Commercial Building Permit — Logan, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.loganutah.org/government/departments/community_development/building_department/fees.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Logan, Utah
Required for new commercial, industrial, and multi-family building construction in Logan. Per Resolution No. 20-09, 'Commercial and Residential Building Permit fees are based on the valuation of the permit' using the same valuation table as residential — but commercial plan review, at 65% of the Building Permit Fee, is charged instead of the 0.1% residential rate, and separate utility impact/connection fees apply. The same valuation table governs at every scale, up to and including an issued City permit for a $16,500,000 new commercial project; source is Logan's own 'Building Permit Fee Valuation Table'.
Verified 2026-07-19 · Source
When you need this permit
- New commercial, industrial, or multi-family building construction on a permitted, properly zoned lot
- Digital plans only — Logan City Building Department 'will only accept DIGITAL plans (except under special circumstances)'; submit application and plans to loganplanreview@loganutah.gov
- Complete architectural and structural drawings for plan review
- Fire Department plan review where the adopted IBC/IFC requires fire suppression or alarm systems
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Logan City Building Permit Fees — Resolution No. Show full citationHide
Logan City Building Permit Fees — Resolution No. 20-09, 'TO DETERMINE FEES': 'Commercial and Residential Building Permit fees are based on the valuation of the permit.' Verified against a real issued permit for a New Commercial project (PV $16,500,000): Building Permit charge was $76,355.00, which exactly matches $6,605 + ($15,500,000/$1,000 × $4.50).Resolution No. 20-09, 'Plan Review Fees': 'All other Commercial, Industrial, Multi-family plan review fees shall be calculated at 65% of Building Permit Fee.' Logan's own 'Building Permit Fee… Show full citationHide
Resolution No. 20-09, 'Plan Review Fees': 'All other Commercial, Industrial, Multi-family plan review fees shall be calculated at 65% of Building Permit Fee.' Logan's own 'Building Permit Fee Valuation Table' (Permit Fees Table.pdf) lists a precomputed 'Commercial Plan Check Fee' column equal to 65% of the Building Permit Fee at every valuation (e.g., $80,000 valuation row: Building Permit $970.00, Commercial Plan Check Fee $630.50). The real $16,500,000 New Commercial permit example billed 'Plan Check Commercial (Additional)' of $49,630.75 — exactly 65% of its $76,355.00 Building Permit charge.Resolution No. 20-09: 'Electrical/Mechanical/Plumbing Permit Fee shall be calculated at 8% of Building Permit Fee.' Verified on the real $16,500,000 New Commercial permit: Electrical Permit,… Show full citationHide
Resolution No. 20-09: 'Electrical/Mechanical/Plumbing Permit Fee shall be calculated at 8% of Building Permit Fee.' Verified on the real $16,500,000 New Commercial permit: Electrical Permit, Mechanical Permit, and Plumbing Permit each charged $6,108.40 — exactly 8% of the $76,355.00 Building Permit fee.Resolution No. 20-09: 'The state adds an extra 1% surcharge fee.' Reverse-engineered from the real $16,500,000 New Commercial permit: 'State Surcharge - City' $142.02 + 'State Surcharge - State'… Show full citationHide
Resolution No. 20-09: 'The state adds an extra 1% surcharge fee.' Reverse-engineered from the real $16,500,000 New Commercial permit: 'State Surcharge - City' $142.02 + 'State Surcharge - State' $804.78 = $946.80 total, which is exactly 1% of Building Permit ($76,355.00) + Electrical + Mechanical + Plumbing ($6,108.40 × 3) = $94,680.20.City of Logan, Utah Impact Fee Schedule, Ordinance No. Show full citationHide
City of Logan, Utah Impact Fee Schedule, Ordinance No. 25-01, effective February 18, 2025 — lists per-meter fees, e.g. Culinary Water 4" Compound Meter $34,398 per ERC, Wastewater Treatment 4" Compound Meter $24,327 minimum. Confirmed as real and substantial on the $16,500,000 New Commercial permit example: that single permit billed $9,172 + $34,398 (Culinary Water), $44,517 (Light & Power), $34,081.54 (Transportation), $2,030 (Wastewater Collection), $41,410.65 (Wastewater Treatment), plus separate water/sewer hookup and tap fees — these are additional to and separate from the Building Permit/Plan Check/MEP fees above and are NOT charged on tenant-improvement-only permits (see Commercial Tenant Improvement entry).Observed as a real line item ('Fire Inspection Fee $675.00') on the issued $16,500,000 New Commercial permit; Show full citationHide
Observed as a real line item ('Fire Inspection Fee $675.00') on the issued $16,500,000 New Commercial permit; Logan's Resolution No. 20-09 and Permit Fees Table.pdf do not separately publish a Fire Inspection Fee schedule, so this figure is reported as observed on one real permit, not as a guaranteed flat rate for all projects.Review timeline
Inspection process
- 1
Footings / Foundation
Before concrete pour — forms, rebar, and anchor bolts per adopted IBC
- 2
Underground / Rough-In (Plumbing, Electrical, Mechanical)
Before backfill and before closing walls or ceilings — all underground and rough-in utilities
- 3
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 4
Fire Sprinkler / Fire Alarm
Required where the adopted IBC/IFC mandates fire suppression or alarm systems
- 5
Final
All work complete — Certificate of Occupancy issued upon passing final inspection
See the full Logan inspection guide — scheduling & re-inspection fees →
Tips
- Logan's Building Department accepts DIGITAL plans only (except under special circumstances) — submit applications and plans to loganplanreview@loganutah.gov to begin plan review.
- Commercial Building Permit fees use the identical valuation table as residential (Resolution No. 20-09) — the difference is plan review (65% commercial vs. 0.1% residential) and the added utility impact/connection fees.
- Utility impact and connection fees (water, sewer, wastewater treatment, Light & Power, transportation) are billed separately from the Building Permit and can be the largest cost on a new commercial project — on the real $16,500,000 example permit reviewed, impact/hookup fees alone totaled over $167,000, versus $76,355 for the Building Permit itself.
- Logan City has its own municipal electric utility (Logan City Light & Power) — new commercial construction pays an Impact Light & Power fee based on service size/phase, separate from Rocky Mountain Power territory rules.
- Call (435) 716-9030 or email loganplanreview@loganutah.gov to confirm current impact fee rates before budgeting, since the Impact Fee Schedule (Ordinance No. 25-01) is revised independently of the Building Permit Fee Resolution.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Logan.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Logan's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Logan yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Logan lands. Privacy.
Other permits in Logan
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Logan project checklist
Describe your project once and get every permit, document, and fee it triggers in Logan — in one checklist. Free, for any city and any number of projects.
Get started →