Solar Permit — Unincorporated Grand County, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.grandcountyutah.net/DocumentCenter/View/18455/Ordinance-688-2024-Consolidated-Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Permit in Unincorporated Grand County, Utah
Grand County's Consolidated Fee Schedule publishes distinct flat fees for solar installations, split by mounting type (roof vs. ground), separate from the general residential valuation-based building permit fee table.
Verified 2026-07-19 · Source
When you need this permit
- Roof-mount or ground-mount solar photovoltaic installation
- Compliance with the statewide adopted 2023 NEC (rapid shutdown and bonding requirements) per Utah Code § 15A-2-103(1)(g)
- Utah State 1% surcharge and one hour of plan review are added to the base permit fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Trench / Rough Electrical
Conduit runs, wire sizing, disconnect and rapid-shutdown placement per the adopted 2023 NEC.
- 2
Final
Final electrical/structural inspection prior to energizing.
See the full Unincorporated Grand County inspection guide — scheduling & re-inspection fees →
Tips
- Grand County is one of the few Utah counties in this dataset that prices solar by mounting type — a flat $65 for roof-mount vs. $130 for ground-mount — rather than a single flat fee or a valuation-based calculation.
- Both solar fee tiers carry a Utah State 1% surcharge and one hour of plan review added on top of the base permit fee, per the footnotes on the county's Specific Projects fee table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Grand County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Grand County
Solar Permit in other cities
Compare solar permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Grand County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Grand County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →