Solar PV Permit in Unincorporated Wasatch County, Utah

Required for solar photovoltaic installations in unincorporated Wasatch County. Wasatch County Code § 16.21.42 (Supplementary Development Standards for solar panels) gives solar installations a genuinely distinct zoning treatment depending on mounting type: flush-mounted roof panels are a permitted use in any zone; 'structured' (non-flush, tilted) roof panels are a CONDITIONAL USE in any zone, requiring Planning Commission approval; freestanding (ground-mounted) panels are a permitted use in residential districts only, subject to height, maximum-area, and setback requirements. A building permit is required for installation regardless of mounting type. Wasatch County's own Building Department pages (municipalcodeonline.com hosts the ordinance on a client-side-rendered platform that returns no readable body text to automated fetch tools) do not publish a distinct solar-specific building-permit fee — the general per-square-foot Building Department fee mechanism documented for this jurisdiction's residential-building-permit entry applies. Re-chased 2026-07-20: the county's live Application Fee Schedule (Wasatch County Code 4.09.02 C, effective 7/2025) publishes an exact Conditional Use Permit fee of $700.00 + costs, which is the fee that governs the § 16.21.42 CUP requirement for 'structured' roof-mounted arrays.

Verified 2026-07-20 · Source

When you need this permit

  • Flush-mounted roof solar panels: permitted use in any zone, per Wasatch County Code § 16.21.42 — no Conditional Use Permit required for this mounting type
  • 'Structured' (non-flush, tilted-rack) roof solar panels: a CONDITIONAL USE in any zone per § 16.21.42, requiring Planning Commission approval before installation
  • Freestanding (ground-mounted) solar panels: a permitted use in residential districts only, subject to height, maximum-area, and setback requirements per § 16.21.42
  • Building permit required for installation regardless of mounting type, submitted through the county's online Plan Review Portal
  • Structural engineering documentation for roof-mounted arrays (roof load capacity) and electrical single-line diagram for grid interconnection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Building Department (general, all mounting types)Wasatch County's own live Frequently Asked Questions page (wasatchcounty.gov/215/Frequently-Asked-Questions and wasatchcounty.gov/frequently-asked-questions), re-fetched directly 2026-07-20: 'Permit fees are based on square footage and vary from project to project. As of June 13, 2016, the average cost for the Building Department portion of the permit is around $1.25 per sq. ft. This includes all square footage, finished, unfinished, garage, and porches and decks.' Though the underlying figure is dated June 2016, the county's own website still actively publishes it as current guidance as of this 2026-07-20 re-fetch — no newer figure has superseded it anywhere on wasatchcounty.gov. No distinct solar valuation table exists; this general mechanism governs the building-permit component of a solar installation the same as it does for any other structure.
approximately $1.25 per square foot (all finished, unfinished, garage, porch, and deck square footage)
County Impact FeeSame live-refetched FAQ page, 2026-07-20. This impact fee applies to new single-family residence construction (connecting to county services); it is unlikely to apply to a stand-alone solar retrofit on an already-connected, existing dwelling, but the FAQ page does not state an explicit solar/retrofit exemption — confirm applicability for your specific project with the Building Department, (435) 657-3200.
$3,085.00 for new single-family residences
Conditional Use Permit Fee ('structured'/non-flush roof panels, or any freestanding installation requiring CUP review)Wasatch County Application Fee Schedule, fetched directly 2026-07-20 (wasatchcounty.gov/DocumentCenter/View/246/Application-Fee-Schedule-PDF, footer-dated 'Wasatch County Code 4.09.02 C - 7/2025'): 'Conditional Use Permit $700 + Costs (Costs include $0.50 per letter, any Engineering Review expenses or legal noticing).' This is the Planning Department's standard, county-wide Conditional Use Permit fee — not solar-specific in the schedule's own text, but it is the exact fee that governs the § 16.21.42 Conditional Use requirement for 'structured' (non-flush) roof-mounted solar arrays.
$700.00 + costs (costs include $0.50 per notice letter, any Engineering Review expenses, or legal noticing)

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Unincorporated Wasatch County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing — not separately published for solar by the county; follows the standard MEP rough-in sequence documented for this jurisdiction's residential-building-permit entry.

  2. 2

    Final

    Panel/array mounting and electrical connections verified — not separately published for solar by the county; follows the standard final inspection documented for this jurisdiction's residential-building-permit entry.

See the full Unincorporated Wasatch County inspection guide — scheduling & re-inspection fees →

Tips

  • Mounting type matters in Wasatch County: flush-mounted roof panels are a permitted use requiring only a building permit, but 'structured' (tilted, non-flush) roof panels are a Conditional Use requiring Planning Commission approval in addition to the building permit — confirm which category your installation falls into before applying.
  • Freestanding (ground-mounted) solar arrays are only a permitted use in residential districts, and must meet height, maximum-area, and setback standards under Wasatch County Code § 16.21.42 — contact the Planning Department, (435) 657-3205, to confirm your parcel's zone and the applicable numeric standards, which could not be independently rendered from the county's client-side ordinance platform.
  • No solar-specific building-permit fee table is published; the general ~$1.25/sq ft Building Department fee (still the county's own live-published figure as of a 2026-07-20 re-check, though originally dated June 2016) applies to the building-permit portion of a solar project, and a $700 + costs Conditional Use Permit fee (Wasatch County Code 4.09.02 C, effective 7/2025) applies if your installation is 'structured' (non-flush) roof-mounted and therefore triggers the § 16.21.42 CUP requirement — confirm directly with the Building Department, (435) 657-3200, and the Planning Department, (435) 657-3205.

Frequently asked questions

It depends on the mounting type. Per Wasatch County Code § 16.21.42, flush-mounted roof panels are a permitted use requiring only a building permit. 'Structured' (non-flush, tilted-rack) roof panels are a Conditional Use in any zone, requiring Planning Commission approval. Freestanding (ground-mounted) panels are a permitted use only in residential districts, subject to height, area, and setback standards. Confirm your specific installation type with the Planning Department, (435) 657-3205.

No solar-specific building-permit fee table is published, but the components that apply are known. The general Building Department fee mechanism documented for residential construction (approximately $1.25 per square foot, still the county's own currently-published figure as of a 2026-07-20 live re-check, though dated June 2016) applies to the building-permit portion. If your installation is 'structured' (non-flush) roof-mounted, Wasatch County's Application Fee Schedule (effective 7/2025) sets the Conditional Use Permit fee at $700.00 plus costs. Contact the Building Department, (435) 657-3200, and Planning Department, (435) 657-3205, for a full project-specific quote.

Unincorporated Wasatch County does not publish a plan-review timeline for this permit. Contact Wasatch County Building Department at (435) 657-3200 for current turnaround.

You'll need: Building Permit Application (online, via Plan Review Portal); Electrical Single-Line Diagram and Equipment Specifications. Depending on your project, Unincorporated Wasatch County may also ask for: Conditional Use Permit Application ('structured'/non-flush roof panels only); Site Plan (freestanding/ground-mounted arrays). See the required-documents checklist on this page for details on each.

Unincorporated Wasatch County requires 2 inspection(s) for a solar pv permit, in order: Rough Electrical, Final. Schedule each through Wasatch County Building Department ((435) 657-3200).

Apply through Wasatch County Building Department at 1891 W 3000 S, Heber City, UT 84032. Phone: (435) 657-3200, email: Bldinfo@wasatch.utah.gov. Office hours: 7:30 AM to 5:30 PM, Monday–Friday, per the Wasatch County Building Department FAQ page (wasatchcounty.gov/215/Frequently-Asked-Questions). Building Department is distinct from the county's Engineering Department (435-657-3305, handles right-of-way/grading/subdivision permits) and Planning Department (435-657-3205, handles impact fees for multi-family/commercial and zoning).. Official information: https://www.wasatchcounty.gov/211/Building-Department.

Unincorporated Wasatch County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Wasatch County's own 'Plan Submission Requirements - Single Family Dwelling' checklist (wasatchcounty.gov/DocumentCenter/View/1032/Checklist-Single-Family-Dwelling) still states plans 'must be designed to and reflect... 2021 International Building Code for structural' (no appendices cited) — live-checked 2026-07-16, the county's own checklist has not been updated to the current statewide edition.; 2021 International Residential Code (IRC), including Appendix AQ — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Wasatch County's own checklist states plans 'must be designed to and reflect the 2021 International Residential Code for architectural' (no distinct Appendix AQ citation) — live-checked 2026-07-16, consistent with the current statute on the base edition.; 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Not separately listed on Wasatch County's own Building Department pages, Forms & Checklists index (wasatchcounty.gov/380), or the Single Family Dwelling checklist — live-checked 2026-07-16; per Utah's Title 15A compliance-agency model (§15A-1-202), unincorporated Wasatch County is bound by this statewide-adopted edition absent its own published amendment.; 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Not separately listed on Wasatch County's own pages — live-checked 2026-07-16; bound by the statewide-adopted edition per §15A-1-202, absent its own published amendment.; 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Not separately listed on Wasatch County's own pages — live-checked 2026-07-16; bound by the statewide-adopted edition per §15A-1-202, absent its own published amendment.; 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is UNCHANGED from the prior code cycle. Not separately listed on Wasatch County's own pages — live-checked 2026-07-16; bound by the statewide-adopted edition per §15A-1-202, absent its own published amendment.; 2024 International Energy Conservation Code (IECC) — one code, no residential/commercial split, per Utah Code §15A-2-103(1)(h). Wasatch County's own checklist references only 'the Utah Energy Conservation Code' without citing an ICC edition number ('If using the Utah Energy Conservation Code, the ResCheck must have a passing score of 5% or better') — live-checked 2026-07-16, still no edition cited; the current statewide edition is stated here rather than the prior 2021 edition previously assumed.; 2024 International Existing Building Code (IEBC) — governs per Utah Code §15A-2-103(1)(i). Not separately listed on Wasatch County's own pages — live-checked 2026-07-16; bound by the statewide-adopted edition per §15A-1-202, absent its own published amendment.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs per Utah Code §15A-2-103(1)(n). Not separately listed on Wasatch County's own pages — live-checked 2026-07-16; bound by the statewide-adopted edition per §15A-1-202, absent its own published amendment.; Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not listed on Wasatch County's own pages — live-checked 2026-07-16.; 2006 Utah Wildland Urban Interface Code, adopted under Utah Code §15A-2-103(2) — referenced directly on the same county checklist for site-plan defensible-space requirements ('defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103').; 2026-07-16 codesAdopted re-verification: Utah Code §15A-2-103 (live-checked at the canonical le.utah.gov URL, current version 'Effective 7/1/2026') now governs statewide construction codes for counties per §15A-1-204, adopting 2024 IBC/IPC/IMC/IFGC/IEBC/IECC and residential 2024 ISPSC, while IRC stays 2021 (App AQ) and NEC stays 2023. Wasatch County's own Single Family Dwelling checklist (live-checked 2026-07-16, re-fetched and confirmed unchanged from the prior review) still names only '2021 International Residential Code' (architectural) and '2021 International Building Code' (structural), with no separate citation for IPC, IMC, IFGC, NEC, IECC edition, IEBC, ISPSC, or MBI Standards — reported verbatim as the county's own published text; the statute is stated as governing above rather than silently assumed.. Local amendments apply — see the Unincorporated Wasatch County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wasatch County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.