Commercial Building Permit in Unincorporated Davis County, Utah

Required for new commercial construction in Unincorporated Davis County, governed by Davis County Code § 15.01.330 and priced per the same valuation-based Building Permit Fee Schedule (§ 2.48.050(A), Ord. No. 4-2017) used for all construction types. Davis County does not publish a separate residential/commercial split in its fee table, but new commercial construction is subject to Planning Commission Site Plan review and the $1,000 New Construction bond tier.

Reviewed 2026-07-20 · Source

When you need this permit

  • New commercial construction regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a))
  • Site Plan (Planning Commission) review, per Davis County Code § 2.48.050(A)'s 'Other building fees' section
  • Building Permit Application submitted through the daviscounty.portal.iworq.net online portal
  • Contractor DOPL license numbers for General, Electrical, Plumbing, and Mechanical contractors as applicable
  • Sewer and water connection verification from the respective service district, or Davis County Health Department approval for septic/well if applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation-based (same table used for all construction types)Davis County Code § 2.48.050(A), Ord. No. 4-2017 (amended 05/23/2017). Davis County's Building Permit Fee Schedule is a single table applied to all construction, with no separate residential/commercial split — confirmed directly against the current fee schedule PDF, which contains one 'Davis County Building Permit Fee Schedule' valuation table.
$200.00 minimum (valuation $0-$7,500), scaling to $17,608.00 minimum + $96.00/hour beyond 183 hours for valuation over $5,000,000.00 — full tiered table matches the Residential Building Permit entry in this file
Plan Review and ApprovalDavis County Code § 2.48.050(A), Ord. No. 4-2017.
65% of the building permit fee, or actual cost of services, whichever is less
Site Plan (Planning Commission)Davis County Code § 2.48.050(A), 'Other building fees': 'Site Plan (Planning Commission): $200.00.'
$200.00
Construction Bond — New Construction (refundable on approved final inspection)Davis County Code § 2.48.050(A), Ord. No. 4-2017. Refunded upon approved final inspection unless repairs to public street improvements are required — same tier used for new residential construction.
$1,000.00
Credit Card Processing FeeDavis County building permits page (daviscountyutah.gov/ced/planning/building-permits). Pay by check to avoid the surcharge.
2.5% of total payment

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Davis County building department
~10–21 business days

How long did your Commercial Building Permit permit actually take in Unincorporated Davis County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Setback, Excavation & Forms, Footings

    Verify setbacks, excavation, formwork, and footing layout before concrete pour.

  2. 2

    Foundation Reinforcing Steel

    Rebar and anchor bolts in foundation walls.

  3. 3

    4-Way Rough (Framing, Mechanical, Electrical, Plumbing)

    After rough framing, rough mechanical, rough electrical, and rough plumbing — all must pass before insulation or wall cover.

  4. 4

    Insulation

    Insulation installed, before drywall.

  5. 5

    Final

    All work complete — Final Electrical, Final Plumbing, Final Mechanical, Final Construction. Certificate of occupancy issued upon passing.

See the full Unincorporated Davis County inspection guide — scheduling & re-inspection fees →

Tips

  • Davis County uses one universal Building Permit Fee Schedule (§ 2.48.050(A)) for all construction — there is no separately-published commercial valuation table or commercial-specific plan-review percentage distinct from residential.
  • A Site Plan (Planning Commission) fee of $200.00 is listed separately in the county code's 'Other building fees' section — budget for this Planning Commission review step in addition to the Building Permit Fee for new commercial construction.
  • Inspections are conducted by Shums Coda Associates — schedule at least 24 hours in advance via email (ut@shumscoda.com) or phone (800-286-0374), same as for residential permits.
  • Davis County's own Building Permits page (daviscountyutah.gov/ced/planning/building-permits) does not describe a distinct commercial application process, fee page, or Planning Commission step beyond what is documented in County Code § 2.48.050(A) — confirm project-specific requirements directly with Community & Economic Development at (801) 451-3278.
  • Davis County does not publish a distinct sign-permit fee. Signs are instead regulated by "Class" (Class 1 through Class 5) directly in the zoning-district use tables of County Code Title 15, Chapter 15.20 — e.g. agricultural/residential districts generally allow Class 1-2 signs, while commercial/industrial districts allow Class 3-5 signs, per Article 10 of that chapter. No separate sign-permit fee line was found in the county's Current Fee Schedule (§ 2.48.050(A)) — signage for a commercial project is expected to be reviewed as part of the same zoning/site plan review documented above, not a standalone permit.

Frequently asked questions

Unincorporated Davis County requires a commercial building permit for: New commercial construction regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a)); Site Plan (Planning Commission) review, per Davis County Code § 2.48.050(A)'s 'Other building fees' section; Building Permit Application submitted through the daviscounty.portal.iworq.net online portal; Contractor DOPL license numbers for General, Electrical, Plumbing, and Mechanical contractors as applicable; Sewer and water connection verification from the respective service district, or Davis County Health Department approval for septic/well if applicable. If your project isn't listed, confirm with Davis County Community & Economic Development — Planning & Zoning at (801) 451-3278 before starting work.

No. Davis County Code § 2.48.050(A) publishes a single valuation-based Building Permit Fee Schedule used for both residential and commercial construction. New commercial construction is additionally subject to a $200.00 Site Plan (Planning Commission) fee and the $1,000.00 New Construction bond tier.

Plan review for a commercial building permit in Unincorporated Davis County typically runs 10–21 business days. This is an estimate, not a published figure — confirm current review times with Davis County Community & Economic Development — Planning & Zoning at (801) 451-3278.

You'll need: Building Permit Application (iworq); Site Plan (Planning Commission review); Digital Plans/Blueprints; Contractor DOPL License Numbers. See the required-documents checklist on this page for details on each.

Unincorporated Davis County requires 5 inspection(s) for a commercial building permit, in order: Setback, Excavation & Forms, Footings, Foundation Reinforcing Steel, 4-Way Rough (Framing, Mechanical, Electrical, Plumbing), Insulation, Final. Schedule each through Davis County Community & Economic Development — Planning & Zoning ((801) 451-3278).

Apply through Davis County Community & Economic Development — Planning & Zoning at 61 South Main Street, Suite 304, Farmington, UT 84025. Phone: (801) 451-3278, email: planning@daviscountyutah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.daviscountyutah.gov/ced/planning/building-permits.

Unincorporated Davis County, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective July 1, 2026 (replaces 2021 IBC); 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); remains in force after July 1, 2026; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective July 1, 2026 (replaces 2021 IPC); 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective July 1, 2026 (replaces 2021 IMC); 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective July 1, 2026 (replaces 2021 IFGC); 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force. NOTE: Davis County's own website does not list a specific NEC edition — the statewide 2023 NEC is the legally in-force edition.; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective July 1, 2026 (replaces 2021 IECC); Utah residential energy provisions effectively follow 2015 IECC residential; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective July 1, 2026 (replaces 2021 IEBC); 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective July 1, 2026; NOTE: Through June 30, 2026, the 2021 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC are in force per Utah Code § 15A-2-103 (version effective through 6/30/2026). Local amendments apply — see the Unincorporated Davis County overview page for the full list.

Davis County Code § 2.48.050(A) lists a distinct $200.00 'Site Plan (Planning Commission)' fee under its building fees, indicating a Planning Commission site-plan step applies to projects like new commercial construction. Confirm the specific process for your project with Davis County Community & Economic Development at (801) 451-3278.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Davis County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Davis County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.