EV Charger / EVSE Permit (Electrical Permit) — Santa Fe, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.santafenm.gov/land-use/building-permits/construction-permit-submittal-checklists
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Electrical Permit) in Santa Fe, New Mexico
The City of Santa Fe has no dedicated EV charger/EVSE permit checklist or fee line — confirmed by reviewing the City's full Construction Permit Submittal Checklists page, which lists dedicated Solar (roof-mounted and ground-/awning-mounted) checklists but nothing for EV chargers. An EV charging station (Level 2 or DC fast charger) installation is processed and billed as a standard Electrical Permit, governed by the 2020 New Mexico Electrical Code (as amended statewide) and, where applicable, the 2012 New Mexico Electrical Safety Code, under the same fixed-fee-by-work-type schedule documented in this file's electrical-permit entry.
Verified 2026-07-20 · Source
When you need this permit
- Work must comply with the 2020 New Mexico Electrical Code (2020 NEC as amended by the State of New Mexico) and, where applicable, the 2012 New Mexico Electrical Safety Code
- Apply using the City's unified Building Permit Application (submitted via the CSS portal) for the electrical scope of work — no separate EV-charger-specific application or checklist exists
- If the EV charger installation requires a new or upgraded electrical panel/service, that scope is billed under the same Electrical Permit's amperage-tiered meter-loop/panel fee lines documented in this file's electrical-permit entry
- Fees for standalone electrical work in Santa Fe are fixed amounts based on the specific type of work (not valuation-based) — confirm with the Building Division (505-955-6600) which specific fee line applies to a dedicated EV-charger branch circuit if no panel work is involved, since the published fee schedule's electrical section does not print a distinct 'new circuit'/'branch circuit' catch-all line beyond the categories already itemized (meter loop, panel upgrade tiers, temporary power pole, service change, low voltage)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Circuit wiring, breaker, and conduit before any wall/finish closure, per NMAC 14.5.3.9.C(3), if applicable
- 2
Final
Charger mounted, connections verified, panel labeled; per NMAC 14.5.3.9.C(5)
See the full Santa Fe inspection guide — scheduling & re-inspection fees →
Tips
- Santa Fe has no dedicated EV-charger checklist like it does for solar (roof-mounted and ground-/awning-mounted PV) — an EV charger installation goes through the standard Electrical Permit process.
- Electrical permit fees in Santa Fe are fixed per work type rather than valuation-based; a $40 base Issuance of Electrical Permit fee applies, plus an amperage-tiered panel fee ($45-$360) only if a panel upgrade is part of the scope.
- Confirm the exact applicable fee line with the Building Division (505-955-6600) before applying — the published fee schedule does not print an explicit 'new EV charger circuit' or generic 'new branch circuit' line separate from its meter-loop/panel/service-change categories.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santa Fe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Santa Fe
EV Charger / EVSE Permit (Electrical Permit) in other cities
Compare ev charger / evse permit (electrical permit) fees across New Mexico →
Look up this fee in a different city →
Related guides
Now live
Build your Santa Fe project checklist
Describe your project once and get every permit, document, and fee it triggers in Santa Fe — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.