Solar Panel (PV) Permit — Hurricane, Utah · Requirements sheet
Verified 2026-07-08 · Source: https://www.cityofhurricane.com/DocumentCenter/View/2678
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Panel (PV) Permit in Hurricane, Utah
Required for residential and commercial solar photovoltaic installations in Hurricane. Handled through Hurricane City Power's solar application process (separate review/fee track) in addition to the standard building permit.
Verified 2026-07-08 · Source
When you need this permit
- Solar Application Packet submitted to Hurricane City Power
- Building permit application via City Inspect for the physical installation
- See Hurricane City Power's Solar Policy and Grid-Tied Policy for interconnection and base-rate requirements
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Hurricane City Consolidated Fee Schedule, current as of July 1, 2026 (Power and Water Service Fees section): 'Solar Application Review Fee.......... Show full citationHide
Hurricane City Consolidated Fee Schedule, current as of July 1, 2026 (Power and Water Service Fees section): 'Solar Application Review Fee.......... $200.00.' Confirmed independently in the Electrical Rates and Fee Schedule PDF ('SOLAR FEES AND RATES October 3, 2024 — Application Review Fee (1st Review) $200.00').Review timeline
Inspection process
- 1
Building Inspection (installation)
Standard combined trades inspection for the physical PV installation, scheduled through City Inspect.
See the full Hurricane inspection guide — scheduling & re-inspection fees →
Tips
- Solar has a two-track process in Hurricane: Hurricane City Power's Solar Application (review fee + net meter fee) is separate from, and in addition to, the standard City Inspect building permit for the physical installation.
- Contact the Power Department at (435) 635-5536 for commercial or solar-specific rate questions, per the Consolidated Fee Schedule.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fee schedules
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Hurricane building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Hurricane's permit history is searchable by address
366 permits on record for Hurricane, 1971–2022 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Hurricane
Solar Panel (PV) Permit in other cities
Compare solar panel (pv) permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Hurricane project checklist
Describe your project once and get every permit, document, and fee it triggers in Hurricane — in one checklist. Free, for any city and any number of projects.
Get started →