Zoning Clearance in Unincorporated Cache County, Utah

Cache County Development Services (Planning & Zoning) requires a Zoning Clearance before most building permit applications can be submitted. County Code Title 17 (adopted by Ordinance No. 2013-02) defines a Zoning Clearance as 'an acknowledgment, provided by the zoning administrator, or designee, identifying that the proposed use, building, structure, or facility complies to the requirements of this Title.' This is a Planning & Zoning-level land-use compliance review, separate from and required before the Building Division's building permit review — the county's own Zoning Clearance Application form states directly: 'Do not submit for a building permit until a zoning clearance has been approved and received.' The form is oriented primarily toward proposed new/modified structures (site plan, floor plan, elevations, dimensions), but its own acknowledgment text also ties any change in use to this same process: 'Any changes in type of structure or placement will require a new zoning clearance.' On the fee, two sets of figures have circulated: $75/$30 on the county's current documents, and a $250/$125/$100/$50 tier reported in an October 2024 news account of a proposed increase. The county's own documents agree on the lower figures: the Zoning Clearance Application form reads 'Fee: Primary - $75' / 'Accessory/Agricultural - $30,' and Cache County's official Land Use Fee Schedule PDF (cachecounty.gov/assets/department/devserv/feeschedule/Fee Schedule.pdf, letterhead-stamped 'Resolution 2018-16') independently confirms the identical figures: 'Zoning Clearance - Primary Use: $75' / 'Zoning Clearance - Accessory Use: $30.' The Cache Valley Daily article (Oct 23, 2024) quotes the fee proposal verbatim: 'zoning clearance applications for primary use, accessory use, agriculture use and third review, which are $75, $30, $30 and $0 respectively. The proposed increase would raise the prices for those services to $250, $125, $100 and $50' — so $75/$30 is the pre-increase baseline the article itself cites, with $250/$125/$100/$50 the proposed new tier presented by Development Services Director Stephen Nelson (one of three proposals he presented, with the smallest-increase option recommended for adoption) at the Oct. 22, 2024 Council meeting. Cache County's Building Division Fee Schedule PDF (cachecounty.gov/assets/department/devserv/Building fees adopted 2024.pdf) is explicitly stamped 'Adopted on 11/6/2024 as Ord. 2024-18' and its building-fee dollar figures exactly match the article's reported building-fee numbers (e.g. $3,480 for a $350,000 home) — confirming Ord. 2024-18 was adopted and did raise Building Division fees as reported. However, no analogous 'Land Use fees adopted 2024' document appears anywhere on cachecounty.gov, and the Land Use/Zoning Fee Schedule PDF that does exist is still stamped with the older 'Resolution 2018-16' and shows the pre-increase $75/$30 figures — meaning Ord. 2024-18's land-use/zoning-clearance fee increase, though reported as approved in the same Oct. 22, 2024 meeting, was either not carried into the final adopted ordinance text, adopted but never implemented in the county's published Land Use fee documentation, or reversed; the Building Division side of the same fee package was clearly implemented and documented, while the Land Use/Zoning side was not. With two currently-live official Cache County documents (the application form and the Land Use Fee Schedule) agreeing on $75/$30 as of mid-2026 — nearly two years after the reported Council vote — $75/$30 is the currently-effective, governing figure. The fee provisions in the county code's own 'FEE SCHEDULE' section (hosted on a municipalcodeonline.com portal) have not been separately confirmed at the ordinance-text level, so applicants budgeting a Primary-use Zoning Clearance above $75 should call Development Services, (435) 755-1640, to rule out an internal fee-schedule update that has not reached either public document.

Verified 2026-08-15 · Source

When you need this permit

  • Required before submitting a building permit application for most projects on a parcel in unincorporated Cache County
  • A complete application must include a site plan, floor plan(s) of all levels, and elevation(s), per the county's Zoning Clearance Application checklist
  • Culinary Water Verification (Utah Division of Water Rights) and Sanitation/Health Department approval (Bear River Health Department) required for any proposed use/building needing water and sewage facilities, per County Code § 17.10.050.A.3.a (Supplemental Standards)
  • An Agricultural Building Statement is required if the structure/use is claimed as Agricultural (must meet Utah Code § 15A-1-202)
  • Any change in type of structure, use, or placement on an already-cleared parcel requires a new Zoning Clearance application, per the application form's own acknowledgment text
  • Approval of a Zoning Clearance is not a waiver of compliance with the zoning ordinance and is not a conditional use permit, per the application form

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Zoning Clearance — Primary use
The Cache County Zoning Clearance Application (form 'ZC_App_CURRENT', cachecounty.gov/assets/department/devserv/building/) reads: 'Fee: Primary - $75.' Cache County's official Land Use Fee Schedule… Show full citationThe Cache County Zoning Clearance Application (form 'ZC_App_CURRENT', cachecounty.gov/assets/department/devserv/building/) reads: 'Fee: Primary - $75.' Cache County's official Land Use Fee Schedule PDF (cachecounty.gov/assets/department/devserv/feeschedule/Fee Schedule.pdf) agrees: 'Zoning Clearance - Primary Use: $75.' A Cache Valley Daily news article (Oct. 23, 2024) reports the County Council approved a new fee schedule on Oct. 22, 2024 that would raise this figure to $250, one of three tiered proposals from Development Services Director Stephen Nelson, with the smallest-increase option recommended for adoption; a companion Ord. 2024-18 did raise Cache County Building Division fees on 11/6/2024, per that division's own 'Building fees adopted 2024.pdf,' whose figures match the article's reported building-fee numbers exactly. No equivalent updated Land Use fee document exists — the Land Use Fee Schedule PDF that does exist is still stamped 'Resolution 2018-16' and still prints $75. Because two independently hosted, currently live official county documents agree on $75 nearly two years after the reported vote, $75 is treated as the currently effective figure; the land-use side of the fee package appears not to have been carried into the county's published documentation even though the building-fee side clearly was. Confirm with Development Services, (435) 755-1640, if you are budgeting for a project where the difference matters.
$75.00
Zoning Clearance — Accessory/Agricultural use
Same application form: 'Accessory/Agricultural - $30.' The Land Use Fee Schedule PDF matches: 'Zoning Clearance - Accessory Use: $30.' An October 2024 news article reports a proposed increase to $125… Show full citationSame application form: 'Accessory/Agricultural - $30.' The Land Use Fee Schedule PDF matches: 'Zoning Clearance - Accessory Use: $30.' An October 2024 news article reports a proposed increase to $125 (Accessory) and $100 (Agriculture) as two separate tiers, plus a new $50 'third review' fee — none of which appear on either of the county's own live-published documents. See the Primary-use fee note above for the full resolution of this discrepancy, and confirm current figures with Development Services.
$30.00

Review timeline

Plan reviewUnincorporated Cache County’s published plan-review target
28–42 business days

How long did your Zoning Clearance permit actually take in Unincorporated Cache County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Completeness Review

    Development Services staff reviews the submitted application against the checklist with the applicant; incomplete applications are not accepted and are returned to the applicant, per the application form.

  2. 2

    Department Review

    Complete applications are forwarded to the necessary departments for review and comments, per the application form.

  3. 3

    Land Use Authority Approval

    Department reviews and comments are used to prepare the zoning clearance approval, which is presented to the county land use authority for approval, per the application form.

See the full Unincorporated Cache County inspection guide — scheduling & re-inspection fees →

Tips

  • Do not submit a building permit application before the Zoning Clearance is approved and received — the county's own application form states this directly, and a building permit submitted first is expected to be rejected or delayed.
  • The application fee is non-refundable, per the application form.
  • Proceeding with a Zoning Clearance application may change a property's greenbelt taxation status and value, per the application form's own notice — contact the County Assessor's Office before applying if the parcel currently carries a greenbelt (agricultural) tax designation.
  • Cache County's own currently-published application form ($75/$30 fees) and its own separately-hosted Land Use Fee Schedule PDF agree with each other, and both disagree with a 2024 local news report describing a Council-approved increase (to $250/$125/$100/$50). A companion ordinance (Ord. 2024-18, adopted 11/6/2024) did raise Cache County Building Division fees exactly as that news report described, but no equivalent update exists for Land Use/Zoning Clearance fees — the increase appears not to have reached the county's published Land Use fee documentation even though it clearly reached the Building Division's. Treat $75/$30 as the currently-effective figure per two independent live official sources, but a phone call to Development Services, (435) 755-1640, is still worthwhile if budgeting a project where the difference matters.

Frequently asked questions

Yes, for most projects. Cache County's Zoning Clearance Application states directly: 'Do not submit for a building permit until a zoning clearance has been approved and received.' The Zoning Clearance is a Planning & Zoning-level review confirming the proposed use, building, or structure complies with County Code Title 17, separate from and prior to the Building Division's building permit review.

$75.00 for a Primary use and $30.00 for an Accessory or Agricultural use, non-refundable. Two currently-live official sources carry these figures: the county's Zoning Clearance Application form and its separate Land Use Fee Schedule PDF. A 2024 local news report describes a County Council-approved fee increase to $250/$125/$100 (plus a new $50 third-review fee) as part of the same fee package that raised Building Division fees via Ord. 2024-18 in November 2024, but this Land Use/Zoning-Clearance portion of that increase does not appear in either of the county's own currently-published documents. Confirm the current fee with Development Services before applying if the distinction matters for your budget.

Approximately four to six weeks from when a complete application and fee are received, per the county's Zoning Clearance Application.

You'll need: Zoning Clearance Application; Site Plan; Floor Plan(s) and Elevation(s). Depending on your project, Unincorporated Cache County may also ask for: Agricultural Building Statement. See the required-documents checklist on this page for details on each.

Unincorporated Cache County requires 3 inspection(s) for a zoning clearance permit, in order: Completeness Review, Department Review, Land Use Authority Approval. Schedule each through Cache County Building Division ((435) 755-1650).

Apply through Cache County Building Division at 179 N Main St, Suite 305, Logan, UT 84321. Phone: (435) 755-1650, email: cachecountyplanreview@gmail.com. Office hours: Mon–Fri 8:00 AM – 5:00 PM (permit pickup/payment ends at 4:45 PM). Official information: https://www.cachecounty.gov/building/.

Unincorporated Cache County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2021 International Residential Code (IRC), plus Appendix AQ of the 2021 IRC — Utah Code § 15A-2-103(1)(b)/(c); unchanged by the July 1, 2026 revision — still the current edition; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); statute has no residential/commercial split — one edition applies to both. NOTE (county page live-checked 2026-07-16): the Cache County Building Code Information page lists 2024 IECC in its main statewide-codes list but separately carries a 'Residential Code: 2021 IRC and the 2021 IECC' line for dwellings up to a duplex — that residential IECC carve-out lags the statute, which adopts a single 2024 IECC edition with no residential/commercial split; the statewide 2024 IECC governs.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the July 1, 2026 revision. NOTE: The Cache County Building Code Information page (last seen 2026-06-30) still lists '2020 NEC' — that page is not updated; the statewide 2023 NEC is the legally in-force edition.; The 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC listed above took effect July 1, 2026, replacing the 2021 editions, per Utah Code § 15A-2-103 (version headed 'Effective 7/1/2026 / Superseded 1/1/2027'). IRC (2021) and NEC (2023) did not change. The 1/1/2027 version of the statute carries identical editions, so no further change is expected then..

Unincorporated Cache County's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Unincorporated Cache County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Unincorporated Cache County lands. Privacy.