Skip to main content
PermitBase

Solar Permit in Unincorporated Grand County, Utah

Grand County's Consolidated Fee Schedule publishes distinct flat fees for solar installations, split by mounting type (roof vs. ground), separate from the general residential valuation-based building permit fee table.

Verified 2026-07-19 · Source

When you need this permit

  • Roof-mount or ground-mount solar photovoltaic installation
  • Compliance with the statewide adopted 2023 NEC (rapid shutdown and bonding requirements) per Utah Code § 15A-2-103(1)(g)
  • Utah State 1% surcharge and one hour of plan review are added to the base permit fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar: Roof MountGrand County Ordinance No. 688 (2024 Consolidated Fee Schedule), § 3.06.100. Plus Utah State 1% surcharge and one hour of plan review added to the permit fee.
$65.00 per permit
Solar: Ground MountGrand County Ordinance No. 688 (2024 Consolidated Fee Schedule), § 3.06.100. Plus Utah State 1% surcharge and one hour of plan review added to the permit fee.
$130.00 per permit

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Grand County building department
~1–14 business days

How long did your Solar Permit permit actually take in Unincorporated Grand County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Trench / Rough Electrical

    Conduit runs, wire sizing, disconnect and rapid-shutdown placement per the adopted 2023 NEC.

  2. 2

    Final

    Final electrical/structural inspection prior to energizing.

See the full Unincorporated Grand County inspection guide — scheduling & re-inspection fees →

Tips

  • Grand County is one of the few Utah counties in this dataset that prices solar by mounting type — a flat $65 for roof-mount vs. $130 for ground-mount — rather than a single flat fee or a valuation-based calculation.
  • Both solar fee tiers carry a Utah State 1% surcharge and one hour of plan review added on top of the base permit fee, per the footnotes on the county's Specific Projects fee table.

Frequently asked questions

Unincorporated Grand County requires a solar permit for: Roof-mount or ground-mount solar photovoltaic installation; Compliance with the statewide adopted 2023 NEC (rapid shutdown and bonding requirements) per Utah Code § 15A-2-103(1)(g); Utah State 1% surcharge and one hour of plan review are added to the base permit fee. If your project isn't listed, confirm with Grand County Building Department at (435) 259-4134 before starting work.

Per Grand County Ordinance No. 688 (2024 Consolidated Fee Schedule), a roof-mount solar permit is $65.00 and a ground-mount solar permit is $130.00, each plus the Utah State 1% surcharge and one hour of plan review added to the base fee.

Plan review for a solar permit in Unincorporated Grand County typically runs 1–14 business days. This is an estimate, not a published figure — confirm current review times with Grand County Building Department at (435) 259-4134.

You'll need: Building Permit Application; Electrical Single-Line Diagram. See the required-documents checklist on this page for details on each.

Unincorporated Grand County requires 2 inspection(s) for a solar permit, in order: Electrical Trench / Rough Electrical, Final. Schedule each through Grand County Building Department ((435) 259-4134).

Apply through Grand County Building Department at 59 N 200 E, Moab, UT 84532. Phone: (435) 259-4134, email: building@grandcountyutah.net. Office hours: Mon–Fri 8:00 AM – 5:00 PM, closed 12:00–1:00 PM and on county holidays. Appointment required — call ahead before visiting; the office does not accept walk-ins.. Official information: https://www.grandcountyutah.net/143/Building-Inspector.

Unincorporated Grand County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Grand County's own Design Criteria page still lists the 2021 IBC with Appendix J (with Utah State Amendments; no Appendix C cited) — live-checked 2026-07-16, the county's own page has not been updated to the current statewide edition.; 2021 International Residential Code (IRC), including Appendix AQ — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Grand County's own Design Criteria page lists the 2021 IRC with Utah State Amendments (no distinct Appendix AQ citation) — live-checked 2026-07-16, consistent with the current statute on the base edition.; 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Grand County's own Design Criteria page still lists the 2021 IPC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Grand County's own Design Criteria page still lists the 2021 IMC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Grand County's own Design Criteria page still lists the 2021 IFGC — live-checked 2026-07-16, lags the current statewide edition.; 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is UNCHANGED from the prior code cycle. Grand County's own Design Criteria page lists the 2020 NEC with Utah State Amendments — live-checked 2026-07-16, one cycle behind the current statewide edition; verify current edition in force with the Building Department at time of application.; 2024 International Energy Conservation Code (IECC) — one code, no residential/commercial split, per Utah Code §15A-2-103(1)(h). Grand County's own Design Criteria page still splits it — 2021 IECC for commercial and 2015 IECC for residential — live-checked 2026-07-16, both lag the current statewide edition; the residential/commercial split itself is preserved here as county-published history, not carried into the governing statutory citation.; 2024 International Existing Building Code (IEBC) — governs per Utah Code §15A-2-103(1)(i). Grand County's own Design Criteria page still lists the 2021 IEBC with Utah State Amendments — live-checked 2026-07-16, lags the current statewide edition.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs per Utah Code §15A-2-103(1)(n). Grand County's own Design Criteria page text reads '2018 edition of the International Swimming Pool and Spa Code' while its hyperlink label reads '2021 ISPSC' (an internal inconsistency on the county's own page, live-checked 2026-07-16, quoted verbatim as history) — both lag the current statewide edition.; Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not listed on Grand County's own Design Criteria page — live-checked 2026-07-16.; ICC A117.1-2009 (Accessibility); 2006 Utah Wildland-Urban Interface Code; HUD Code (manufactured/mobile homes). Local amendments apply — see the Unincorporated Grand County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Grand County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.