Residential Building Permit — Unincorporated Garfield County, Utah · Requirements sheet
Verified 2026-07-13 · Source: https://www.garfield.utah.gov/Departments/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Unincorporated Garfield County, Utah
Required for new single-family/manufactured home construction, additions, and structural alterations in unincorporated Garfield County. The Garfield County Building Department issues the building permit, performs plan review, and conducts all inspections for the unincorporated county AND — per contract — for essentially all of the county's small incorporated towns (documented explicitly for Boulder Town, which contracts with Garfield County 'to issue the actual Building Permit, conduct all building code inspections, and issue the Certificate of Occupancy'). Property inside city/town limits requires town-level zoning/project approval first, but the building permit itself still comes from the county.
Verified 2026-07-13 · Source
When you need this permit
- New single-family dwelling or manufactured home construction
- Additions to existing residential structures
- Any structural modification, remodel, repair, or demolition
- Basements, second levels, decks, private garages, carports, patio covers, and other accessory structures per the fee schedule
- Large sheds (200 sq ft or more, or any shed with power/water/heat) — see Local Amendments
- Two complete sets of plans (one retained by the building department, one kept on the jobsite)
- City/town zoning approval first if the property is within incorporated city/town limits
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footings
After excavation with required forms and reinforcing steel in place; other required materials except concrete must be on the job site, including slab-edge insulation where applicable.
- 2
Foundation Walls
After forms and reinforcing steel are in place with other required materials on-site; includes basement wall exterior insulation or crawl space wall insulation where applicable.
- 3
4-Way Rough
Rough framing, rough electrical, rough plumbing, and rough mechanical performed together where possible. Energy code items (floor/wall insulation, glazing and door area, mass walls, joints/penetrations, duct insulation, vapor retarder, duct construction) checked at the same inspection where applicable.
- 4
Insulation Inspection and Shower Pan
Insulation installed and shower pan liner tested before cover
- 5
Gypsum Board
After gypsum board is in place, before taping and finishing
- 6
Final Inspection
After finish grading and building completion, ready for occupancy but before occupying. The county will not perform a final inspection on an occupied building, and will not issue a signed Final Inspection or Certificate of Occupancy with uncorrected code violations.
See the full Unincorporated Garfield County inspection guide — scheduling & re-inspection fees →
Tips
- Requests for inspection must be made to the Garfield County Building Department no less than two working days prior to the proposed inspection date, by telephone or in writing.
- If your property is within Tropic or anywhere west of Tropic, get your Utah Prairie Dog clearance letter from DWR (Patrick Anderson, 435-691-5700) before applying — the application will not be accepted without it.
- If your property is within an incorporated city/town (Antimony, Boulder Town, Bryce Canyon City, Cannonville, Escalante, Hatch, Henrieville, Panguitch, Tropic), get town-level zoning/project approval first — the county will not issue the building permit until the town approves the project. Boulder Town's process is fully documented as a two-step Town Project Approval + County Building Permit; most other incorporated towns in the county follow the same pattern of contracting building-permit issuance to the county.
- Sheds under 200 sq ft with no power, water, or heat are exempt from a building permit; sheds at or above 200 sq ft, or any shed with power/water/heat regardless of size, require one.
- Applications are submitted through the 'City Inspect' online portal — new users create an account and receive a temporary password by email.
- Two complete sets of plans are required — one is retained by the building department, one must stay on the jobsite.
- Permits expire if construction has not commenced within 180 days of issuance, or if work is suspended for 180 days; no fees are refunded after 180 days.
- EV charger / EVSE installation is not itemized anywhere in the Garfield County Building Department Fees schedule — a full-text review of its itemized valuation tiers, Manufactured Home, Basement, Second Level, Garage, Deck, Plan Review, WUI, Re-Inspection, and Permit Renewal line items found no 'EV,' 'electric vehicle,' or 'charging station' entry. A standalone EV charging circuit would be expected to fall under the general valuation-based Building Permit Fee applied to other electrical work; confirm with the Building Department, (435) 676-1111, before budgeting a specific project.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Garfield County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Garfield County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Garfield County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Garfield County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →