Residential Building Permit — Unincorporated Grand County, Utah · Requirements sheet
Verified 2026-07-08 · Source: https://www.grandcountyutah.net/DocumentCenter/View/3875/Building-permit-application-requirements_residential_2020
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Unincorporated Grand County, Utah
Required for new single-family residential construction, additions, and structural alterations in unincorporated Grand County, Utah (outside Moab city limits). The Grand County Building Department issues permits for all of Grand County including Castle Valley and the unincorporated area, and also serves as the county Floodplain Administrator.
Verified 2026-07-08 · Source
When you need this permit
- New single-family dwelling construction
- Additions to existing residential structures
- Structural alterations or renovations
- Zoning sign-off required before building permit application (contact Grand County Zoning first)
- Floodplain Development Permit Application required if construction is in or touches the floodplain/floodway
- Water and sewer service sign-off from Grand Water & Sewer Service Agency (GWSSA), or Health Department sign-off if served by well/septic
- All contractors/subcontractors must hold a current Utah State Contractor's license Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Sewer and Water Service Lines
Installation from road to structure — before excavation is covered
- 2
Electrical Trench
Underground electrical service trench before backfill
- 3
Footing
Excavation complete, forms and reinforcing steel in place — before any concrete is poured
- 4
Foundation
Forms and reinforcing steel in place — before any concrete is poured
- 5
Underground / Under-Slab / Interior Shovel Footings
Sub-rough plumbing and heating in place, pressure tested — before pipes are buried and floor slab poured
- 6
Slab
Before concrete pour on slab
- 7
Temporary Power
Construction power contracted by contractor — Rocky Mountain Power work order number required when scheduling
- 8
Weather Barrier / Lath & Flashing
Before or after the four-way — before any brick or stucco is installed on a foundation ledge
- 9
Duct Blaster Test
Performed by third-party inspector; report must be submitted to building@grandcountyutah.net prior to requesting the four-way inspection
- 10
Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)
All roof/wall/floor framing, fire stopping, and bracing complete with truss calculations on site; wiring, plumbing, and mechanical rough-in complete before concealment
- 11
Gas Line
Gas piping installed and pressure tested
- 12
Insulation
After insulation installed, before drywall
- 13
Drywall
After nailing and before taping of required firewalls and braced walls
- 14
Shower Pan
Before tile/finish installed over shower pan liner
- 15
Power to Panel / Permanent Power
Electrical meter base placed and ready to energize — Rocky Mountain Power work order number required when scheduling
- 16
Mechanical
After all dust-producing work complete, equipment installed/vented, combustion air supplied
- 17
Final
All work complete, prior to occupancy. Final Floodplain inspection (post-construction Elevation Certificate) also required prior to Certificate of Occupancy if the site is within a flood hazard area.
See the full Unincorporated Grand County inspection guide — scheduling & re-inspection fees →
Tips
- Plans are reviewed first-come, first-served for complete submittals; the Building Department publishes a plan review timeline of 'up to two (2) weeks depending on current demand' — apply with buffer time.
- Incomplete submittals are rejected and returned for resubmittal (inaccurate design criteria, irrelevant general notes, missing or invalid designer stamps are common rejection reasons) — this resets the review clock, so submit a complete packet the first time.
- Contact Zoning first, before applying for a building permit, to confirm what you can build and where on your parcel — zoning sign-off is required as part of the online application routing.
- Inspections require a minimum 24-hour notice and can only be scheduled by phone at (435) 259-4134 — email, text, and voicemail requests are not accepted.
- Rocky Mountain Power work order numbers are required when scheduling both Temporary Power and Power to Panel/Permanent Power inspections.
- Building permits expire 180 days (six months) after issuance or after the last inspection; a one-time 6-month extension may be requested in writing before expiration; a $65 renewal fee may apply if the permit lapses.
- One re-inspection per required inspection type is included in the base permit fee; a $65/hour fee applies starting with the 3rd or subsequent re-inspection of the same kind.
- CC&Rs are enforced by the property's HOA, not by Grand County.
- EV charger / EVSE installation is not itemized as its own line item in Grand County's 2024 Consolidated Fee Schedule (Ordinance No. 688) — a full-text review found no 'EV,' 'electric vehicle,' or 'charging station' entry among the schedule's 'Specific Projects' fees (which do separately list Solar roof mount $65.00/permit and Solar ground mount $130.00/permit). A standalone EV charging circuit is standard electrical work and would be expected to fall under the schedule's existing 'Mechanical, electrical, and/or plumbing separate permits' line item, billed at $65.00 per inspection, per Ordinance No. 688 § 3.06.100(B).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Grand County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Grand County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →