Fire Sprinkler System Permit in Holladay, Utah
Fire protection system permitting in Holladay is handled by Unified Fire Authority (UFA), a special fire district separate from the Holladay Building Division. Holladay City is listed among UFA's member communities. UFA requires a permit for installation or modification of any automatic fire sprinkler system, plus mandatory third-party peer review of the design (except for minor work below specific device-count thresholds). UFA itself charges no permit fee for this — confirmed against UFA's own FY26/27 Adopted Budget, which itemizes the Fire Prevention division's entire fee revenue as Hazardous Materials & Tank Permits, Firewatch Reimbursements, and Fireworks Permits only. The applicant instead pays a privately-set fee directly to one of UFA's approved third-party peer-review firms.
Verified 2026-07-20 · Source
When you need this permit
- Permit required from the fire code official (UFA) before beginning work on any fire protection system, per International Fire Code Section 105.1.1 — beginning work before permit issuance and plan approval is done at the contractor's own risk
- Fire Sprinkler System plans must be submitted to a UFA-approved Third Party Review company before final submittal to UFA (ufaplansubmittal@unifiedfire.org)
- Third-party peer review required for automatic fire sprinkler system installation/modification, EXCEPT: installation of fire hydrants/underground supply lines, pre-engineered kitchen hood suppression systems, or installation/relocation of fewer than 20 sprinkler heads
- System designer must be NICET Level III (Water-Based Fire Protection Systems Layout) or better, a Fire Protection Engineer, or a licensed engineer with specific additional fire protection training
- Design and installation per the most recent NFPA 13, 13-R, or 13-D adopted by the State of Utah
- Systems with 20 or more sprinkler heads (with limited 13-D/13-R exceptions) require off-site remote monitoring from an approved monitoring company
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
UFA's FY26/27 Adopted Budget (unifiedfireut.gov/wp-content/uploads/ProposedBudget_040626.pdf), Fire Prevention division Revenue Summary, p.288, breaks the division's complete FY27 fee revenue into… Show full citationHide
UFA's FY26/27 Adopted Budget (unifiedfireut.gov/wp-content/uploads/ProposedBudget_040626.pdf), Fire Prevention division Revenue Summary, p.288, breaks the division's complete FY27 fee revenue into exactly three categories — Hazardous Materials & Tank Permits ($370,000), Firewatch Reimbursements ($9,000), and Fireworks Permits ($6,000), totaling $385,000. No fire sprinkler or fire alarm permit fee line item appears anywhere in that revenue breakdown: UFA does not bill a permit fee for these systems.UFA's 'Peer Review for Fire Protection Systems' roster (unifiedfireut.gov/wp-content/uploads/Peer-Review-for-Fire-Protection-Systems-4.25.pdf) lists 10 UFA-approved private engineering… Show full citationHide
UFA's 'Peer Review for Fire Protection Systems' roster (unifiedfireut.gov/wp-content/uploads/Peer-Review-for-Fire-Protection-Systems-4.25.pdf) lists 10 UFA-approved private engineering firms/individuals (e.g., Protection Consultants Inc., Spectrum Engineers, Impact Fire Protection) and instructs applicants to 'submit plans to the company of your choice' — UFA does not set, collect, or publish this fee since it is a private commercial transaction between the applicant and the reviewer they select.Review timeline
Inspection process
See the full Holladay inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler permitting in Holladay runs through Unified Fire Authority (UFA), NOT the Holladay Building Division — Holladay's own Consolidated Fee Schedule has no fire sprinkler permit fee line item because UFA handles this separately.
- UFA itself charges no plan-review or permit fee for fire sprinkler systems — confirmed by UFA's FY26/27 Adopted Budget, which lists the Fire Prevention division's entire fee revenue (Hazmat & Tank Permits, Firewatch, Fireworks Permits) with no sprinkler/alarm line item. The real cost to the applicant is the market rate charged by whichever UFA-approved third-party peer reviewer they hire.
- Design and third-party peer review must be completed BEFORE final plans go to UFA — starting sprinkler work before permit issuance and plan approval is done at the contractor's own risk with no special allowances.
- Any change to a fire sprinkler system's hazard classification design requires a new permit and a new third-party plan review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holladay building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Holladay's permit history is searchable by address
13,808 permits on record for Holladay, 2015–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
97% of Holladay's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.
Other permits in Holladay
Fire Sprinkler System Permit in other cities
Compare fire sprinkler system permit fees across Utah →