Skip to main content
PermitBase

Commercial Tenant Improvement / Tenant Finish Permit in Hurricane, Utah

Required for tenant improvement and tenant finish work in existing commercial buildings in Hurricane. Hurricane does not publish a dedicated tenant-improvement checklist or a separate TI-specific valuation rate distinct from new commercial construction — a search of cityofhurricane.com's Building Department page, Document Center, and the Consolidated Fee Schedule found no tenant-improvement-specific document as of 2026-07-19. The general commercial building-permit fee mechanism (Resolution 2025-39, Table AL101.1 applied to Exhibit B's occupancy-classification valuation) is inferred to apply, but this is not confirmed by an explicit tenant-improvement line item.

Reviewed 2026-07-19 · Source

When you need this permit

  • Commercial remodel or tenant improvement work in an existing commercial structure, regulated by the 2024 IBC and 2024 IEBC (existing building provisions)
  • Application and plan submittal through the City Inspect online portal (hurricane.cityinspect.com)
  • Construction plans and engineering appropriate to the scope of the tenant finish work — no dedicated Hurricane-published TI checklist was located to confirm the exact document list

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based (2021 IRC Table AL101.1), inferred mechanismHurricane City Resolution 2025-39 does not publish a distinct valuation rate for tenant improvement / tenant finish work (unlike, e.g., Murray's published 'Mall Tenant Finish' supplemental rate). This entry assumes the same general fee mechanism used for new commercial construction applies to TI work, based on the resolution's general framing ('building permit fees within Hurricane City'), but this has not been confirmed against an explicit tenant-improvement line item. Confirm the applicable valuation approach directly with the Building Department, (435) 635-2811.
Same tiered schedule as the Commercial Building Permit (Resolution 2025-39, Exhibit A), applied to a declared project valuation

Review timeline

Plan reviewTypical estimate — confirm current times with the Hurricane building department
~21–21 business days

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Hurricane?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Structural (if applicable)

    Wall construction and any structural modifications verified before close-in, where applicable to the scope of work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  3. 3

    Final

    All work complete before occupancy.

See the full Hurricane inspection guide — scheduling & re-inspection fees →

Tips

  • Hurricane does not publish a dedicated tenant-improvement checklist or fee line distinct from new commercial construction — confirm document requirements and the applicable valuation method directly with the Building Department, (435) 635-2811, before submitting.
  • Because the general commercial 'Table AL101.1 fee scale + Exhibit B occupancy valuation' mechanism is the only published fee framework for commercial work of any kind in Hurricane, it is the best available reference point for estimating a TI permit fee, but it is not confirmed as the exact TI method.
  • Hurricane City has no separate, published Change of Use or Change of Occupancy permit with its own fee. The city's own Business License Application (form PDF, DocumentCenter/View/2778) includes an office-use-only checklist with independent 'New Construction: yes/no', 'Remodel: yes/no', 'Building Permit: yes/no', and 'Certificate of Occupancy or Tenant Improvement inspection required: yes/no' fields — meaning a business license for an existing building can still trigger a CO/TI-inspection check even with no active building permit — but this is folded into the standard $75.00 Business License Application ($25.00 application + $50.00 license) rather than billed or processed as its own permit.

Frequently asked questions

Hurricane requires a commercial tenant improvement / tenant finish permit for: Commercial remodel or tenant improvement work in an existing commercial structure, regulated by the 2024 IBC and 2024 IEBC (existing building provisions); Application and plan submittal through the City Inspect online portal (hurricane.cityinspect.com); Construction plans and engineering appropriate to the scope of the tenant finish work — no dedicated Hurricane-published TI checklist was located to confirm the exact document list. If your project isn't listed, confirm with Hurricane City Building Department at (435) 635-2811 before starting work.

Not that is published separately. As of 2026-07-19, no dedicated tenant-improvement checklist, application category, or valuation rate was found on cityofhurricane.com distinct from new commercial construction. Confirm the applicable fee and document requirements directly with the Hurricane City Building Department at (435) 635-2811.

Plan review for a commercial tenant improvement / tenant finish permit in Hurricane typically runs 21–21 business days. This is an estimate, not a published figure — confirm current review times with Hurricane City Building Department at (435) 635-2811.

You'll need: City Inspect Online Application; Construction Plans and Engineering. See the required-documents checklist on this page for details on each.

Hurricane requires 3 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Structural (if applicable), MEP Rough-In, Final. Schedule each through Hurricane City Building Department ((435) 635-2811).

Apply through Hurricane City Building Department at 147 N 870 W, Hurricane, UT 84737. Phone: (435) 635-2811, email: karri@hurricane.utah.gov. Official information: https://www.cityofhurricane.com/161/Building-Department.

Hurricane, Utah has adopted: 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did NOT change this edition in the 7/1/2026 amendment. Matches Hurricane City's official Building Department page (live-checked 2026-07-16), which still displays the older 'EFFECTIVE JULY 1, 2023' banner text but lists the correct, still-current 2021 IRC.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute.; 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a), superseding the 2021 IBC. Hurricane's own Building Department page, live-checked 2026-07-16, still displays the 'EFFECTIVE JULY 1, 2023' banner listing the 2021 IBC — the city's page has NOT been updated to reflect the 7/1/2026 statewide flip. The statute controls regardless of the city page's lag. Note: Resolution 2025-39 Exhibit B already separately used a '2024 IBC Modified' Square Foot Construction Cost table for fee-valuation purposes (see entry below) — that fee-valuation reference now also happens to match the statute-current adopted edition, though it was adopted for valuation purposes only, not as a wholesale code-adoption statement.; 2024 International Plumbing Code (IPC) — statewide per Utah Code § 15A-2-103(1)(d), effective 7/1/2026; not itemized on Hurricane's own Building Department page (live-checked 2026-07-16, which lists only IRC/IBC/NEC), added here per statute since the city's own materials omit it entirely.; 2024 International Mechanical Code (IMC) — statewide per Utah Code § 15A-2-103(1)(e), effective 7/1/2026; not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f), effective 7/1/2026; not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; 2023 National Electrical Code (NEC) — statewide-mandatory edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (the 2023 NEC baseline predates this code cycle). Hurricane's own Building Department page lists '2020 National Electric Code' under its 'EFFECTIVE JULY 1, 2023' banner — one edition behind the statewide-mandatory floor, confirmed still unchanged via live-check 2026-07-16. Per Utah Code § 15A-1-204 (statewide-mandatory construction code), the 2023 NEC governs regardless of the city's own page.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — statewide per Utah Code § 15A-2-103(1)(h), effective 7/1/2026 (no residential/commercial split under current law); not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute. Note: the city's Building Department forms index lists a downloadable 'IRC_IECC Code Compliance (PDF)' form whose specific IECC edition was not independently verified in this pass — not asserted here.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i), effective 7/1/2026; not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n), effective 7/1/2026; not itemized on Hurricane's own Building Department page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Modular Building Institute (MBI) Standards 1200 and 1205 — statewide per Utah Code § 15A-2-103(1)(o); not listed on Hurricane's own Building Department page, added here per statute.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Hurricane's Building Department page (cityofhurricane.com/161/Building-Department) was live-checked 2026-07-16 via real-browser navigation and confirmed still displaying its 'EFFECTIVE JULY 1, 2023' banner listing only 2021 IRC / 2021 IBC / 2020 National Electric Code — it does not itemize IPC, IMC, IFGC, IECC, IEBC, or ISPSC at all, and has not been updated for the 7/1/2026 statewide flip. The statewide statute controls over the city's un-updated page; codes the city omits entirely are added above per statute since they apply statewide regardless of local publication.. Local amendments apply — see the Hurricane overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hurricane building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Hurricane.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.