Residential Building Permit in Logan, Utah
Required for new residential construction, additions, and structural alterations in Logan.
Verified 2026-06-27 · Source
When you need this permit
- Project valuation over $500
- New construction or structural modification
- Changes to electrical, plumbing, or mechanical systems
Required documents
- Req
Building Plans
Complete construction drawings to scale (floor plans, elevations, sections, structural details). Most Utah jurisdictions now require a single PDF set uploaded through their online permit portal.
- Req
Site Plan
Property survey showing setbacks and footprint
- Req
Energy Compliance
REScheck or equivalent energy calculation
- Req
Engineered Truss Plans
Sealed truss layouts for new construction
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit (valuation-based) | Per Logan fee table by valuation: $50 min (up to $500); $230 ($10k); $455 ($25k); $730 ($50k); $1,050 ($90k); $1,780 ($200k); $2,755 ($350k); $3,730 ($500k) | — |
| Plan Check (One/Two-Family Dwellings) | 0.1% of construction valuation (valuation x .001), $15 minimum | — |
| Re-Inspection / After-Hours | $50 per hour (2-hour minimum after hours) | — |
| State Surcharge | 1% of building permit fee | — |
Review timeline
~10–21 business days
Typical estimate — confirm current times with the Logan building department
Inspection process
- 1
Foundation
Before concrete pour — forms, rebar, anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete, ready for occupancy
Tips
- Contact the Logan Permit Center at (435) 716-9000 to discuss your project with a permit tech before applying.
- Logan enforces snow load requirements — ensure your structural plans account for Cache Valley winter conditions.
- Schedule inspections at least 24 hours in advance.
Frequently asked questions
- How much does a residential building permit cost in Logan?
- Logan City building permit fees are valuation-based per the city fee table: $50 minimum (up to $500 valuation), $230 at $10k, $730 at $50k, $1,050 at $90k, $1,780 at $200k, $3,730 at $500k. Residential plan check is 0.1% of valuation ($15 min). Electrical, mechanical, and plumbing permits are each 8% of the building permit fee. State surcharge of 1% applies. (Resolution 20-09)
- How long does permit review take in Logan?
- Logan does not publish a fixed plan-review turnaround. Across Utah jurisdictions, residential plan review typically runs about 2-4 weeks, but times vary with project scope and department workload — confirm current timelines with the Logan building department before you submit.
Sources & verification
Key facts verified against official sources. Last reviewed 2026-06-27.
- Logan City Building Department — official building department
- Logan Building Permit Fee Resolution 20-09
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Logan
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.