Solar PV Permit in Unincorporated Wasatch County, Utah
Required for solar photovoltaic installations in unincorporated Wasatch County. Wasatch County Code § 16.21.42 (Supplementary Development Standards for solar panels) gives solar installations a genuinely distinct zoning treatment depending on mounting type: flush-mounted roof panels are a permitted use in any zone; 'structured' (non-flush, tilted) roof panels are a CONDITIONAL USE in any zone, requiring Planning Commission approval; freestanding (ground-mounted) panels are a permitted use in residential districts only, subject to height, maximum-area, and setback requirements. A building permit is required for installation regardless of mounting type. Wasatch County's own Building Department pages (municipalcodeonline.com hosts the ordinance on a client-side-rendered platform that returns no readable body text to automated fetch tools) do not publish a distinct solar-specific building-permit fee — the general per-square-foot Building Department fee mechanism documented for this jurisdiction's residential-building-permit entry applies. Re-chased 2026-07-20: the county's live Application Fee Schedule (Wasatch County Code 4.09.02 C, effective 7/2025) publishes an exact Conditional Use Permit fee of $700.00 + costs, which is the fee that governs the § 16.21.42 CUP requirement for 'structured' roof-mounted arrays.
Verified 2026-07-20 · Source
When you need this permit
- Flush-mounted roof solar panels: permitted use in any zone, per Wasatch County Code § 16.21.42 — no Conditional Use Permit required for this mounting type
- 'Structured' (non-flush, tilted-rack) roof solar panels: a CONDITIONAL USE in any zone per § 16.21.42, requiring Planning Commission approval before installation
- Freestanding (ground-mounted) solar panels: a permitted use in residential districts only, subject to height, maximum-area, and setback requirements per § 16.21.42
- Building permit required for installation regardless of mounting type, submitted through the county's online Plan Review Portal
- Structural engineering documentation for roof-mounted arrays (roof load capacity) and electrical single-line diagram for grid interconnection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing — not separately published for solar by the county; follows the standard MEP rough-in sequence documented for this jurisdiction's residential-building-permit entry.
- 2
Final
Panel/array mounting and electrical connections verified — not separately published for solar by the county; follows the standard final inspection documented for this jurisdiction's residential-building-permit entry.
See the full Unincorporated Wasatch County inspection guide — scheduling & re-inspection fees →
Tips
- Mounting type matters in Wasatch County: flush-mounted roof panels are a permitted use requiring only a building permit, but 'structured' (tilted, non-flush) roof panels are a Conditional Use requiring Planning Commission approval in addition to the building permit — confirm which category your installation falls into before applying.
- Freestanding (ground-mounted) solar arrays are only a permitted use in residential districts, and must meet height, maximum-area, and setback standards under Wasatch County Code § 16.21.42 — contact the Planning Department, (435) 657-3205, to confirm your parcel's zone and the applicable numeric standards, which could not be independently rendered from the county's client-side ordinance platform.
- No solar-specific building-permit fee table is published; the general ~$1.25/sq ft Building Department fee (still the county's own live-published figure as of a 2026-07-20 re-check, though originally dated June 2016) applies to the building-permit portion of a solar project, and a $700 + costs Conditional Use Permit fee (Wasatch County Code 4.09.02 C, effective 7/2025) applies if your installation is 'structured' (non-flush) roof-mounted and therefore triggers the § 16.21.42 CUP requirement — confirm directly with the Building Department, (435) 657-3200, and the Planning Department, (435) 657-3205.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Wasatch County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Wasatch County
Solar PV Permit in other cities
Compare solar pv permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Wasatch County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Wasatch County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →