Logan building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Logan, Utah.
Verified 2026-06-30 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 290 N 100 W, Logan, UT 84321
- Phone
- (435) 716-9030
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- Call (435) 716-9030 with 24-hour notice to schedule inspections. (Roofing Permit)
- Sprinkler hydrostatic, flush, and thrust block tests must be witnessed by an LCFD fire official before the final inspection can be scheduled — coordinate timing directly with the Fire Prevention Bureau. (Fire Sprinkler System Permit)
- Hydrostatic, flush, and thrust block testing must be witnessed by an LCFD fire official before the final inspection can be scheduled (Fire Sprinkler System Permit)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footings
Before concrete pour — forms, rebar, and anchor bolts
- 2
Foundation
Foundation walls and waterproofing before backfill
- 3
Below-Grade Plumbing / Mechanical
Underground pipes and connections before concrete pour
- 4
Shear Wall
Shear panels and hold-downs before sheathing covered
- 5
Rough 4-Way
Interior framing, weather barrier, power-to-panel connection, mechanical rough, plumbing rough, electrical rough, and gas line pressure test — all at once before walls closed
- 6
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Commercial Building Permit
- 1
Footings / Foundation
Before concrete pour — forms, rebar, and anchor bolts per adopted IBC
- 2
Underground / Rough-In (Plumbing, Electrical, Mechanical)
Before backfill and before closing walls or ceilings — all underground and rough-in utilities
- 3
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 4
Fire Sprinkler / Fire Alarm
Required where the adopted IBC/IFC mandates fire suppression or alarm systems
- 5
Final
All work complete — Certificate of Occupancy issued upon passing final inspection
Applies to: Change of Use (Business License Amendment / Commercial Certificate of Occupancy)
- 1
Planning/Zoning Conformance (Design Review Record of Decision, landscaping)
Sign-off by a City Planner (435-716-9021), required on the Gold Card before the Building Inspector's final.
- 2
Fire Marshal — Fire Suppression/Alarm and Final Inspection
Sign-off by the Fire Marshal (Craig Humphreys, 435-716-9515), required on the Gold Card.
- 3
Public Works (water/sewer, curb/gutter, sidewalk, storm water, parking, access)
Sign-off required on the Gold Card (435-716-9153).
- 4
Building Inspector Final
Must have all other applicable department sign-offs completed (temporary or permanent) before this final can be scheduled, per the Gold Card form.
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Footings
Before concrete pour — forms, rebar, anchor bolts
- 2
Rough 4-Way
Framing, mechanical, plumbing, and electrical rough-ins before walls closed
- 3
Final
All work complete, ready for occupancy
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings verified
- 2
Rough 4-Way
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In (MEP)
After framing and rough-in mechanical, electrical, and plumbing work — before insulation or wall cover
- 2
Fire Sprinkler / Fire Alarm (if applicable)
Required where the tenant improvement scope modifies existing fire suppression or alarm systems
- 3
Final
All work complete — space approved for occupancy under the tenant's use classification
Applies to: Deck Permit
- 1
Footings
Verify footing depth (below frost line — 30 inches residential), diameter, and rebar before concrete pour
- 2
Rough 4-Way (Framing)
Posts, beams, joists, ledger connection, and hardware before decking
- 3
Final
Decking, stairs, guards, and railings complete — 36-inch guard height required at 30+ inches above grade
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Fire Sprinkler System Permit
- 1
Hydrostatic, Flush, and Thrust Block Testing
Must be witnessed by an LCFD fire official prior to scheduling the final inspection.
- 2
Fire Sprinkler Rough-Install Inspection
Performed after rough-in of the sprinkler system, before it is concealed.
- 3
Final Inspection (24-hour test, 2 visits)
Combined final fire-system inspection; shared with the fire alarm final inspection if both systems are present on the project.
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support.
- 2
Final
All devices installed, GFCI/AFCI protection verified, panel labeled.
Applies to: Fire Alarm System Permit
- 1
Fire Alarm Rough-Install Inspection
Performed after rough-in wiring and device placement, before walls are closed.
- 2
Final Inspection (24-hour test, 2 visits)
Combined final fire-system inspection; shared with the fire sprinkler final inspection if both systems are present on the project.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Siding & Window Replacement Permit
- 1
Weather Barrier / Framing
House wrap and any modified framing verified before siding installed
- 2
Final
Siding and windows complete, flashing and weatherproofing verified
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Sign Permit, Water Heater Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Logan building permits
Get alerts for Logan
We'll email you when Logan's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.