indicator Valve) handles locked off, and hydraulic calculation tags on risers required at acceptance; Fire alarm systems: alarm certificate of completion, verified reporting to Santa Fe Regional Dispatch, lock-out/tag-out on the fire alarm circuit, a document cabinet, and labeled initiating devices (batteries, smoke detectors, pull stations) required at acceptance; Hood fire suppression systems: system tied to the building fire alarm (if one is provided), appliances in place as designed, all power/gas shut off except exhaust on activation, and a Class K extinguisher located within 30 feet of cooking surfaces; Ongoing compliance for Certificate of Compliance/business-licensing purposes: sprinkler risers require a tag documenting quarterly inspections; alarm systems require documentation of annual inspection. If your project isn't listed, confirm with City of Santa Fe Planning, Land Use and Housing Department — Building Division (Permitting) at (505) 955-6571 (Planning, Land Use and Housing Department main line); Building Permit Division direct: (505) 955-6588 before starting work.

Per SFFD's Fire Prevention and Protection Fees Invoice (fee code #11001.430210): $50.00 for residential automatic fire sprinkler system plans, $150.00 for commercial automatic fire sprinkler system plans, and $50.00 for a commercial sprinkler system modification.

Santa Fe does not publish a plan-review timeline for this permit. Contact City of Santa Fe Planning, Land Use and Housing Department — Building Division (Permitting) at (505) 955-6571 (Planning, Land Use and Housing Department main line); Building Permit Division direct: (505) 955-6588 for current turnaround.

You'll need: SFFD Fire Prevention and Protection Fees Invoice; FP-1 Site Plan Checklist (Building Permits); FP-2 Floor Plan Checklist (Building Permits); Acceptance/Commissioning of Life Safety Equipment Requirements. Depending on your project, Santa Fe may also ask for: Deferred Submittal Requirements. See the required-documents checklist on this page for details on each.

Santa Fe requires 2 inspection(s) for a fire sprinkler & fire alarm system permit, in order: Contractor Self-Test (Pre-Rough-In), SFFD Acceptance/Commissioning Final Inspection. Schedule each through City of Santa Fe Planning, Land Use and Housing Department — Building Division (Permitting) ((505) 955-6571 (Planning, Land Use and Housing Department main line); Building Permit Division direct: (505) 955-6588).

Apply through City of Santa Fe Planning, Land Use and Housing Department — Building Division (Permitting) at Santa Fe City Hall, 200 Lincoln Ave., 1st Floor (southwest entrance facing Marcy Street nearest the Convention Center), Santa Fe, NM 87501; Mailing: City of Santa Fe Building Permit Division, P.O. Box 909, Santa Fe, NM 87504-0909. Phone: (505) 955-6571 (Planning, Land Use and Housing Department main line); Building Permit Division direct: (505) 955-6588, email: permitcounter@santafenm.gov. Office hours: By appointment only, 8:00 a.m.–Noon and 1:00–4:00 p.m., Monday–Friday. Drop-off hours for revision/amendment submittals only: Monday–Thursday 8:00 a.m.–3:00 p.m., Friday 8:00 a.m.–11:00 a.m.. Official information: https://www.santafenm.gov/land-use/building-permits.

Santa Fe, New Mexico has adopted: 2021 New Mexico Commercial Building Code (2021 IBC as amended by the State of New Mexico); 2021 New Mexico Residential Building Code (2021 IRC as amended by the State of New Mexico), plus the City of Santa Fe Residential Green Building Code; 2021 New Mexico Existing Building Code (2021 International Existing Building Code as amended by the State of New Mexico); 2021 New Mexico Plumbing Code (2021 Uniform Plumbing Code as amended by the State of New Mexico), plus City of Santa Fe UPC amendments; 2021 New Mexico Mechanical Code (2021 Uniform Mechanical Code as amended by the State of New Mexico); 2020 New Mexico Electrical Code (2020 National Electrical Code as amended by the State of New Mexico); 2012 New Mexico Electrical Safety Code (2012 National Electrical Safety Code as amended by the State of New Mexico); 2021 New Mexico Earthen Building Materials Code; 2021 New Mexico Historic Earthen Buildings Code; 2021 New Mexico Energy Conservation Code (2021 International Energy Conservation Code as amended by the State of New Mexico); 2012 New Mexico Swimming Pool, Spa, and Hot Tub Code (2012 Uniform Swimming Pool, Spa and Hot Tub Code as amended by the State of New Mexico); 2012 New Mexico Solar Energy Code (2012 Uniform Solar Energy Code as amended by the State of New Mexico); 2021 International Fire Code, plus City of Santa Fe IFC amendments; New Mexico Administrative Code (NMAC) Title 14, Chapter 5: 14.5.1 General Provisions, 14.5.2 Permits, 14.5.3 Inspections; 2017 ICC A117.1-2017 Accessible and Usable Buildings and Facilities. Local amendments apply — see the Santa Fe overview page for the full list.

No — both are reviewed by the same City of Santa Fe Fire Department Fire Marshal's Office under one Fire Prevention and Protection Fees Invoice, which lists a $50.00 plan review fee for a commercial fire alarm system alongside the sprinkler and hood suppression fee lines.

Sources & verification

Verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Fe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.