Solar Permit in Unincorporated Garfield County, Utah
Garfield County Building Department publishes a distinct fee schedule for solar photovoltaic installations, separate from the general Residential Dwelling and Commercial Building permit fee lines. Applications are submitted through City Inspect, the county's online permitting portal, the same as other building permits.
Verified 2026-07-19 · Source
When you need this permit
- Rooftop or ground-mounted solar photovoltaic installation, residential or commercial
- Compliance with the statewide adopted 2023 NEC (rapid shutdown and bonding requirements) per Utah Code § 15A-2-103(1)(g)
- Submission via the City Inspect online permitting portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect and rapid-shutdown placement per the adopted 2023 NEC.
- 2
Final Inspection
Final electrical/structural inspection prior to energizing, per the county's standard Inspection Information and Schedule.
See the full Unincorporated Garfield County inspection guide — scheduling & re-inspection fees →
Tips
- Garfield County publishes a distinct solar-specific fee formula rather than folding solar into the general valuation-based building permit fee table: a $252.43 minimum at $14,000 valuation, then 65% plan check and 40% of the combined total for projects under $100,000.
- Projects with a valuation over $100,000 fall back to the county's general Total Building Permit Valuation fee schedule rather than the solar-specific formula.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Garfield County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Garfield County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Garfield County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Garfield County lands. Privacy.
Other permits in Unincorporated Garfield County
Solar Permit in other cities
Compare solar permit fees across Utah →
Look up this fee in a different city →