Solar Panel Permit in Unincorporated Davis County, Utah

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Unincorporated Davis County. Davis County uses the standard unified building permit application. Solar installations typically include both structural (mounting) and electrical (wiring) scopes under one permit.

Verified 2026-07-01 · Source

When you need this permit

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Battery storage system installation (if structural and electrical work involved)
  • Electrical service upgrade for solar interconnection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar permit — Valuation-based per Building Permit Fee ScheduleGrounded: the current Davis County Fee Schedule PDF (§ 2.48.050, Ord. No. 4-2017, fetched and text-extracted 2026-07-01 from daviscountyutah.gov/docs/librariesprovider28/default-document-library/current-fee-schedule.pdf) lists valuation-based building permit fees plus a defined set of flat/per-sqft categories (shed, reroof, remodel, agriculture buildings, swimming pool, wood stoves, deck, temporary trailer, demolitions, manufactured housing, cell tower site) and contains NO dedicated solar line item. Absence of a dedicated line in the published, cited fee schedule is itself the grounding for 'solar uses the standard valuation-based building permit fee table' — this is a confirmed negative, not an assumption. Total project valuation (panels, racking, electrical, labor) is used to compute the fee via the tiered table; 65% plan review also applies.
Valuation-based per Davis County Code § 2.48.050(A), Ord. No. 4-2017 (minimum $200.00)
Plan ReviewDavis County Code § 2.48.050(A), Ord. No. 4-2017.
65% of the building permit fee, or actual cost, whichever is less

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Davis County building department
~5–14 business days

How long did your Solar Panel Permit permit actually take in Unincorporated Davis County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

See the full Unincorporated Davis County inspection guide — scheduling & re-inspection fees →

Tips

  • Davis County does not publish a dedicated solar permit fee — solar uses the standard valuation-based building permit fee table (§ 2.48.050, Ord. 4-2017). Include total installed cost in the valuation.
  • Rocky Mountain Power interconnection approval is required before energizing a grid-tied system.
  • The 2023 NEC governs solar electrical installations statewide in Utah.
  • Maintain 3-foot access pathways on rooftop solar arrays for firefighter access per adopted fire codes.

Frequently asked questions

Yes. Davis County requires a building permit for solar installations covering both the structural mounting and electrical wiring scopes. The fee is valuation-based per County Code § 2.48.050 (Ord. 4-2017). Apply at daviscounty.portal.iworq.net.

In Unincorporated Davis County, the published Solar permit — Valuation-based per Building Permit Fee Schedule is: Valuation-based per Davis County Code § 2.48.050(A), Ord. No. 4-2017 (minimum $200.00). Additional published fees: Plan Review — 65% of the building permit fee, or actual cost, whichever is less. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a solar panel permit in Unincorporated Davis County typically runs 5–14 business days. This is an estimate, not a published figure — confirm current review times with Davis County Community & Economic Development — Planning & Zoning at (801) 451-3278.

You'll need: Building Permit Application (iworq); Solar/Roof Site Plan; Electrical Single-Line Diagram; Structural Analysis; Equipment Specifications. See the required-documents checklist on this page for details on each.

Unincorporated Davis County requires 2 inspection(s) for a solar panel permit, in order: Rough Electrical, Final / Structural. Schedule each through Davis County Community & Economic Development — Planning & Zoning ((801) 451-3278).

Apply through Davis County Community & Economic Development — Planning & Zoning at 61 South Main Street, Suite 304, Farmington, UT 84025. Phone: (801) 451-3278, email: planning@daviscountyutah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.daviscountyutah.gov/ced/planning/building-permits.

Unincorporated Davis County, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective July 1, 2026 (replaces 2021 IBC); 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); remains in force after July 1, 2026; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective July 1, 2026 (replaces 2021 IPC); 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective July 1, 2026 (replaces 2021 IMC); 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective July 1, 2026 (replaces 2021 IFGC); 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force. NOTE: Davis County's own website does not list a specific NEC edition — the statewide 2023 NEC is the legally in-force edition.; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective July 1, 2026 (replaces 2021 IECC); Utah residential energy provisions effectively follow 2015 IECC residential; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective July 1, 2026 (replaces 2021 IEBC); 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective July 1, 2026; NOTE: Through June 30, 2026, the 2021 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC are in force per Utah Code § 15A-2-103 (version effective through 6/30/2026). Local amendments apply — see the Unincorporated Davis County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Davis County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.