Solar PV Permit — Unincorporated Wasatch County, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.wasatchcounty.gov/211/Building-Department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Unincorporated Wasatch County, Utah
Required for solar photovoltaic installations in unincorporated Wasatch County. Wasatch County Code § 16.21.42 (Supplementary Development Standards for solar panels) gives solar installations a genuinely distinct zoning treatment depending on mounting type: flush-mounted roof panels are a permitted use in any zone; 'structured' (non-flush, tilted) roof panels are a CONDITIONAL USE in any zone, requiring Planning Commission approval; freestanding (ground-mounted) panels are a permitted use in residential districts only, subject to height, maximum-area, and setback requirements. A building permit is required for installation regardless of mounting type. Wasatch County does not publish a distinct solar-specific building-permit fee (the county's ordinance is hosted on municipalcodeonline.com) — the general per-square-foot Building Department fee mechanism documented for this jurisdiction's residential-building-permit entry applies. The county's Application Fee Schedule (Wasatch County Code 4.09.02 C, effective 7/2025) publishes an exact Conditional Use Permit fee of $700.00 + costs, which is the fee that governs the § 16.21.42 CUP requirement for 'structured' roof-mounted arrays.
Verified 2026-07-20 · Source
When you need this permit
- Flush-mounted roof solar panels: permitted use in any zone, per Wasatch County Code § 16.21.42 — no Conditional Use Permit required for this mounting type
- 'Structured' (non-flush, tilted-rack) roof solar panels: a CONDITIONAL USE in any zone per § 16.21.42, requiring Planning Commission approval before installation
- Freestanding (ground-mounted) solar panels: a permitted use in residential districts only, subject to height, maximum-area, and setback requirements per § 16.21.42
- Building permit required for installation regardless of mounting type, submitted through the county's online Plan Review Portal
- Structural engineering documentation for roof-mounted arrays (roof load capacity) and electrical single-line diagram for grid interconnection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Wasatch County's Frequently Asked Questions page (wasatchcounty.gov/215/Frequently-Asked-Questions and wasatchcounty.gov/frequently-asked-questions) states: 'Permit fees are based on square footage… Show full citationHide
Wasatch County's Frequently Asked Questions page (wasatchcounty.gov/215/Frequently-Asked-Questions and wasatchcounty.gov/frequently-asked-questions) states: 'Permit fees are based on square footage and vary from project to project. As of June 13, 2016, the average cost for the Building Department portion of the permit is around $1.25 per sq. ft. This includes all square footage, finished, unfinished, garage, and porches and decks.' The underlying figure dates from June 2016, but the county still publishes it as current guidance and no newer figure supersedes it anywhere on wasatchcounty.gov. There is no distinct solar valuation table; this general mechanism governs the building-permit component of a solar installation the same as it does any other structure.Per the same County FAQ page. This impact fee applies to new single-family residence construction connecting to county services; Show full citationHide
Per the same County FAQ page. This impact fee applies to new single-family residence construction connecting to county services; it is unlikely to apply to a stand-alone solar retrofit on an already-connected, existing dwelling, but the FAQ page states no explicit solar or retrofit exemption — confirm applicability for your specific project with the Building Department, (435) 657-3200.Wasatch County Application Fee Schedule, fetched directly 2026-07-20 (wasatchcounty.gov/DocumentCenter/View/246/Application-Fee-Schedule-PDF, footer-dated 'Wasatch County Code 4.09.02 C - 7/2025'):… Show full citationHide
Wasatch County Application Fee Schedule, fetched directly 2026-07-20 (wasatchcounty.gov/DocumentCenter/View/246/Application-Fee-Schedule-PDF, footer-dated 'Wasatch County Code 4.09.02 C - 7/2025'): 'Conditional Use Permit $700 + Costs (Costs include $0.50 per letter, any Engineering Review expenses or legal noticing).' This is the Planning Department's standard, county-wide Conditional Use Permit fee — not solar-specific in the schedule's own text, but it is the exact fee that governs the § 16.21.42 Conditional Use requirement for 'structured' (non-flush) roof-mounted solar arrays.Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing — not separately published for solar by the county; follows the standard MEP rough-in sequence documented for this jurisdiction's residential-building-permit entry.
- 2
Final
Panel/array mounting and electrical connections verified — not separately published for solar by the county; follows the standard final inspection documented for this jurisdiction's residential-building-permit entry.
See the full Unincorporated Wasatch County inspection guide — scheduling & re-inspection fees →
Tips
- Mounting type matters in Wasatch County: flush-mounted roof panels are a permitted use requiring only a building permit, but 'structured' (tilted, non-flush) roof panels are a Conditional Use requiring Planning Commission approval in addition to the building permit — confirm which category your installation falls into before applying.
- Freestanding (ground-mounted) solar arrays are only a permitted use in residential districts, and must meet height, maximum-area, and setback standards under Wasatch County Code § 16.21.42 — contact the Planning Department, (435) 657-3205, to confirm your parcel's zone and the applicable numeric standards, which could not be independently rendered from the county's client-side ordinance platform.
- No solar-specific building-permit fee table is published; the general ~$1.25/sq ft Building Department fee (still the county's own live-published figure as of a 2026-07-20 re-check, though originally dated June 2016) applies to the building-permit portion of a solar project, and a $700 + costs Conditional Use Permit fee (Wasatch County Code 4.09.02 C, effective 7/2025) applies if your installation is 'structured' (non-flush) roof-mounted and therefore triggers the § 16.21.42 CUP requirement — confirm directly with the Building Department, (435) 657-3200, and the Planning Department, (435) 657-3205.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wasatch County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Wasatch County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Wasatch County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Wasatch County lands. Privacy.
Other permits in Unincorporated Wasatch County
Solar PV Permit in other cities
Compare solar pv permit fees across Utah →
Look up this fee in a different city →