EV Charger / EVSE Permit — Unincorporated Wasatch County, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.wasatchcounty.gov/215/Frequently-Asked-Questions
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Wasatch County, Utah
Wasatch County publishes no separate EV charger (EVSE) permit type or fee line. EV charger installation is treated as standard electrical work under the same general Building Permit process used for every other permit type. The county's Building Permit FAQ (wasatchcounty.gov/215/Frequently-Asked-Questions) itemizes 'Other Fees' — Temporary Power $75.00, Solid Waste SSD Garbage Fee, and fire/water/sewer/power district fees — with no electrical trade-permit line and no EV-charging line item. The county publishes no standalone electrical permit fee either, so budget an EV charger installation under the same general per-square-foot Building Department fee mechanism documented for the residential building permit.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in unincorporated Wasatch County — treated as standard electrical work under the county's general Building Permit process
- Building Permit Application submitted through the county's online Plan Review Portal (wasatchcounty.gov/Building)
- Compliance with the 2023 NEC, which governs statewide per Utah Code § 15A-2-103(1)(g)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Wasatch County Building Permit FAQ (wasatchcounty.gov/215/Frequently-Asked-Questions): 'Permit fees are based on square footage and vary from project to project... Show full citationHide
Wasatch County Building Permit FAQ (wasatchcounty.gov/215/Frequently-Asked-Questions): 'Permit fees are based on square footage and vary from project to project... the average cost for the Building Department portion of the permit is around $1.25 per sq. ft.' (that figure is dated June 2016 but is still the county's own currently-published guidance). No EV-charger-specific or general standalone-electrical-permit fee line is published anywhere on wasatchcounty.gov; the county's FAQ 'Other Fees' section lists only Temporary Power ($75.00), Solid Waste SSD, and Special Service District fees, with no electrical trade-permit or EV-specific line item. Contact the Building Department at (435) 657-3200 for a project-specific quote.Review timeline
Inspection process
- 1
Electrical
Not separately published for EV chargers by the county; follows the standard rough-in and final electrical inspection sequence documented for this jurisdiction's residential-building-permit entry.
See the full Unincorporated Wasatch County inspection guide — scheduling & re-inspection fees →
Tips
- Wasatch County treats EV charger installation as ordinary electrical work under its general Building Permit process — there is no dedicated EV-charger permit type, application, or fee category.
- Wasatch County publishes no standalone Electrical Permit fee line at all — confirm the applicable fee for a standalone EV charger installation directly with the Building Department at (435) 657-3200 before you quote the job.
- The Plan Review Fee (65% of the Building Department fee) is invoiced by email after submittal, not collected at time of application — online payment only.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wasatch County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Wasatch County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Wasatch County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Wasatch County lands. Privacy.
Other permits in Unincorporated Wasatch County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Wasatch County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Wasatch County — in one checklist. Free, for any city and any number of projects.
Get started →